1 / 29

RPC HV-LV project

Alfonso Boiano 1 , Flavio Loddo 2 , Pierluigi Paolucci 1 , Antonio Ranieri 2. 1) I.N.F.N. of Naples, 2) I.N.F.N. of Bari. RPC HV-LV project. I.N.F.N. Naples. Introduction RPC description Requirements SASY 2000 project Prototype tests. Project description cables and connectors

Anita
Télécharger la présentation

RPC HV-LV project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alfonso Boiano1, Flavio Loddo2, Pierluigi Paolucci1, Antonio Ranieri2 1) I.N.F.N. of Naples, 2) I.N.F.N. of Bari RPC HV-LV project I.N.F.N. Naples • Introduction • RPC description • Requirements • SASY 2000 project • Prototype tests • Project description • cables and connectors • Cost estimation • Schedule • Conclusions Pierluigi Paolucci - I.N.F.N. Naples

  2. Introduction I I.N.F.N. Naples • TheRPC detectors will be equipped with a large part of the HV-LV system placed in a “not accessible area”. • The HV “remote hardware” will be placed in the UXC zone, around the detector, and it will be accessible just in some dedicated period. • The system will work in very hard conditions due to the high magnetic field and high radiation environment. Pierluigi Paolucci - I.N.F.N. Naples

  3. Introduction II I.N.F.N. Naples • A common project (SASY 2000) for the HV-LV RPC systems for LHC is going on between the I.N.F.N. and the CAEN company. • A first prototype has been delivered on June 2002 and is now under tests. • A lot of different tests will be performed on the CMS HV-LV RPC system: • Magnetic field test (CERN) • Radiation test (Louvain la Neuve) • High Stress test (Naples) • Long term test (Naples/Bari) Pierluigi Paolucci - I.N.F.N. Naples

  4. RPC detector description I I.N.F.N. Naples It consists of a Barrel (5 wheels) and two Endcap plates Endcap Barrel Pierluigi Paolucci - I.N.F.N. Naples

  5. RPC detector description II I.N.F.N. Naples Each wheel is divided in 12 sectors DT chamber RB4 RPC - 2 bi-gaps RPC - 2 bi-gaps DT chamber RPC - 2 bi-gaps RPC - 2 bi-gaps RB3 bigap RPC - 3 bi-gaps DT chamber RB2 bigap RPC - 2 bi-gaps bigap RPC - 2 bi-gaps DT chamber RB1 z y RPC - 2 bi-gaps z bigap bigap x Pierluigi Paolucci - I.N.F.N. Naples

  6. RB3/RB4 RB2 reference plane RB1/RB2in Bigap Bigap Bigap Bigap Bigap Bigap Bigap Bigap ALV2 DLV2 ALV1 DLV1 Bigap HV1 HV2 HV1 HV2 ALV1 DLV1 ALV2 DLV2 4 RPC gaps 6 front-end boards HV1 HV2 ALV1,ALV2,ALV3 DLV1,DLV2,DLV3 HV1 HV2 HV3 4 RPC gaps 12 front-end boards 6 RPC gaps 18 front-end boards RPC schema I.N.F.N. Naples Pierluigi Paolucci - I.N.F.N. Naples

  7. FEB FEB FEB FEB FEB FEB FEB FEB FEB FEB FEB FEB RPC HV - LV description I.N.F.N. Naples RB1/RB2in RPC chamber Front-End Bigap FEB FEB FEB FEB Distrib. board Bigap ALV1 DLV1 ALV2 DLV2 ALV Analog Voltage = 7V Working Cur. = 0.42 A DLV Digital Voltage = 7V WorkingCur. = 0.9 A I2C input LV+I2C FEB out LV in Distributes analog and digital LV It supplies LV power to 3 FEB chains It supplies the I2C main line from LB and one backup line from DT. Total power/(ALV+DLV) ch.:1.32 A * 7 V = 9.24 W Expected Power 120 W/sector 7.2 kW/Barrel Pierluigi Paolucci - I.N.F.N. Naples

  8. HV - LV numbers I.N.F.N. Naples The barrel system consists of: Now we will describe the HV-LV project in order to quantify the number of channels we need. Pierluigi Paolucci - I.N.F.N. Naples

  9. HV – LV requirements I.N.F.N. Naples • General: • system working in high magnetic field; • system working in an high radiation environment; • distributed remote system; • floating HV and LV channel (noise reduction). • HV: • 15 KV – 1 mA (resolution of 0.1 mA) • LV: • +7 V – 0.42 A (analog) and +7 V – 0.9 A (digital) Pierluigi Paolucci - I.N.F.N. Naples

  10. SASY2000 project for RPC I I.N.F.N. Naples • The aim of the I.N.F.N. – CAEN project is to find a common solution for the RPC HV-LV systems of the LHC experiments. • The SASY2000 project is based on the following ideas: • Mainframe SY1527 (local system – control room); • 48 Volts Power Source; • Remote distribution system consisting of a custom 6U crate housing: • 2 independent crate controller; • 8 HV-LV boards each with 4 HV + 8 LV floating channels Pierluigi Paolucci - I.N.F.N. Naples

  11. SASY2000 project for RPC II I.N.F.N. Naples Control Room 1 1 From 1 to 16 Branch controller 4 4 Pierluigi Paolucci - I.N.F.N. Naples

  12. SASY2000 project for RPC III I.N.F.N. Naples Detector region Electronic house 4 8 … 16 HV #1 HV #2 Branch controller #1 Complex ch. 1 LV #1 LV #4 256 Remote boards Branch controller #2 HV #1023 HV #1024 Complex ch. 512 … … … 256 LV #2047 LV #2048 Branch controller #16 What do we need ?? 26 ch * 12 sect * 5 wheels = 1560 LV 17 ch * 12 sect * 5 wheels = 1020 HV One mainframe is enough for the barrel The remote board has 2 Complex ch. each equipped with: 2 HV ch and 4 LV ch. Pierluigi Paolucci - I.N.F.N. Naples

  13. RPC HV-LV prototype 0 I.N.F.N. Naples • The HV-LV CAEN functional prototype consists of: 1 HV board, 3 LV board and 1 controller. • The prototype has been split in three pieces, following a “logical separation” of the system, in order to study the functionality of every single piece and component. The final HV-LV board will have 2 complex channel each with 2 HV + 4 LV floating channels . It will be 6U high and 2 slots width. After the tests the factory will begin to design the final board integrating all these components in a single 6U – 2 slots boards. Pierluigi Paolucci - I.N.F.N. Naples

  14. Test to be performed I.N.F.N. Naples • The following tests will be performed on both the prototypes and the final board: • Magnetic field test up to 7 KGauss (at CERN); • Radiation testup to 10 LHC eq-years (at Louvain La Neuve); • Test on the RPC detector to study the noise condition(at the test station in Bari); • High Stress Testto study the system under very hard conditions (in Napoli). Pierluigi Paolucci - I.N.F.N. Naples

  15. Magnetic field test I.N.F.N. Naples Pierluigi Paolucci - I.N.F.N. Naples

  16. Neutron radiation test I I.N.F.N. Naples The SASY2000 HV-LV prototype has been tested for the first time at the Louvain La Neuve radiation facility in May the 21th. The total neutron fluency requested was2-3 • 1012n/cm2 for 10 LHC years, corresponding to about 80 min with a beam at 1 mA. The people involved were: Boiano (NA), Loddo (BA), Paolucci (NA), Passuello (CAEN) and Ranieri (BA) SASY2000 Pierluigi Paolucci - I.N.F.N. Naples

  17. Neutron radiation test II I.N.F.N. Naples • The setup consisted of: • CMS SASY2000 prototype placed at 110 cm from the beam; • SY2527 mainframe placed 30 m far from the SASY2000; • Laptop to monitor the system. The system worked well for 30 min. corresponding to about8 • 1012n/cm2. Then it lost the communication with the SASY2000 showing some problems on the HV channels. We took data for all the 80 min in order to analyze every single components after the test. Pierluigi Paolucci - I.N.F.N. Naples

  18. High Stress Test in Naples I.N.F.N. Naples • The High Stress Test is based on a test station designed and built in Naples. • The test station consists of a Pierluigi Paolucci - I.N.F.N. Naples

  19. High Stress Test in Naples I.N.F.N. Naples • The High Stress Test is based on a large number of cycles of the following tests: • Low current(1 mA) test at “working” voltage (10 KV); • Medium range current scan (from 10 to 300 mA) at “working” voltage: • High current (1 mA) test at “working” voltage (10 KV); • Over-current and Trip test (I > 1 mA); • Maximum voltage test (12 KV) at different absorbed currents; • Discharge and short circuit test made with two pins at different distances; • Imon, Vmon calibration test made with an independent volt-meter. Different HV resistors A PC running LabVIEW will be used to control the system and to analyze the data. Final HV-LV cable/connector will be used. Pierluigi Paolucci - I.N.F.N. Naples

  20. RPC HV-LV final prototype I.N.F.N. Naples • The full set of tests of the prototype 0 will finish before the end of the 2002; • If and only if the test results will be very encouraging, showing a very good performances of the HV-LV system the RPC collaboration will order a final prototype; • It consists of a 6U – 2 slots board equipped with 4 HV and 8 LV floating channels. • The final prototype will be produced in about 1 year and it will be tested following the same procedure. • Only after this second step will be possible to start the final production consisting of about 260 remote boards and 2 SY1527 mainframes. Pierluigi Paolucci - I.N.F.N. Naples

  21. 2 bi-gaps 2 bi-gaps 2 bi-gaps LVA channel LVD channel HV channel RB = remote board HV-LV architecture for a barrel sector I.N.F.N. Naples 26 LV channels 4 Remote Boards 17 HV channels RB4 2 bi-gaps 2 bi-gaps 4 LV 4 HV ch 2 RB 1 RB 4 HV ch RB3 2 bi-gaps 2 bi-gaps 4 LV 3 bi-gaps 6 LV ch 3 HV ch RB2 1 RB 1 RB 4 LV ch 2 HV ch 4 LV ch 2 HV ch RB1 1 RB 1 RB 4 LV ch 2 HV ch 2 bigaps = 96 strips = 6 febs 26 ch * 12 sect * 5 wheels = 1560 LV 17 ch * 12 sect * 5 wheels = 1020 HV 4 remote boards * 12 sect * 5 wheels = 240 RB Pierluigi Paolucci - I.N.F.N. Naples

  22. HV – LV numbers I.N.F.N. Naples The barrel system consists of: having been chosen: 2 gaps per HV channel and 6 FEBs per LV channel Pierluigi Paolucci - I.N.F.N. Naples

  23. 1 2 3 4 LV-HV LV-HV 5 6 7 8 LV-HV LV-HV Barrel cables routing I.N.F.N. Naples 26 LV ch/cable + 17 HV ch/cableper sector LV-HV LV-HV Sector -4 Sector -5 LV-HV Muon racks 2 RPC HV-LV crates Sector –6 LV HV 26 LV ch/cable 17 HV 26 LV Elect. house 17 HV 26 LV 17 HV ch/cable 48 remote boards/wheel 240 Remote Board 1 crates/rack  8 crates/wheel  40 crates LV 26 ch * 12 sect * 5 wheels = 1560 LV 17 ch * 12 sect * 5 wheels = 1020 HV HV

  24. HV cable I.N.F.N. Naples The HV cable has been chosen and approved • Suitable to sustain up to 15 kV • Cable characteristics: • According CERN safety instruction IS 23 • Single conductor- = 0.16 mm • Conductor resistance @ 20°C = 147 /Km • Core- = 3 mm • Screen wire-=0.2 mm (for 10 conductors) • Overall diameter = 8.4 mm (for 3 conductors) • Price: 1.050 €/Km (for 10 Km and 3 conductors cable) Pierluigi Paolucci - I.N.F.N. Naples

  25. HV connectors I I.N.F.N. Naples The HV connector has been chosen and approved Possibility to stack it up • Electrical characteristics: • Operating voltage: 15 kV • Testing conditions: 20 kV • 2 high voltage pins to supply –12 kV • 1 pin for signal return • insulating material • Polietilene HDPE (Eraclene Polimeri Europa (57%) • Masterbatch (GPO1246 Viba) (43%) (Conforming to TIS Rules) • Metal cover connected to external chamber aluminum frame • ZAMA (UNI 3717 G-Zn A14 Cu1) Pierluigi Paolucci - I.N.F.N. Naples

  26. HV connectors II I.N.F.N. Naples By CPE (www.cpeitalia.com) Price: 3 CHF/contact/10.000 pieces • Schedule: • The connector has passed CERN tests for chemical analysis • Made electrical test performance (before and after radiation exposure) • We are waiting for the final quotation before final order Pierluigi Paolucci - I.N.F.N. Naples

  27. Cost estimation I.N.F.N. Naples • The Pierluigi Paolucci - I.N.F.N. Naples

  28. Schedule I.N.F.N. Naples • The Pierluigi Paolucci - I.N.F.N. Naples

  29. Summary I.N.F.N. Naples • The SASY2000 project, developed by the CAEN-INFN for the LHC experiment will be intensively test in high magnetic field at CERN, high radiation flux at Louvain and for long term in Naples. • The total number of HV ch. is:1020 • The total number of LV ch. is:1560 • The total number of HV-LV remote board is:240 • The HV-LV crate will be designed and built in Naples • The prototype will be under test until Sept 2002 • Magnetic Field test: MAY 2002 (results are under study) • High Radiation test: MAY 2002 – JULY 2002 • High Stress test: SEPT-OCT 2002 • An alternative project for the LV system is under study. • The HV-LV project will be discussed at INFN in Sept 2002. Pierluigi Paolucci - I.N.F.N. Naples

More Related