Download
chapter 10 techniques for making better engineering management decisions n.
Skip this Video
Loading SlideShow in 5 Seconds..
Chapter#10 Techniques for making better engineering management decisions PowerPoint Presentation
Download Presentation
Chapter#10 Techniques for making better engineering management decisions

Chapter#10 Techniques for making better engineering management decisions

629 Vues Download Presentation
Télécharger la présentation

Chapter#10 Techniques for making better engineering management decisions

- - - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

  1. COURSE INSTRUCTOR : PROF. DR. SHAHAB KHUSHNOOD Chapter#10Techniques for making better engineering management decisions Lecture No. 08 Course: Engineering Management MED DEPARTMENT, U.E.T TAXILA

  2. INTRODUCTION • During middle of 1940s, a significant growth of quantitative management techniques occurred. • The increase in the use of computers and the modern problem complexities have enhanced the importance of many of these techniques. For Example: • Linear Programming. • Non-Linear Programming.

  3. Today, the mostly management techniques which are in practice: • Linear Programming • Decision Trees • Exponential Smoothing • Discounted Cash Flow Analysis

  4. Optimization Techniques There are two widely known optimization techniques known as: • Lagrangian Multiplier Technique (Technique of undetermined Multipliers) • Linear Programming Technique (Advanced form of simplex method technique)

  5. 1-LAGRANGIAN MULTIPLIER TECHNIQUE • This technique is demonstrated for a two variable function. • However on similar lines it can be extended fornvariables. • Assume that we have defined function f(y1,y2) Subject to the constraint function k(y1,y2)=0

  6. 1-LAGRANGIAN MULTIPLIER TECHNIQUE • With the aid of these two functions the Lagrangian function , L(y1,y2,λ) formulated as follows:

  7. 1-LAGRANGIAN MULTIPLIER TECHNIQUE • Subject to the following necessary conditions for estimating a relative maximum or minimum value: • Expressions for y1,y2 and λ can be obtained by solving the simultaneous equations.

  8. EXAMPLE-1

  9. Solution: The Lagrange function is formulated as follows Taking the partial derivative with respect to y1,y2 and λresults in

  10. 2y1+2λ = 0 2y2- λ=0 2y1-y2=0 So Y1=8/5 Y2=-8/10 λ =-8/5 Thus the critical point of f, subjected to specified condition, is (8/5,-8/10) .

  11. 2-LINEAR PROGRAMMING • In real life situations the objective and constraint functions will be rather complex. • However the simplest form of linear programming problem formulation may be expressed as follows

  12. This can be subject to

  13. Where

  14. Example 2 For above equations following values for symbols are defined Write down the resulting equations by assuming that the objective function is to be maximized.

  15. Example 2 (cont.…)

  16. EXAMPLE-3

  17. Solution:

  18. (1) (2) (3) (4) (5) (6)

  19. Plot Equation (1) to (6) as:

  20. From Plot of equations 1-6: • Company profit is optimum at point F. (F point satisfies all the constraints) • F point shows maximum profit. The optimum values of Z1 and Z2 at point F are 6.5 and 2. substitute these values in equation.1.

  21. Discounted Cash Flow Analysis • In various engineering investment decisions, the time value of money plays an important role. • Therefore it is necessary for the engineers to have some knowledge of engineering economics.

  22. Discounted cash flow analysis The basics of engineering economics are • Simple Interest • This is the interest which is calculated on the original sum of money, called the original principal, for the period in which the lent or borrowed sum is being utilized. • The simple interest,St,is given by: (1) Where M is the principal amount lent or borrowed i is the interest rate per period ( this is normally a year) k is the interest periods (these are usually years)

  23. Simple Interest (Cont.…) The total amount of money, Mt, after the specified lent or borrowed period is given by (2)

  24. Example: 4

  25. Solution: (1) (2)

  26. 2. Compound Interest • In this case at the end of each equal specified period, the earned interest is added to the original principal or amount lent or borrowed at the beginning of that period • Thus, this new principal, or amount, acts as a principal for the next period and the process continues.

  27. To calculate compound amount, Mck, the resulting formula is developed as follows:

  28. Example:5

  29. Solution:

  30. 3.Present Worth • The present worth of a single payment is given by: • In simple terms, this formula is used to obtained the present worth, M, of money,Mck, after k periods, discounted at the periodic interest rate of i. • Sometime above equation can be written as

  31. Example # 6

  32. Solution:

  33. Formula For Uniform Periodic Payments • For using formula it is assumed that at the end of each of the K period or years, the depositor adds D amount of money. The money is invested at the interest rate i, compounded annually or periodically. • Thus the total amount of money (1) where

  34. It should be noted in this equation that the D amount of money is first time deposited at the end of first year or period.

  35. Example # 07

  36. Solution:

  37. By substituting k=3, D=2000 and i= 0.15 in equation (1): From above equation the total amount of money after three year period is:

  38. Example # 8 Given Data: (From Example 7)

  39. Solution: Substitute the data in given equation:

  40. PRESENT VALUE OF UNIFORM PERIODIC PAYMENTS • In present value of uniform periodic payment we wish to find the present value of uniform periodic payments after K periods or years instead of total amount. • Thus the present worth, PW, of uniform periodic payments is given by • Multiply both side with (1+i)-1,The resulting present worth formula

  41. Example # 9

  42. Solution: In this example following values are given: Substitute these values in equation:

  43. Example 9 Cont. • Thus decision to purchase the machine will be profitable investment.

  44. Depreciation Techniques • The term “Depreciation” means a decline in value. • In order to take into consideration the change in the value of the product, the depreciation charges are made during the useful life of the engineering products. • The three depreciation techniques are: 1-Declining-Balance Depreciation Method 2-Straight-line Depreciation Method 3-Sum Of Digits Depreciation Method

  45. Depreciation Techniques (Cont..) 1. Declining-Balance Depreciation Method • This method dictates the accelerated write-off of the product worth in its early productive years and corresponding lower write-off near the end of useful life years. • The depreciation rate αd is given by where

  46. The declining balance techniques requires a positive value of s. The product book value, Vbv(M), at the end of year M is given by:

  47. The annual depreciation charge, DC(M), at the end of year M is given by

  48. Example # 10

  49. Solution: From example statement Substitute in equation