EU projects, IT department Collaboration with FI-CTR
60 likes | 189 Vues
This document outlines the financial follow-up framework for CERN's EU projects, particularly regarding the EGEE-II and EGEE-III budgets. It identifies key personnel involved, including Anna Cook, Dita Mocova, and Roberta Faggian-Marque, and details the support required for various projects involving CERN. Additionally, it provides a step-by-step guide aimed at new project proposers, highlighting crucial tasks, budget codes, and contacts. Regular visits and communication protocols are emphasized to ensure effective project administration and grant management.
EU projects, IT department Collaboration with FI-CTR
E N D
Presentation Transcript
EU projects, IT departmentCollaboration with FI-CTR Anna Cook, Dita Mocova, Roberta Faggian-Marque CERN 6th December 2006
IT EU projects financial follow-up: Current set-up • EGEE-II budget coordination and EGEE-III budget preparation • Dita Mocova • EGEE-Related EU projects (with CERN partnership): • Roberta Faggian Marque • 9 projects in which CERN participates • All require financial follow-up • Support required on CERN’s requirements (Budget, CET, APT, etc.) • ETICS and ISSeg (Coordinated by CERN): • Karin Burghauser • ISSeG: complex project (sub-contracting involved) • Unclear financial follow-up: Karin needs support EGEE, Related Projects, FI-CTR meeting, 6th December 2006
Tasks discussed at 14/09 meeting • STEP BY STEP GUIDE • The design of a step by step guide for new projects at CERN (FP7) • Taking would-be proposers through the various tasks to be completed CERN-side • Budget codes set-up, • APT, • Main contacts for each step. • This could be web-based • Will complement the ongoing discussions with CERN-EU office on a harmonious and coherent "entry" point for all EU matters. EGEE, Related Projects, FI-CTR meeting, 6th December 2006
Tasks discussed at 14/09 meeting • MONTHLY PERSONNEL/BUDGET CODE STATUS • Provision of a monthly personnel to budget code table for all projects, as well as financial status. (Templates to be agreed) • Ensures both the project administrator and FI-CTR are aware of project status EGEE, Related Projects, FI-CTR meeting, 6th December 2006
Tasks discussed at 14/09 meeting • COST CLAIM VERIFICATION • Check the cost claims of projects (cost claims will be prepared by Dita Mocova and passed on to FI-CTR). EGEE, Related Projects, FI-CTR meeting, 6th December 2006
Tasks discussed at 14/09 meeting • REGULAR VISITS TO IT PROJECT ADMINISTRATORS (Roberta and Karin) • KEY CONTACT PERSON FOR ANY OPEN FINANCIAL ISSUE (Procedures, implementation of changes, etc.) EGEE, Related Projects, FI-CTR meeting, 6th December 2006