Catholic University of America A Prototype Attitude Determination System for High Altitude Research Balloons Erin Doody, Fernando Esteves, Devon Gonteski, Michael Lamos, Jason Quisberth, Peter Schramm, Raissa Silva, Gary Uritskiy, Patricia Yoritomo
Table of Contents • Mission Overview • Components • Theory and Concepts • Expected Results • System Overview • Block Diagrams • Mass Budget • Subsystem Design • Star Camera • Flight Computer • Pressure Vessel • Electrical Box • Gyros • Prototyping Plan • Assembly and Testing • Management Plan • Schedule • Budget • Task Distribution • Contact Matrix
Mission Overview Overall goal: Design, fabricate, test, and launch a system that collects data • 20kg payload • Measure altitude to arc-second precision • Use of commercially available and low-cost components • Meets Columbia Scientific Balloon Facility (CSBF) requirements • Meets Undergraduate Student Instrument Project (USIP)
Main Components • Daytime-Capable Star Camera • Gyroscopes • Tilt Sensors • Flight Computer • Magnetometer • Clinometer • Thermometer • Pressure Vessel • Box
Theory & Concepts • Electrical engineering, Mechanical engineering, and applied physics ideas and concepts will be used to order to construct, build, test, and fly payload • heat transfer • signal processing and filtering • thermodynamics • Knowledge of computer programming languages such as python will be used in order to operate the electronic components. • Similar projects are seen on the HASP carrier by NASA BPO and LaSPACE • Successful flights and good data are signs that this project is feasible within the timeline given
Expected Results To develop a low-cost, low-mass system for real-time attitude determination • Using of individual sensors including a daytime-capable digital star camera, MEMS gryoscopes, magnetometers, and tilt sensors (clinometers). • The fast, relative sensors (gyroscopes) that are continuously updated by the slower, absolute sensors (star camera, magnetometers). The integration of the gyro output will demonstrate real-time attitude determination to arc-second or better precision.
System Level Block Diagram AAS – Absolute Attitude Sensing CCM – Climate Control and Monitor MP – Mounting Plate PV – Pressure Vessel RAS – Relative Attitude Sensing SP – Signal Processing UB – Unpressurized Box VRB – Voltage Regulator Board *
Star Camera Lens Section • This system is design with the intent to to capture images of stars in both the day and night during flight • One of the requirements for the lens is that it must capture a minimum of 4 stars in the pipeline. • By choosing a lens with a greater area we see an increase in performance by a factor of 1.36. • Another advantage of the smaller f-stop lens is the size of the filter, 72mm vs. 58mm. The larger diameter lens provides a larger area and gives us a larger area of usable frame. • Even though the f/1.2 lens is heavier (545g vs. 290g) the HASP payload bay that we have acquired is 20Kg, well within our current estimate of 3.54Kg. *
Lens: Trade Studies Product Chosen: EF 50mm f/1.2L USM Standard & Medium Telephoto • Focal Length & Maximum Aperture -50mm f/1.2 • Lens Construction -8 elements in 6 groups • Diagonal Angle of View -46° (with full-frame cameras) • Focus Adjustment AF with full-time manual • Closest Focusing Distance -1.48 ft. / 0.45m • Filter Size -72mm • Max. Diameter x Length, Weight- 3.4 in. x 2.6 in./85.4mm x 65.5mm,19.2 oz./545g (lens only) *
Camera Body Design Section • The camera body will be connected to the computer through the means of a USB 2.0 cable. • The software that will facilitate the communication between the flight computer is called gphoto2 and it will give use the ability to cycle shutter speed in flight • The photos that will be take will be sent to the external hardrive. • The reason for choosing the Canon 7D was that it is one of the only camera that is compatible with the gphoto2 software. • This limited the cameras that we could research thus almost forcing us to choose the 7D. *
Camera Body: Trade Study Product Chosen: *
AAS: Risk Matrix AAS.RSK.1: Mission objectives aren't met if the Star Camera overheats. AAS.RSK.2: Mission objectives are affected if the Star Camera parameters had not been set right. AAS.RSK.3: Mission objectives aren't met if the Camera fails to communicate with the flight computer. AAS.RSK.4: Mission objectives are affected if the camera lens becomes obstructed *
Flight Computer Design Section • The flight computer will be responsible for the data acquisition and signal processing. It should have a good processing potential, enough I/O ports to connect all devices, compact size and be robust to different environments. • The first option we consider for the flight computer was a ASUS laptop. It had all the processing potential we need and I/O ports. However, it had some disadvantages such as high price, big size, power consuming and produces too much heat. • Single board computers are a very compact and cheap option that have also a great processing potential. The BeagleBoard-xM (the flight computer selected) have all the capacities we need for a very good price. It has 512 MB DDR memory, 1 GHz ARM Cortex-A8 processor, provides 4 USB ports and runs differents versions of linux. *
Flight Computer: Trade Studies • Show rationale for you choices in components. You basically weigh your options against your requirements and what each component can offer. Don’t forget things like: availability, cost, and prior knowledge. I recommend an online search for examples if you are unsure, or contact me. *
Subsystem Design Section • This section is where you explain how each subsystem was designed • Start with your organization chart with each of your subsystems labeled • Discuss how you researched components that would meet your requirements • Show trade studies if necessary, and if you show them, be prepared to explain the scoring and categories • The most important part is explaining how you reached your major design decisions in each subsystem • After explaining components, discuss any risks associated with this subsystem *
SP: Risk Matrix SP.RSK.1: Mission objectives aren't met if the computer or the PSyncADC board overheats. SP.RSK.2: Mission objectives aren't met if the flight computer fails in communicating to the PSyncADC. SP.RSK.3: Mission objectives aren't met if the flight computer fails in processing sensor data. SP.RSK.4: Mission objectives will be affected if bad sensor data is not filtered. SP.RSK.5: Mission objectives will be affected if the hard drive gets damaged on landing. *
Subsystem Overview – Block Diagram Pressure Vessel and Electrical Box • The pressure vessel will connect to the electrical box that will connect to the large payload (carrier) Pressure Vessel Electrical Box Carrier *
Pressure Vessel Pressure Vessel • Top view • Side view Star Camera Flight Computer Hard drive *
Electrical Box Electrical Box • Top View • Side View Gyro Board P-Sync *
EPS: Trade Studies • Show rationale for you choices in components. You basically weigh your options against your requirements and what each component can offer. Don’t forget things like: availability, cost, and prior knowledge. I recommend an online search for examples if you are unsure, or contact me. • You should have completed a trade study for each block, but you only need to present the 2-3 most important. • Numbers are relatively subjective, but 10 should represent a perfect fit, 5 will work, but is not desirable, and 0 does NOT meet expectations. • The component with the highest average should drive your choice for design. *
PV: Risk Matrix PV.RSK.1: Mission objectives aren't met if the pressure vessel leaks. PV.RSK.2: Mission objectives aren't met if pressure vessel opens entirely/explode. PV.RSK.3: Mission objectives are affected if the pressure vessel could not provide the right pressure. PV.RSK.4: Mission objectives are affected if the pressure vessel detached from other components PV.RSK.5: Mission objectives are affected if the pressure vessel gets dented after landing. *
CCM: Risk Matrix CCM.RSK.1: Mission objectives are affected if heaters could not provide enough energy. CCM.RSK.2: Mission objectives are affected if thermometers fails to measure data correctly. CCM.RSK.3: Mission objectives are affected if heaters fails provide excessive energy; *
VRB: Risk Matrix VRB.RSK.1: Mission objectives aren't met if power supply cannot give enough power for the whole system. VRB.RSK.2: Mission objectives are affected if voltage regulation board fails in provide the correct voltage. VRB.RSK.3: Mission objectives aren't met if power supplies excessive amounts of current. *
UB: Risk Matrix PV.RSK.1: Mission objectives are affected if the unpressured box opens. PV.RSK.2: Mission objectives are affected if the unpressured box gets damage. *
Gyro Overview – Block Diagram • Show your subsystems, now with more detail inside the boxes, and the connections between them *
Subsystem Design Section • This section is where you explain how each subsystem was designed • Start with your organization chart with each of your subsystems labeled • Discuss how you researched components that would meet your requirements • Show trade studies if necessary, and if you show them, be prepared to explain the scoring and categories • The most important part is explaining how you reached your major design decisions in each subsystem • After explaining components, discuss any risks associated with this subsystem *
Gyro: Trade Studies • Show rationale for you choices in components. You basically weigh your options against your requirements and what each component can offer. Don’t forget things like: availability, cost, and prior knowledge. I recommend an online search for examples if you are unsure, or contact me. *
RAS: Risk Matrix RAS.RSK.1: Mission objectives are affected if a gyro fails or sends corrupted data to signal processing. RAS.RSK.2: Mission objectives are affected if the Magnetometer fails or sends corrupted data to signal processing. AAS.RSK.3: Mission objectives are affected if the Clinometer fails or sends corrupted data to signal processing. *
Payload Prototype Assembly • Construct metal box of identical dimensions to actual payload in order to test different part positioning • Things to consider: • Positioning of all the parts relative to each other • Vacuum chamber integrity • Insulation positioning
Sensor Testing • Once all the parts are hooked up together and functioning, the multiple sensors present on the payload must be tested • Things to consider • Sensor calibration • Sensor positioning within the payload • Reliability and accuracy of each sensor
Gyroscope Testing • After the completion of gyro fabrication, test all gyros for proper functioning separately, then together as a system to guarantee that each board operates both by itself and in a system • The accuracy and precision of the final gyroscope unit will be measured in a variety of tests
Temperature Regulation Requirements • The payload electronic parts must remain in a certain temperature range to ensure proper function • Temperature of the electric board(s) must be above 5°C but below 60°C • To ensure this is met, the prototype of the payload must be put under extensive testing in extreme temperature conditions
Important Factors to consider • Insulation – a insulating layer must be present to slow down heat dissipation from and into the vessel • Ventilation – there must be circulation in the payload to ensure that the hottest parts do not overheat too quickly • Thermostat heating – we plan on having an on-board thermostat with a heating element to heat up the system if the air inside goes too low
Testing the Prototype • There are two conditions under which the system must be able to function • Room temperature: the heat dissipation from the prototype vessel must be great enough so that it does not overheat, which means the excessive insulation must be avoided • Upper stratosphere temperature (-5°C): the thermostat must be able to heat the system in the case in which the heat from the functioning parts is insufficient to maintain functional temperature
Final testing • Once the payload prototype is fully assembled and all its parts are functional, it is important to leave the entire system running for several days at a time to identify any weak links in the physical and software design • Running for long testing periods will reveal elusive coding bugs, design flaws, and system glitches that could potentially occur in flight
Work Breakdown Structure Pressure Vessel: • Trade studies • Designs and brainstorming • Sketch SolidWorks drawings • Electronic simulation and testing in SolidWorks • Purchase materials • Preliminary fabrication process • Thermal testing and insulation design • Test preliminary fabrication design • Final compiling with electrical components Unpressurized Box • Trade studies • Designs and brainstorming • Sketch SolidWorks drawings • Electronic simulation and testing in SolidWorks • Purchase materials • Preliminary fabrication process • Thermal testing and insulation design • Test preliminary fabrication design • Final compiling with electrical components