Project aims to replace aged infrastructure, cater to current and future water demand, and enhance system reliability across various roads in Winchester, Kentucky. It includes improvements to raw water intake, pump station, and transmission lines. Impacting over 14,000 customers, the project also involves road closures, noise, and dust with necessary easements acquired. For inquiries, contact Winchester Municipal Utilities.

akamu
Télécharger la présentation

Water System Infrastructure Upgrade Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Raw and Finished Water System ImprovementsApril 22, 2014

  2. Project Purpose…. • Replace aged infrastructure • Provide for current water demand • Provide for future water demand • Improve system reliability

  3. Project Area…. - Ford Road - McClure Road - New Boonesboro Road - Colby Road - Old Boonesboro Road - April Way - Water Works Road - Bypass Road

  4. Area Impact…. • 11,761 WMU • 2,365 East Clark County Water District • 215 Kentucky American Water Company 14,341 Total Customers

  5. Scope of Work…. • 12,000’ of 24” Ductile Iron Raw Water Line • 36,000’ of 24” Ductile Iron Finished Water Line • KY Raw Water Intake and Pump Station Improvements • In total 9 miles of large diameter raw and finished water transmission lines

  6. Project Cost…. *Does Not Include WMU Staff Time

  7. Project Disruptions…. • Road Closures / Detours • Noise • Dust

  8. Easements…. • Temporary and Permanent Easements Required New easement – Not in flood plain – $4.00/ft. New easement – In the flood plain – $3.00/ft. Existing easement (Increase width) – $2.00/ft. Temporary (all) – $1.00/ft. *Any variance from this payment schedule will require authorization from the WMU Commission.

  9. Project Schedule….

  10. Key Contacts…. Winchester Municipal Utilities 150 North Main Street PO Box 4177 Winchester, KY 40392-4177 Phone: (859) 744 – 5434 Fax: (859) 745 – 4146