1 / 10

Progress With Commissioning Plan

Progress With Commissioning Plan . ABT/BTP. Transfer Lines Commissioning. TCDI setup at 4.5 sigma around reference orbit: Ok Dispersion mismatch measurements: Ok

aleron
Télécharger la présentation

Progress With Commissioning Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress With Commissioning Plan ABT/BTP

  2. Transfer Lines Commissioning • TCDI setup at 4.5 sigma around reference orbit: Ok • Dispersion mismatch measurements: Ok • Aperture measurements: Ok for amplitudes of 2-3 sigma (coupling studies), to be done for 4.5 sigma amplitude (machine protection validation).

  3. Commissioning Tests @ Injection • Adjust collimator for injection protection: TDI, TCLI to 6.8 sigma (around golden orbit)  Ok & interlocked (rechecked with high intensity 1.1×1011 p+) • MKI beam synchronization: Ok • MKI.P8 waveform with adjustment of kick delay (TDI at +/- 10 mm): Ok, must be done for P2 (not critical). • Loss maps during overinjection on PROBE (PROBE  INDIV: 1.1×1011 p+) Ok (BLM thresholds had to be reviewed). • Loss maps during injection of nominal bunches: Ok • MKI limits in IPOC: to be adjusted

  4. LBDS and Abort Gap Commissioning • Setup of TCDQ and TCSG@IP6 collimators around the golden orbit new injection settings defined with high intensity (1.1×1011 p+): TCDQ.B1 @ 19.4mm, TCSG.B1 @ 16.8/-15.5mm TCDQ.B2 @ 16.3mm, TCSG.B2 @ 13.4/-14.0mm (Old TCDQ.B1 @ 13.053mm, TCSG.B1 @ 8.23/-6.75mm TCDQ.B2 @ 15.16mm, TCSG.B2 @ 6.39/-7.69 mm). To be checked • Change logic of collimator application and sequencer when requesting to set TCDQ to present position: to be done • Beam size measurement at the TCDQ at 3.5 TeV: to be done • Check TCDQ HW energy interlock (functions): Ok • Insert settings in LSA: to be done when all fixed in terms of betas and settings • IP6 aperture measurements for circulating and extracted beam: Ok

  5. LBDS and Abort Gap Commissioning • Complete analysis and cross-checks of losses at the TCTs during asynchronous beam dump: to be completed • Calibration of BLMs at TCTs in point 5: to be done. • Calibration of BLM at the TCDQ: Ok 1Gy ~ 9.2×1010 p+  5.7×1011 p+ • LBDS system off with circulating beam: Ok, small losses on TCDS/TCDQ but both beams dumped correctly, no BETS error • RF frequency interlock: Ok • BPM interlock  understand the remaining 20 mm offset at 450GeV: to be done • Losses at TCDS (3.5 TeV): to be understood

  6. LBDS and Abort Gap Commissioning • Abort gap cleaning: to be done • Abort gap keeper fine adjustment: to be done (not critical) • 1 MKD kicker knob rechecked for B1 and B2: Ok, both beams extracted correctly for (validation old measurements).

  7. LBDS and Abort Gap Commissioning • Synchronization tests of TCDQ positions and interlocks with other collimators during ramp: Ok with and without beam. Without beam TCDQ position and limits With beam Intensity Energy TCDQ SIS interlock active during the ramp! Step before squeeze TCDQ position

  8. LBDS from 11/05/2010 meeting

  9. LBDS from 11/05/2010 meeting

  10. LBDS from 11/05/2010 meeting

More Related