1 / 2

Prepared by the

ARMY - AMC/PEO VE SAVINGS ACTUAL vs. GOAL AS OF 30 JUNE 2010. VE TRAINING. U.S. Army Materiel Command/ Program Executive Office Value Engineering Fiscal Year 2010 3 rd Quarter Report. Date Course Location FY11 1Q CAVE VECP Training at Las Vegas, NV

amy
Télécharger la présentation

Prepared by the

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARMY - AMC/PEO VE SAVINGS ACTUAL vs. GOAL AS OF 30 JUNE 2010 VE TRAINING U.S. Army Materiel Command/ Program Executive Office Value Engineering Fiscal Year 2010 3rd Quarter Report DateCourseLocation FY11 1Q CAVE VECP Training at Las Vegas, NV DMSMS Conf. TBD ILSC Maint. VE Review TBD TBD PEO GCS HBCT New Hire TACOM LCMC Awareness Quarterly Review TBD New Employee/Intern Co-Op VE/OSCR Orientation TACOM LCMC TBD ARDEC Training Picatinny Arsenal, NJ Goal: $503.052M Achieved: $150.266M CAVE - Contractual Aspects of Value Engineering (CON 236) is now available on the DAU website at: http:/ /www.dau.mil/schedules/schedule/asp UPCOMING VE WORKSHOPS DateItemLocation FY10 4Q Corrosion M270/HIMARS TBD FY11 1Q ATC TTCS Redstone Arsenal, AL FY11 2Q Blackhawk Duckbill; Stratford, CT Sikorsky FY11 3Q MOD 1 Workshop Redstone Arsenal, AL TBD NLOS w/Raytheon TBD TBD Soldier Focused Logistics VE TBD TBD VE Workshop Pine Bluff Arsenal, AR POINTS OF CONTACT DA: Chris Neubert DSN 656-9239 or (703) 806-9239; Christopher.neubert@us.army.mil AMC: Matt Schade DSN 793-7787 or (309) 782-7787; Matthew.schade@us.army.mil AMCOM LCMC: Tom Reynolds DSN 746-8163 or (256) 876-8163; Tom.Reynolds@us.army.mil CECOM LCMC: Gary Jackson DSN 987-6461or (732) 427-6461; Gary.Jackson@us.army.mil JM&L LCMC: Robert Combs DSN 793-7770 or (309) 782-7770; robert.n.combs@us.army.mil PEO-STRI: Robert Forbis DSN 970-3884 or (407) 384-3884; robert.forbis@us.army.mil TACOM LCMC: Bernice Conn DSN 786-9773 or (586) 282-9773 bernice.conn@us.army.mil “Supporting Army Strong” VE CONTINUOUS LEARNING COURSE Value Engineering The Defense Acquisition University’s (DAU’s) continuous learning course on VE (CLE001) is available at: http://clc.dau.mil • Lesson 1: Introduction to VE • Lesson 2: VE Application Areas • Lesson 3: Implementation through VE Workshops • Lesson 4: Understanding the VE methodology • Lesson 5: Using VECPs • Lesson 6: Summary • To obtain continuous learning credit for taking the module, register and log-in if you have not previously done so. Prepared by the U.S. Army Research, Development and Engineering Command for the Deputy Chief of Staff for Business Transformation HQ, U.S. Army Materiel Command http://www.ve.ria.army.mil/

  2. THIRD QUARTER FINDINGS This Value Engineering (VE) Quarterly Report summarizes savings and cost avoidance results achieved by reporting organizations that include the AMC major subordinate commands (MSCs), Life Cycle Management Commands (LCMCs), and DA Program Executive Offices (PEOs). The summary shown on the right is for the end of the Third Quarter of Fiscal Year 2010 (FY10). Current VE goals have been established based on 1.5 percent of the organization’s Total Obligation Authority based on guidance in the DoD VE Strategic Plan. Each organization’s progress is measured against those goals. The AMC and PEO community has achieved 30 percent of the AMC/PEO goal of $503.052M with savings and cost avoidances totaling $150.266M. Although this figure is significantly lower than at this time last year, expectations are that the overall FY10 VE savings goal is attainable, especially considering projects in the pipeline. Typically most of the progress toward achieving the VE goal is made in the second half of the fiscal year. Workshops/studies scheduled for FY10 are expected to generate significant reportable savings in FY10 and beyond. OTHER NEWS The FY09 DoD VE Awards Ceremony was held on 12 May 2010 in the Pentagon Auditorium with a reception immediately following in the Executive Dining Room. The DUSD(A&T), The Honorable Frank Kendall, and the DDR&E, The Honorable Zachary Lemnios co-presided. Award recipients and photos of the event are available for viewing on the DoD VE website identified below. AMCOM will be conducting 10 Primary Support Review sessions between now and 1 Dec 10 and will cover VE extensively during each one. The Summer 2010 AMC VE Functional Coordinating Group Meeting is scheduled for 25-26 Aug 10 at Rock Island Arsenal, Rock Island, IL. The Unique Identification Forum will be held 7-9 Sep 10 in Orlando, FL. The DMSMS Conference will be held 25-27 Oct 10 in Las Vegas, NV. The DoD VE website is continually updated with information on recent activities in the DoD VE community and to provide current VE guidelines. For more information, check out the website at: http://ve.ida.org/ve/ve.html • Inquiries on having workshops or concerning this report should be directed to the Edgewood Chemical Biological Center - Rock Island (RDCB-DES-S), Mr. Matt Schade, DSN 793-7787, email: matthew.schade@us.army.mil

More Related