The Bidding, Procurement & Selection Process . Board Study Session Monday, June 25, 2007 Eric Hall . Key Questions. What are the requirements for competitive bidding? What are the stages in the bidding process? What are the various bid structures available to the district?

ancelin
Télécharger la présentation

The Bidding, Procurement & Selection Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Bidding, Procurement & Selection Process Board Study Session Monday, June 25, 2007 Eric Hall Capo USD, Bidding, Procurement & Selection Process

  2. Key Questions • What are the requirements for competitive bidding? • What are the stages in the bidding process? • What are the various bid structures available to the district? • What are the requirements/practices for the selection of Contracts for Special Services? • What is the district’s philosophy? Capo USD, Bidding, Procurement & Selection Process

  3. Bid Limits Formal bids are required in all cases where supplies, equipment, and services exceed the State mandate under Public Contract Code. Bids required for: • Public work projects that meet or exceed $15,000 involving labor; and • Projects where materials and/or equipment exceed $69,000. Capo USD, Bidding, Procurement & Selection Process

  4. Recent Bid Approvals • Provide/install book lockers at Aliso Niguel HS, Aliso Viejo MS, Newhart MS • Example: Bid # 06-07-21, May 7, 2007 • Bid price = $301,350 • Artificial turf at San Juan Hills HS • Example, Bid # 06-07-12, April 2, 2007 • Bid price = $2.095 million • Newhart Middle - 2 story modular classroom grading and site work • Example Bid # 06-07– 26, June 4, 2007 • Bid price = $1.93M Capo USD, Bidding, Procurement & Selection Process

  5. Bid Process: Pre-Bid StagePreparation is Critical ! • Identify need for materials or services; • Identify that a Budget has been developed and approved and that funds are available; • Determine scope of work; • Develop specifications to meet scope of work; • Request Board approval to go out for bid; Capo USD, Bidding, Procurement & Selection Process

  6. Bid Process: Bid Stage 6. When appropriate Utilize OCDE general bid documents; 7. Include specifications; 8. Establish bid opening date and time; 9. Advertise for two weeks in a journal of general publication. Capo USD, Bidding, Procurement & Selection Process

  7. Specifications – Finding the Balance Require high caliber contractors • Proven ability to perform public works or specific to school work? • Ability to respond to district’s needs • Equipment and labor force sufficient for size of job But……encourage and Include all capable contractors • Keep contact information on all contractors that have expressed interest • Encourage contractors to bid • Answer Request For Information (RFI) expediently and clearly Capo USD, Bidding, Procurement & Selection Process

  8. Bid Stage: Pre Selection • Open bids at the place, time, and date advertised (open to the public); • Review documents to determine bidder is qualified, see below; • Tabulate bid prices submitted; Capo USD, Bidding, Procurement & Selection Process

  9. Bid Stage: Pre Selection • Confirm contractor licenses • Board Approval • Example, HVAC equipment Del Obispo Elem & RH Dana ENF Bid #06-07-23, June 4 board, $587k) • Agreement signed, notice to proceed and purchase order issued. Capo USD, Bidding, Procurement & Selection Process

  10. Bid Stage: Pre Selection • Bids submitted must be sealed • Bids must be received at the designated place and time • Bid openings are open to all interested parties • Bids must meet definition of “responsive” Capo USD, Bidding, Procurement & Selection Process

  11. Bid Stage: Selection Criteria Items submitted by bidders (with bid) • Bid bond • Bid form • Designation of subcontractors • Information required of bidder • Certification of participation of Disabled Veteran Business Enterprise (DVBE) • Non-collusion affidavit, notarized Capo USD, Bidding, Procurement & Selection Process

  12. Bid Structures General Contractor Bid • Typically used for construction projects • Architectural plan and specification issued to bidders • Mandatory pre-bid conference and/or job walk conducted • Sub-contractors listed Capo USD, Bidding, Procurement & Selection Process

  13. Bid Structures Unit Price Bids • Used when the volume of work or materials required is not known • Bidders provide a per-hour rate for specific trade, apprentice, and laborer • Bidders provide prices based on a specific unit of measure Capo USD, Bidding, Procurement & Selection Process

  14. Bid Structures Unit Price Bids • Possible work that may occur during the year-used to secure price in advance • Used for – • Emergency repairs – Montano Plumbing • Supplement labor force – PRB Construction • Specialized work – Hardy & Harper Paving • Materials – California Electrical Distributors Capo USD, Bidding, Procurement & Selection Process

  15. Bid Structures Extensions of Bids • Allowed by Education Code 17596 • Labor bids may total five years; One year contract may be extended for 4 additional years. • Material and supplies bids may total four years; One year contract maybe be extended for 3 additional years. Capo USD, Bidding, Procurement & Selection Process

  16. Bid Structures Extension of Bids • May be in the best interest of the district • Contractor knowledge and experience • Prices are secured, 10% cap on increases • Extensions may be good business decision • Efficient use of staff time • District must consider the need to ‘pass the work around’. Capo USD, Bidding, Procurement & Selection Process

  17. Bid Structures Extension of Bids • Is Competition restricted? • Is there a potential for better price? • Does an extension limit the district? • New and different processes • New and better contractors • A fresh approach to services • New contractors moved into the field • Speaks to the need to balance extensions with new bids Capo USD, Bidding, Procurement & Selection Process

  18. Bid Structures Piggyback Bids • Allowed by PCC 20118 and 20652 • Equipment and materials only • Contract items are identical to CUSD specifications • Saves time and money • Economies of scale Capo USD, Bidding, Procurement & Selection Process

  19. Bid Structures Common Types of Piggyback Bids • General Services Agency (GSA) - Federal • California Multiple Awards Schedule (CMAS) - State • Other public agencies, such as county, state, and other school districts • Co-ops, used in Food Services Capo USD, Bidding, Procurement & Selection Process

  20. Bid Structures: Piggyback Bids • Bids generated by CUSD, others have used: • Musical instruments • Audio visual equipment • Flooring • Shade Structures • Bids generated by others CUSD has used: • Classroom furniture • Computers • Gasoline • Buses Capo USD, Bidding, Procurement & Selection Process

  21. Special Services Contracts: Guidelines and Procedures Government Code section 53060 creates an exception to competitivebiddinglaws Special services and advice: • financial • economic • accounting • engineering • legal • textbooks, library books, etc. Capo USD, Bidding, Procurement & Selection Process

  22. Special Services Contracts: Guidelines and Procedures • The district can solicit under a Requests for Proposals (RFP) format, • Or, The district can solicit under a Request for Qualification (RFQ) format. • RFP’s include pricing, schedule and terms, RFQ’s ask for only qualifications • Or, The district can look for providers of services by asking for simple quotes. Capo USD, Bidding, Procurement & Selection Process

  23. Special Services Contracts: RFP’s & RFQ’s The RFP or RFQ Process • District solicits for goods or services • District spells out desired outcome • Proposals provide solutions to desired outcome • Award based on criteria that best meets desired outcome Capo USD, Bidding, Procurement & Selection Process

  24. Special Services Contracts: Recent Approvals Recently approved RFP/RFQ’s include: • Architectural services • Copier improvement program • Parent notification system • Planning/relocation mgmt services • Superintendent search firm Capo USD, Bidding, Procurement & Selection Process

  25. Special Services Contracts: What’s included? Proposals often include: • A Not to Exceed (NTE) price • Terms, monthly, annual, renewals • Insurance coverage • Names of reps working with us • All Agreements approved by Board • Purchase orders issued • May encumber the entire amount • Budgetary Cash flow may suggest incremental p.o.’s Capo USD, Bidding, Procurement & Selection Process

  26. Summary: What have we covered? • Limits • Stages • Bid Specs • Structures • General Contract • Unit Rate/Price • Piggy Back • Extensions • Contracts for Special Services and Advise • RFP’s, RFQ’s or simple quotes And now two questions for consideration……. Capo USD, Bidding, Procurement & Selection Process

  27. Discussion Each District must determine its bidding philosophy based upon the board’s policy…. and the recommendations of staff. Two Discussion Questions for consideration: • What is our bidding philosophy? • How can we improve the selection process? Capo USD, Bidding, Procurement & Selection Process

  28. Thank You !! Capo USD, Bidding, Procurement & Selection Process