1 / 7

EN/STI investigations during LS1 in TDC2 and TCC2

EN/STI investigations during LS1 in TDC2 and TCC2. TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment *Cabling *Flow meters Annual maintenance. To keep in mind for each operation: waste, contamination. TCSC in TDC2.

apu
Télécharger la présentation

EN/STI investigations during LS1 in TDC2 and TCC2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EN/STI investigations during LS1in TDC2 and TCC2 TDC2: -TCSC (collimator) to be replaced if … TCC2: -Targets Stations T2-T4-T6 *Monitors and Target equipment *Cabling *Flow meters Annual maintenance To keep in mind for each operation: waste, contamination

  2. TCSC in TDC2 To be replaced only if budget is allocated and dripping acid is stopped from falling onto the TCSC!! Needs: -RP -Transport -VSC -STI Conflicts: -Large radioactive vessel to transport

  3. TARGET Stations T2-4-6 in TCC2 Moniteur TBIU BAC Moniteur TBID Moteur blindage mobile Switchs Blindage mobile Patch Panel Ventilateur

  4. Monitors and Target to replace Only if BI budget accepted! Needs: -RP -Transport -STI Conflicts: -Large amount of radioactive assemblies to transport (x9)

  5. Cabling on Targets to replace Needs: -RP -BI -VSC -STI To replace To remove To keep

  6. Flow meters to replace on T2-4-6 T2-T4 T6 Needs: -RP -CV -STI

  7. Annual maintenance

More Related