Shut-down progress report

Shut-down progress report. Weeks 10 & 11 M.Weber. General. Mechanical, electrical, cryo work Emergency power switch maintenance Online computer server upgrades Online controls software upgrades Cooling the solenoid. Layer0 clearance measurement.

aram
Télécharger la présentation

Shut-down progress report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shut-down progress report Weeks 10 & 11 M.Weber AEM Dzero, M.Weber

  2. General • Mechanical, electrical, cryo work • Emergency power switch maintenance • Online computer server upgrades • Online controls software upgrades • Cooling the solenoid AEM Dzero, M.Weber

  3. Layer0 clearance measurement • 6.8mm radial space.Survey the clearance.- Is the overlap at Z=0 what we expect ? - Is there a restriction by previously not measured membranes ? • The measurements have been successfully completed • Clearance appears adequate for the installation of Layer 0 AEM Dzero, M.Weber

  4. EC Be SNEG AEM Dzero, M.Weber

  5. Beam pipe re-connected • Installed new SNEG pipe • Re-made the joints SNEG to EC and EC to Be • Restored dry atmosphere for SMT • Currently pumping(Ion Pumps) 1E-8 Thu 0800 AEM Dzero, M.Weber

  6. Installed a Layer0 test module • Connected to the ‘real’ PS, which have been previously installed during this shut-down • Included into the Silicon readout • Remapping of cables needed for Layer0 installation next year is partially done AEM Dzero, M.Weber

  7. Silicon • Silicon has been cooled to operation temperature • The SMT group was able to bring up the system within hours(after several weeks without reading it out and touching (all) components of the readout, including removing all sequencers) • Currently working on recovering HDIs, which failed during data taking AEM Dzero, M.Weber

  8. Next • Complete silicon work in the Calorimeter Gaps • Close the Gaps and survey • Close Toroid Irons and survey • Activate SNEG • Detector and Magnets checkout • Survey detector position AEM Dzero, M.Weber