1 / 28

Week 6, CE 552

Week 6, CE 552. The Traffic Safety Profession and the Highway Safety Improvement Program (HSIP). The Four E’s. Engineering Education Enforcement Emergency Response. Professions and their impact. Administrators (programs) Planners (land use/networks) Designers (trade-offs)

arch
Télécharger la présentation

Week 6, CE 552

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Week 6, CE 552 The Traffic Safety Profession and the Highway Safety Improvement Program (HSIP)

  2. The Four E’s • Engineering • Education • Enforcement • Emergency Response

  3. Professions and their impact • Administrators (programs) • Planners (land use/networks) • Designers (trade-offs) • Construction (workzone) • Traffic Engineers (operations) • Maintenance • Cops

  4. Enforcement • Automated enforcement • HW 4 Speed study • Popular mechanics response letter • Popular science rebuttal

  5. Emergency Response • Rural issues (from NCHRP 500-15) • Geographical barriers; • Inadequate financial resources; • Aging or inadequate equipment; • Gaps in telecommunications; • Lack of proper medical direction; • Difficulty in maintaining skills due to low call volumes; • Lack of training opportunities close to home; • High reliance on increasingly hard-to-find volunteer staff; • Absence of regionalized systems of specialized EMS care, such as trauma systems; and • Absence of local medical facilities to adequately support effective EMS delivery systems.

  6. Education/Public Involvement From 1946: "This 30-foot neon traffic safety sign at Second and Grand avenues was presented to the city Thursday by the Des Moines Junior Chamber of Commerce. The Roosevelt High school band played at the presentation ceremony." Source: Des Moines Register

  7. Agencies and Organizations Road Users Federation National Safety Council Red Cross Professional Associations ASCE ITE ATSIP NACE APWA ATSSA Research Institutions Universities (CUTC) TRB Institutes NHI NHTSA’s equivalent of NHI (one of the books, Evans? Talked about it) many more … • Federal Agencies • NHTSA • FHWA • State Agencies • DOTs • DMV • State Police • GTSB • Local Agencies • Police, Sheriff • City/County Engineer, Public Works • Private Sector • Insurance companies and groups (AAA, IIHS …) • Consultants (Cambridge, SAIC, …) • Interest Groups, foundations • ABATE • AAAFTS (major initiatives: usRAP, safety culture, two more) see Peter’s presentation

  8. Programs, Laws and Funding Section 164 Repeat offender Section 405 Occupant protection (405b Child safety seats), also section 2011 Section 402 Highway Safety Grants (>40% to locals) Section 410 Impaired driving programs Section 411 (now 408) safety data improvement grants Section 2009 high visibility enforcement Section 2010 motorcycle safety ISTEA, TEA-21, SAFETEA-LU • Federal incentives or disincentives (e.g., transfer $ from highway funds to safety funds or withhold altogether if certain state laws are not established; parts of Title 23 chapter 1: • Section 153 Seat belts and helmet use (old) • Section 154 Open container • Section 157 Seat belt usage rates (now 406?) • Section 163 alcohol .08 limit

  9. Iowa’s Traffic Safety Improvement Program (TSIP) • Also known as "Traffic Safety Fund," "TSF," or "Half-Percent" Program • One half of one percent (0.5%) of Iowa’s Road Use Tax Fund (approximately $5 million per year) • $500,000 per year for Traffic Control Device projects. • $500,000 per year for Research, Studies and Public Information initiatives. • Remainder available for Site-specific projects. • Benefit/Cost Worksheet (tsipB-C.xls) • Includes B/C worksheets for both roadway segments and intersections/spot locations

  10. Highway Safety Improvement Program Basic Components

  11. HSIP Basic Phases Planning and analysis What should we do? Implementation Do it. Evaluation Was it successful?

  12. Planning and analysis • Collect and Maintain data • Identify hazardous locations to prioritize needs • Conduct engineering studies 4) Establish project priorities

  13. Planning and analysis 1. Collect and Maintain data a) Establish Location System … where are the crashes? • Milepost • Reference point • Link-node • Coordinates (GIS)

  14. Planning and analysis • Collect and Maintain data b) Types of data Crash data Forms and databases Spot maps Collision diagrams Traffic data Volumes, time of day Classification Highway system • road types - classification • pavement type and condition • geometric conditions • photologs, etc.

  15. Planning and analysis 2) Identify hazardous locations to prioritize needs Techniques to consider … • accident frequency • accident rate • accident severity • rate-quality control • hazard index • EB ...

  16. Planning and analysis • Conduct engineering studies a) Conduct studies to identify contributing causes • speed studies • lane occupancy • sight distance • skid resistance • lighting • traffic control devices • school crossing studies • environment, etc.

  17. Planning and analysis • Conduct engineering studies b) Develop Countermeasures • Evaluate cause-effect relationships • Consider accident patterns c) evaluate cost- effectiveness • Crash costs • National Safety Council • NHTSA • DOT, others • Crash reduction factors (CRF) or Accident Modification Factors (AMF or ARF) • Many sources (with large variations) • Cost effectiveness, B/C, ROR, TOR, NB.

  18. Planning and analysis 4) Establish project priorities Strategies • ranking • Incremental benefit-cost, • linear programming, • Dynamic programming • Other

  19. Implementation Initiate the selected programs • GANTT charts • PERT • CPM • MSS

  20. Evaluation a)determine the effect of safety improvements (crashes) Experimental plan • Before and after study at treatment sites • Before and after study with control sites • Comparative, parallel study • Bayesian probability statistics, • etc.

  21. Evaluation b) perform non-accident evaluation • changes in speed • changes in conflicts • other c) review administrative performance • timely process? • within budget?

  22. Highway Safety Improvement Program

  23. Federal (FHWA) Highway Safety Improvement Program • Core program of SAFETEA-LU • Separately funded (Section 148) • Requires Strategic Highway Safety Plan (SHSP) • ID and analyze problems/opportunities • ID projects and strategies • Evaluate accuracy of data • Prioritize improvements • Hazard Elimination Safety (HES) program • section 152 • High Risk Rural Roads (HRRR) program • Rail-Highway Grade Crossing program • Section 130

  24. The Safety Improvement Index (SII) • TXDOT application SII = B/C, where: S = annual savings in crash costs (equal to crash cost savings per year less annual maintenance costs) R = percentage reduction factor (see following subsection for explanation) F = number of fatal and incapacitating injury crashes (see following subsection for explanation) Cf = cost of a fatal or incapacitating injury crash (see following subsection for explanation) I = number of non-incapacitating injury crashes (see following subsection for explanation) Ci = cost of a non-incapacitating injury crash (see following subsection for explanation) Y = number of years of crash data M = change in annual maintenance costs for the proposed project relative to the existing situation Q = annual change in crash cost savings Aa = projected average annual Average Daily Traffic (ADT) at the end of the project service life Ab = average annual ADT during the year before the project is implemented L = project service life (see following subsection for explanation) B = present worth of project benefits over its service life C = initial cost of the project