1 / 9

Profiling and Settlement Review Group

Profiling and Settlement Review Group. Presentation to DCMF. Purpose of Profiling and Settlement Review. Report to SVG (a BSC Panel Committee) on whether current arrangements for profiling and settlement remain appropriate, given rollout of HH-capable metering to all customers:

Télécharger la présentation

Profiling and Settlement Review Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Profiling and Settlement Review Group Presentation to DCMF John Lucas 3 August 2010

  2. Purpose of Profiling and Settlement Review Report to SVG (a BSC Panel Committee) on whether current arrangements for profiling and settlement remain appropriate, given rollout of HH-capable metering to all customers: Profile Classes 5-8 by 2014 Then Profile Classes 1-4 [rollout targets to be defined] ELEXON, Supplier, DNO and Ofgem participants

  3. Process Followed 4 meetings so far Discussions have homed in on question of why ‘elective’ Half Hourly settlement is so little used Are there artificial barriers to HH settlement that ought to be removed? Would mandatory HH settlement be more accurate and equitable? Consultation (May 2010) on factors driving choice of HH or NHH settlement

  4. Views from May Consultation Choice of HH or NHH settlement is customer driven in most cases HH settlement currently means a more complex supply contract HH settlement means higher cost to serve Supplier Agent costs, BSC Charges Concern about network charges DUoS charges higher? TNUoS charges less predictable? (Triads)

  5. Next Steps PSRG intends to continue exploring: Options for removing barriers to elective HH Cost-benefit of mandatory HH settlement Late August – will be issuing impact assessment requests for: Mandatory HH settlement in PC5-8 (from April 2014 onwards) Impact of applying some GSP Group Correction to HH market

  6. Next steps (cont.) 1 October - Impact assessment responses received back 1 November – report drafted 30 November – report to SVG

  7. DUoS Charges a Potential Barrier to Elective HH? We tried to quantify this as part of our May consultation: Calculated HH and NHH charges (in each DNO area) for typical customer in PC5 to PC8 Used average load research data for demand shape (and assumed NHH night rate from 00:00-07:00 GMT) Capacity based on peak demand and appropriate Load Factor Assumed no reactive power charges

  8. DUoS Findings Our rough calculation gave some support to Supplier concerns that HH DUoS charges are higher: 14% higher for PC5 8% higher for PC6 3% higher for PC7 1% lower for PC8 Not huge differences, but consultation responses suggest Suppliers see it as a concern

  9. Request for DCMF Help Do DUoS charges create an artificial incentive to choose NHH over HH settlement (for below-100kW customers, where the choice exists)? Would a different approach to DUoS for the HH elective market better facilitate the Charging Objectives? For example – apply NHH charges to everyone below 100kW?

More Related