1 / 12

Using Uncertainty Modeling to Optimize M&V in ESPC Projects

Using Uncertainty Modeling to Optimize M&V in ESPC Projects. Discussion Document 10/31/02. Overview. Context: Concern about level of M&V Difficult to reach consensus on a specific project General concern about the degree of stipulation and utility bill reduction

ashley
Télécharger la présentation

Using Uncertainty Modeling to Optimize M&V in ESPC Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Using Uncertainty Modeling to Optimize M&V in ESPC Projects Discussion Document 10/31/02

  2. Overview • Context: Concern about level of M&V • Difficult to reach consensus on a specific project • General concern about the degree of stipulation and utility bill reduction • Can we add value to the current M&V decision-making process (largely qualitative) by incorporating uncertainty modeling (more quantitative)? • Can we do this without complex (expensive) analysis?

  3. Role of M&V in ESPC • Maintain the integrity of the ESPC program • Identify risk parameters and assign responsibilities • Generally, ESCOs responsible for equipment “performance” and agency responsible for “operational” factors. • Define required measurement parameters and protocol • Future role: Help correlate interest rates with energy savings uncertainty

  4. M&V Decision-making in ESPCs – Current Status • Available Tools • FEMP M&V Guide – based on IPMVP • Risk/Responsibility matrix • M&V decision support flowchart • ASHRAE Guideline 14 • Limitations – Lack of “context-specific” guidance • What is the risk tolerance of ESCO and agency? • What is the “optimal” (not ideal) level of analysis, given data, time, and budget constraints for a given project?

  5. M&V Decision-making in ESPCs – Proposed Improvement • Apply quantitative uncertainty analysis to optimize M&V, considering: • Savings uncertainty • Cost of reducing uncertainty via M&V • Risk tolerances of the agency and ESCO • This allows agency and ESCO to make a more informed decision • Tradeoff M&V value (uncertainty reduction) and M&V cost

  6. This is not new! • FEMP M&V Guidelines already recommend use of uncertainty analysis • Section 2.5: Selection of M&V methods & rigor • Appendix D: Sampling guidelines • FEMP Method A Detailed Guidelines • Section 3.1: Considering uncertainty • Section 3.2: How stipulations apportion risks and responsibilities • We also don’t need to invent new science! • Apply well-established risk management techniques for FEMP context

  7. ESPC Cash-flow Model • Payments to ESCO <= Total cost savings • Total Cash flow during ESPC is (supposed to be) less than before ESPC Savings Total Energy + O&M Cost Savings ESCO Payment Energy + O&M Energy + O&M Agency Cash flow ($) During ESPC Before ESPC

  8. ESPC Cash-flow Model • In reality, there are uncertainties around each cash flow component weather, energy prices, etc. Savings ESCO Payment ESCO Payment + = + = Energy + O&M Energy + O&M Energy + O&M Agency Cash flow ($) Typically fixed Equip performance, model assumptions, etc. Before ESPC During ESPC

  9. Cash-flow Uncertainty vs. Risk Tolerance Expected Cash-flow Cash-flow Uncertainty Agency Risk Tolerance Risk Management Need $/yr Agency Cash-flow

  10. M&V and Risk Management • Optimize M&V based on risk management needs • M&V is not an end in itself! Expected Cash-flow Uncertainty w/ no risk mgmt $0 for M&V Agency Risk Tolerance Uncertainty w/ some risk mgmt $X for M&V Uncertainty w/ more risk mgmt $2X for M&V $/yr Agency Cash-flow

  11. M&V and Risk Management – Illustrative Example

  12. Proposed LBNL Work (FY 2003) • Pilot Projects • Select 2-3 ESPC projects as pilots before M&V decisions are made • Analyze uncertainty (work with ESCO, PF) • Assess agency risk tolerance (discussions with agency) • Analyze costs/benefits of different M&V options • Record final decision-making process • Assess lessons learned - policy implications for FEMP • Risk assessment/management requirements • Incorporation of risk management items in contracts • Need, if any, for guidelines and tools • Leverage FEMP M&V Committee for peer-review, guidance and dissemination

More Related