DDS design status Task 9.2-Sub-task 2
DDS design status Task 9.2-Sub-task 2. Alessandro D’Elia on behalf of Roger M. Jones. CLIC_DDS_A. CLIC_DDS_A production is proceeding as scheduled We are waiting for the disks and couplers RF measurements (RF transmission measurements and bead pull) will be done at CERN
DDS design status Task 9.2-Sub-task 2
E N D
Presentation Transcript
DDS design statusTask 9.2-Sub-task 2 Alessandro D’Elia on behalf of Roger M. Jones
CLIC_DDS_A • CLIC_DDS_A production is proceeding as scheduled • We are waiting for the disks and couplers • RF measurements (RF transmission measurements and bead pull) will be done at CERN • If everything is fine, the all the further necessary steps will follow (final assembly and bonding) • RF power tests to be discussed and to be planned according to CERN test stand availability
D. Schulte, PAC09, FR5RFP055 8 x DDS_Circular Assumption: Kick on only following trailing bunch CLIC_G Wake limit Too high!! Wake limit In the specs Courtesy of V. Khan and A. Grudiev
New Structure with 2/3 phase advance CLIC_DDS_A Bandwidth is ~2GHz No interleaving in all cases Better performances than CLIC_DDS_A but still not in the limits
Cell#1: different phase advance WGW 5/6 WGH SlotH 2/3 SlotW Htot 5/9
Conclusions • CLIC_DDS_A production reached its final stage • Studies on the wakefield seems confirming that conventional DDS does not meet the wakefield damping specs • New DDS design improves the performances but is still not enough • Studies of structures with different parameters (phase advance) are ongoing