1 / 11

City of New Orleans Infrastructure Update

City of New Orleans Infrastructure Update. June 2019. Infrastructure Snapshot Year to Date Comparison. Infrastructure Challenges – May 2018. Roads. 1,500 Miles of City-owned roads Standard design life of a roadway is 20-30 years

avon
Télécharger la présentation

City of New Orleans Infrastructure Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. City of New Orleans Infrastructure Update June 2019

  2. Infrastructure SnapshotYear to Date Comparison

  3. Infrastructure Challenges – May 2018 Roads • 1,500 Miles of City-owned roads • Standard design life of a roadway is 20-30 years • Prior to Katrina- annual $16-19M in roadway maintenance and capital improvements • As of 2016 Stantec study • 44% of roads were rated “Very Poor/Failure” • 21% of roads were rated “Poor” • More than $5B needed to repair streets rated “Poor” or below; JIRR only covers approximately 25% of this need • $200-250M needed annually to bring average pavement condition to Fair

  4. Infrastructure Challenges – May 2018 Water and Drainage • Water System • 1,800 Miles of main lines • More than half of main lines are over 100 years old • Only 5 miles of mains replaced over the last 25 years • JIRR program only covers the Katrina damaged portion of the system • Drainage • More than 15,000 miles of pipes between DPW and SWBNO • More than 72,000 catch basins • 24 Drainage Pump Stations • Deferred and ongoing maintenance needs do not address needed improvements to the system like Urban Water Plan projects

  5. Where We AreAccomplishments Since May 2018 Fair Share • Dedicates more than $200 million toward our most critical infrastructure needs in the next five years: • One-time funding that will lead toward fiscal solvency for the Sewerage and Water Board. • Recurring funding to clean our drainage lines at an industry-standard rate, to improve power generation, and to continue to improve our city streets. Joint Infrastructure Recovery Request (JIRR) Program • Submitted 26 DPW/SWB coordinated JIRR projects worth $126M into the FEMA approval process in March 2019. • Convened 16 meetings with key staff from FEMA, GOHSEP, SHPO, the City and SWB to design and institute the program fundamentals (Standard Operating Procedures (SOPs), Metrics, Monthly/Quarterly Reporting, etc.) and work through issues the program is facing.  • Executed the Abbreviated Consultation Process (ACP) with FEMA/ SHPO/ Tribes as of December 17, 2018, which is shortening review and approval timelines with FEMA and helping to accelerate the rate at which the City can put new projects out for bid. • Hired the City’s first ever Archaeologist and Historic Preservation Specialist in November 2018, both of whom are helping to create a roadmap for prioritizing the nearly 200 sub-projects associated with the JIRR. • Established and integrated an infrastructure management system (DPW Dashboard) so that the work under the JIRR is fully coordinated.  • Finalizing a Cooperative Endeavor Agreement to document the annual management between for the JIRR Program.

  6. Where We AreAccomplishments Since May 2018 • Green Infrastructure (Drainage) • Moved $27M Hazard Mitigation Grant Program (HMGP) projects into construction. • Hagan Lafitte Drainage Upgrades -Under Construction 4Q 2018 • Pontilly Neighborhood Stormwater Network -Construction 1Q 2019 • Mirabeau Water Garden - Construction 2Q 2019 • Moved more than $87M in new projects in design through the HUD-funded Gentilly Resilience District. Easton Park – Hagan Lafitte Mirabeau – Pontilly

  7. Where We AreJIRR – Project Distribution (No. of Projects) by Phase Read West Group A

  8. Where We AreJIRR Projects In Construction and Bid & Award * Total construction cost is award amount and all approved plan changes

  9. Where We AreJIRR Projects In Construction Broad St. Construction Project – District B Read West Group A Lakeshore Group A Lakeview South Group A Lower Ninth Ward Northwest West End Group A FQ Infrastructure Improvement Project – District C (East Bank) Berkley and Lancaster – District C (West Bank) Gentilly Terrace Group A Read East Group A

  10. Where We Are GoingJIRR Program Six Month Look Ahead

  11. Construction Hotline: 504.658.ROAD (7623) Facebook.com/roadworkNOLA @roadworkNOLA We have also joined Next Door! @RoadworkNOLA + Monthly Newsletter

More Related