1 / 23

The AHU From

The AHU From. INLAND EMPIRE CHAPTER. Hell. A Case Study Presented by David Sellers Portland Energy Conservation Inc. 1 - 2/27/2002. 2 - 2/27/2002. 3 - 2/27/2002. 4 - 2/27/2002. 5 - 2/27/2002.

beau
Télécharger la présentation

The AHU From

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The AHU From INLAND EMPIRE CHAPTER Hell A Case Study Presented by David Sellers Portland Energy Conservation Inc. 1 - 2/27/2002

  2. 2 - 2/27/2002

  3. 3 - 2/27/2002

  4. 4 - 2/27/2002

  5. 5 - 2/27/2002

  6. At the time this was all going on, the clean room conditions were stable and within specifications; 68°F+1-1/2°F, 45%+3% relative humidity. 6 - 2/27/2002

  7. Leaving preheat coil Outdoor condition Leaving cooling coil, repaired condition; leaving humidifier, as found condition Space condition Leaving fans Leaving cooling coil, as found condition Leaving reheat coil The process as found was using $5,000 - $7,000 of unnecessary energy per month. 7 - 2/27/2002

  8. How Could This Be? • Clean room conditions were at spec • Fast track design build project • Specific clean room requirements • Non-specific HVAC process requirements • Clean room qualification based commissioning focus • The nature of the semi-conductor industry business cycle 8 - 2/27/2002

  9. Preheat Problems • Shut down steam when its not needed • Integral face and bypass type preheat coil • Valve in place, not control signal • Calibrate sensor • Add Alarms 9 - 2/27/2002

  10. Preheat Problems • Integrate control cycle • Eliminate multimode control approach • Operating cycles based on OAT rather than clean room • Inconsistent operation • Sequence with chilled water and reheat • Lock out when not required • Maintain an independent low limit 10 - 2/27/2002

  11. Cooling Problems • Calibrate sensor • A little tricky with an averaging element • Relative calibration more important than absolute calibration • Lock out when not required • Add alarms 11 - 2/27/2002

  12. Humidification and Reheat Problems • Eliminated by the other fixes • Improved space sensor calibration routine • Add alarms • Fan heat provided most of the reheat 12 - 2/27/2002

  13. The cost of correction is projected to be between $4,700 and $8,000. • Exact value depends on the hourly rate used. • Most of the cost was in facilities engineering labor. • Some modest costs were associated with hardware. 13 - 2/27/2002

  14. Educating the Operators Ensured Persistence • Diligent, talented operators • Lacking training in psychrometrics • Lacking training in clean room process • Informal training provided empowerment • Kept a psych chart by the operators console • Nature of engineering support requests changed • Acted on their own initiative 14 - 2/27/2002

  15. Systems Integration Problems 24 hour per day plant operating spec taken literally • No light switches in the clean rooms • No provisions for coordinated start-up and shut down Power failures and equipment failures caused severe pressure fluctuations in the fab • Contamination issue • Safety issue • Restart issue 15 - 2/27/2002

  16. Systems Integration Problems Multiple power sources on the same system • Controls on uninterruptible power supply • Drives on emergency power with different auto-restart options selected • Control interlock circuit on normal power 16 - 2/27/2002

  17. Power Coordination Coupled with an Assembly Problem for a DISASTER!!! 17 - 2/27/2002

  18. Fab Leakage = Energy Burden + Operational Danger Two parallel, redundant fans designed so: • Only one fan runs • Provides 27,000 cfm at 3.5 inches w.c. Clean room leakage resulted in running both fans to achieve pressurization required • 14,000 extra cfm of outside air to move and condition • Static requirement increased to 7 in.w.c. • Duct pressure class was 4 in.w.c.!! 18 - 2/27/2002

  19. Pressure Relief Doors Provide Protection • Protect from air hammer effects due to sudden damper position changes. • Protect over-pressurized ducts to the extent possible 19 - 2/27/2002

  20. Improved Damper Reinforcement Simply matched factory instructions • Reinforcing plate between sections • Bracing is an alternative approach 20 - 2/27/2002

  21. Permissive Interlocks and Better Quality Limit Switches • Start command opens dampers • Limit switches proving starts the fan • Wired to work in all selector switch positions • “Local” control mode on the drive disabled 21 - 2/27/2002

  22. HVAC Process/Efficiency Commissioning Benefits • Reduction in operating cost and improved performance and reliability in retrocommissioning arena. • Reduction in operating cost and first cost with improved performance and reliability in new construction. • Reduction in CO2 emissions. • Complements energy savings. • Potential for additional financial leverage. 22 - 2/27/2002

  23. Barriers to Moving from Qualification Based Approach • Rapid fluctuations in the semiconductor market cycle. • Short paybacks demanded. • Design innovations not embraced. • Drive to get on line and in production ASAP. • Production process tolerances. • Run on detection limits. • Extremely costly to ship bad product. 23 - 2/27/2002

More Related