The current status update highlights significant progress and pending tasks within the team. Suzy has joined, facilitating onboarding and team completion. The Innovation Roadmap is structurally completed, paving the way for upcoming implementations. However, the Idea Generator is currently down and requires attention. The Requirements Workshop at the partner site faced delays, but efforts are in progress to ensure timely completion. Continued focus on resolving critical issues will benchmark future events and maintain project momentum.
E N D
ComVantage – Status WP X, dd/mm/yyyy Progress since last status update • Team completion by on-boarding of new team member Suzy • Innovation Roadmap structurally completed • First implementation of conceptual layout Critical issues • Idea Generator is down Upcoming WP events • Requirements Workshop at Partner Site delay completed completed in progress