1 / 20

U.S. Army Corps of Engineers Tulsa District

U.S. Army Corps of Engineers Tulsa District. Tulsa District. 666 people Civil Geographic Area - Arkansas River Basin and Red River Basin Oklahoma, Southern Kansas and Texas Panhandle Military Geographic Area – Oklahoma and Texas – 2 Army, 4 Air Force

bernad
Télécharger la présentation

U.S. Army Corps of Engineers Tulsa District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S. Army Corps of EngineersTulsa District

  2. Tulsa District • 666 people • Civil Geographic Area - Arkansas River Basin and Red River Basin Oklahoma, Southern Kansas and Texas Panhandle • Military Geographic Area – Oklahoma and Texas – 2 Army, • 4 Air Force • 5 Major Missions of the Corps of Engineers • Warfighting • Homeland Security • Infrastructure • Environmental • Water Resources

  3. Our Priorities: • Support the Global War on Terrorism • Support deployment to AED, GRD • Reach Back Support – BDT • FEST-A Support • Disaster Response • Provide volunteers as required • Leverage Unique District Capabilities • PRT Support – 4 Power Teams • Be prepared to assume RFO Mission • Execute, Execute, Execute • Priority to Fort Sill and Fort Bliss BRAC • Meet MILCON metrics • Meet stakeholder, sponsor commitments on CW projects • Strategic Planning to Prepare for Future

  4. Future Opportunities

  5. Arkansas River Corridor Master Plan The Greater Tulsa Area communities recognize that the Arkansas River Corridor is an important natural resource that could be developed to stimulate immense private investment and greatly improve the quality of life for current and future generations.

  6. Current O&M budgets inadequate to meet recreation demands. Seeking public partnerships/private investments to meet demands. Example: Skiatook Lake Cross Timbers Development Public/Private Development for Increased Recreation

  7. McClellan Kerr Arkansas River Navigation System 12 Foot Channel • Project authorized under PL 108-137 in 2004. • Currently 90% of the system is already 12 foot deep. • Scope: Increase the minimum channel depth from 9 foot to 12 foot, modify the existing flow management plan, and perform channel maintenance dredging. Provide environmental mitigation.

  8. Fort Sill BRAC Execution Tulsa District’s #1 Priority

  9. MASTER PLANNING LAND USE AREAS BIG BLOCKS Fires HQ School TEMF and LTA Proposed DUST Fires COE Instructional Facilities Fires COE Instructional Facilities BOLC II Proposed Instructional Facilities NCOA Fires BDEs / 31st ADA SSQ Housing Reserves/ Guard Multi Family Housing 88M Training Facs

  10. ADA School Campus Area Fort Sill Master Plan Map (getting from F. LePine)

  11. Fort Sill BRAC/MILCON Projects FY07 ADA School Restationing, Increment 1: $138M BRAC Armed Forces Reserve Center Phase 1: $8.7M BRAC FY08 ADA School Restationing, Increment 2: $87M BRAC 31st ADA Brigade Restationing, Increment 1: $89M BRAC Armed Forces Reserve Center Phase 2: $34M BRAC Training Aids Center: $6M BRAC Modified Record Firing Range $2.85M MCA

  12. Fort Sill BRAC/MILCON Projects FY09 31st ADA Brigade Restationing, Increment 2: $67M BRAC - Fire and Movement Range: $1.3M MCA - Infantry Squad Battle Course: $3.3M MCA FY10 Joint Net Fires Training Facility: $27M BRAC Net Fires School HQ: $3.5M BRAC Central Issue Facility: $13.4M MCA Chapel: $9.1M MCA Barracks Renovation: $6.6M O&M Total BRAC: $460M Total MCA/AFH thru FY12 : $405.7M - Major Projects Include: Family Housing Privatization, CIF, Multi-Purpose Physical Fitness Cntr, Initial Entry Training Complex Bldg, Brks Upgrade, Vehicle Maintenance ShopX 2, Battle Command Tng Cntr, Fires Brigade Complex

  13. Contracting Opportunities

  14. MILCON/BRAC Opportunities • FY Installation Project Name ($M) • 07 Fort Sill Whole Neighborhood, 416 units $ 35-45 • 07 McAlester AAP Dunnage Mill $ 2–3 • 07 Fort Sill ADA School, AIT Barracks $ 30-50 (*) • 07 Fort Sill ADA School, UEPH Barracks $ 20-30 (*) • 07 Fort Sill ADA School, TEMF $ 5-10 (*) • 07 Fort Sill ADA School Dining Hall $ 5-10 (*) • 07 Fort Sill ADA School, Patriot GIF $ 20-40 • (*) Task Orders to IDIQ Contracts

  15. MILCON/BRAC Opportunities • FY Installation Project Name ($M) • 07 Fort Sill ADA School, Stinger/Avenger GIF $ 30-50 • 07 Fort Sill Ada School, Infrastructure $ 5-10 • 07 Fort Sill ADA School, Renovations, ctr level $ 10-25 • 07 Fort Sill ADA School, Renovations, 1600 area $ 3-5 • 07 Fort Sill ADA School, Renovations, 3600 area $ 5-10 • 07 Fort Sill ADA School, Renovations, Bldg 3602 $ <500K • 07 Tinker AFB Electrical Substation $ 5-10

  16. MILCON/BRAC Opportunities • FY Installation Project Name ($M) • 07 Vance ADAL Parking Apron $ 5-10 • 07 Vance Squadron Facilities $ 3-5 • 07 Vance ADAL Survival Equip/Ren SIm $ 2-3 • 07 Tinker Expand Hydrant Fuel System $ 1-2

  17. Other Military Opportunities • FY Installation Project Name ($M) • 07 Fort Sill Various O&M $ 8.0 – 12 (*) • 07 Tinker AFB Various O&M $ 20 – 25 (*) • 07 Altus AFB Various O&M $ 0.5 – 1.0 (*) • 07 Vance AFB Various O&M $ 0.5 – 1.0 (*) • 07 McAlester AAP Various O&M $ 8.0 – 12 (*) • 07 Sheppard AFB Various O&M $ .5 – 1.0 (*) • (*) Task Orders

  18. Civil Works Fiscal Year Project Name PA ($M) 07 Misc O&M 3 - 5.0 07 Canton Dam Safety 1.0 – 3.0 07 Wichita River Basin 3.0 – 7.0 07 Sand Creek 1135 (KS) 3.0 – 7.0 07 Cowskin Creek (KS) 2.0 – 5.0 07 Augusta Levee (KS) 3.0 – 7.0

  19. Other Contracts Performance Oriented Construction Activities ID/IQ 8(A) Design Build ID/IQ Contracts for Environmental Services ID/IQ Architect/Engineering and Construction Support Services Contracts Geotech/Materials A/E Dam Safety Evaluation/Inspection Surveying Photogrammetric Mapping

  20. Contacts Colonel Miroslav Kurka, District Commander, 918-669-7201 miroslav.kurka@usace.army.mil John Roberts, Deputy for Project Management, 918-669-7201 john.h.roberts@usace.army.mil Yolane Hartsfield, Small Business Officer, 918-669-7530 m.hartsfield@us.army.mil www.swt.usace.army.mil