An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Narcoossee Roadway Corridor Analysis http://www.osceola.org/index.cfm?lsFuses=department/Engineering/EngCurrentProjects&nChapterID=15776 Osceola County Board of County Commissioners Meeting December 4, 2006

  2. Location

  3. Narcoossee Road • Corridor Study from US-192 to Orange County line (~7.4 miles) • Primary north-south arterial road in Northeast County

  4. Existing Conditions • 2 lane rural arterial road • 12 – foot travel lanes • 4 – foot shoulders • Open drainage system • 55 MPH speed limit

  5. Need for Improvement • Current Average Annual Daily Trips (AADT) = 15,002 – 16,247 • Projected to fail adopted Level of Service (LOS) ‘D’ in 2010 • By 2030, projected 44,000 – 47,500 AADT

  6. Need for Improvement • Safety • 2005: 21 accidents (7 injuries) • January 2006 – March 2006: 9 accidents (10 injuries)

  7. Typical Sections • Urban section • Closed drainage • Design for 6-lane • Construct 4-lane • 45 MPH design speed

  8. Typical Section - IA

  9. Typical Section - IB

  10. Typical Section - IC

  11. Typical Section II

  12. Methodology - Roadway • Typical section requires 130’ of R/W • Minimize R/W takes • Existing R/W Typically 100’ • Many segments of 130’ R/W • Minimize impacts to existing buildings • Minimize environmental impacts

  13. Cyril’s Dr. to Orange County Line Existing Conditions: • Single family residential on both sides • Houses on left are closer to road • Reduced typical section Preliminary Recommendation: • Right widening • 15’ additional R/W required

  14. Orange County Line to Boggy Creek Rd. • Inter-local agreement • Maintain reduced typical section • Orange County is constructing 6-lanes • Possibly re-align Boggy Creek Rd. intersection

  15. Schedule

  16. Cost Right-of-way $12,600,000 Engineering $6,102,000 Construction $61,024,000 CEI $6,102,000 Program Mgmt. $6,102,000 Total $91,930,000

  17. Recommendations • Continue public involvement • Reduce speed limit • Closed drainage system • Investigate landscape options • Investigate noise abatement options • On street bicycle lanes and/or multi-use paths • Reduced typical section at north end to minimize impacts

  18. Proposed Alignment