1 / 23

Interconnection Process (Afternoon Detailed Session)

Interconnection Process (Afternoon Detailed Session). Topics to Cover. Interconnection Process Overview Application Timing and Completeness Technical Scoping Meeting Study Process Interconnection Agreement Project Implementation Deliverability References .

betty_james
Télécharger la présentation

Interconnection Process (Afternoon Detailed Session)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Interconnection Process(Afternoon Detailed Session)

  2. Topics to Cover • Interconnection Process Overview • Application Timing and Completeness • Technical Scoping Meeting • Study Process • Interconnection Agreement • Project Implementation • Deliverability • References

  3. Overview of Wholesale Generation Interconnection Process Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting • Transmission Interconnections • Governed by California Independent System Operator Corporation (CAISO) Tariff • PG&E’s transmission interconnections are for 60 kV and higher • All applications must be submitted to the CAISO • These slides are per CAISO Tariff which is subject to the CAISO • Distribution Interconnections • Governed by PG&E’s Wholesale Distribution Tariff (WDT) • PG&E’s distribution voltage level is defined as facilities operating below 60 kV • All applications must be submitted to PG&E • These slides assume FERC approval of the proposed WDT to be filed in February 2011

  4. Application Processing Timeline Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting * Subject to CAISO ** PG&E Extension Business Rule

  5. What is in a complete application? Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting • Transmission Interconnections • Completed Application • Site Plan Diagram • Single Line Diagram • Application Fee • Site Control or • In-Lieu Financial Security • Distribution Interconnections • Completed Application • Site Plan Diagram • Single Line Diagram • Application Fee • Site Control

  6. PG&E Application Note this application is a DRAFT form

  7. PG&E Application Note this application is a DRAFT form • The Application must be completed in its entirety • Point of Interconnection must be identified • Commercial Operation Date must be identified

  8. PG&E Application Note this application is a DRAFT form • Site Control Requirements must be met

  9. Attachment A Generating Facility Data * Typically applies to Transmission

  10. Scoping Meeting Purpose Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting • Scoping Meeting is designed to provide the Interconnection Customer: • Ensure common understanding of Interconnection Customer’s project • Ensure understanding of Generator Interconnection Procedure • Come to agreement on Point of Interconnection and generator size • PG&E will provide technical system details, limitations, and queued ahead projects • PG&E will advise regarding which process Interconnection Customer qualifies for and study to be conducted • Next Steps • 5 Business Days after Scoping Meeting, the Developer must: • Provide confirmation on the Point of Interconnection • Provide confirmation on Generator Size

  11. Scope of Studies Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting • Technical Studies are intended to provide: • Impact of generation on PG&E’s electric system • Scope of Capital Improvements to PG&E’s electric system to ensure the safety, reliability, and integrity of the grid: • -Interconnection Facilities • Generator Specific facilities required for interconnection • -Distribution Upgrades • Upgrades to the Distribution System triggered by Generator or Cluster • -Network Upgrades • Upgrades to the Network (CAISO Controlled Grid) triggered by Generator or Cluster • Cost Estimate for Scope of Capital Improvements Required and Schedule

  12. Study Results + Project Implementation Contract Technical Studies Cost Estimate Accuracy Supplemental Review System Impact Study Phase 1 Study Facilities Study Phase 2 Study Initial Review Project In-Service Construction • Designs the job and estimates the job with a +/- 10% Accuracy • Provides a detailed Scope of Work. • Provides the Customer +/- 25% Accuracy • Provides a Scope of Work. • Provides the Customer +/- 50% Accuracy • Provides a Rough Scope of Work • Determines acceptance of Fast Track Process -

  13. Interconnection Study Processes Fast Track Initial and Supplemental Review • 2 MW on 12kV and 3 MW on 21 kV and 5 MW on higher voltages • Fast Track Screens • Electrical Independence Screens • Commercial Operation Date Screen (CAISO) • No MW limit • Financial security requirements Independent Study Process System Impact and Facilities Study Cluster Study • Default process, no MW limit • One annual study • Financial security requirements Phase I and II Studies • All processes may apply for full capacity. Deliverability assessment will be conducted by CAISO in CAISO’s cluster process. • PG&E plans on filing a reformed Wholesale Distribution Tariff at the end of Feb seeking approval for a March 1 effective date. These slides assume acceptance by FERC.

  14. Fast Track BD – Business Day

  15. Independent Study Process Facilities Study begins when Initial Posting is made BD – Business Day, CD – Calendar Day

  16. Cluster Study Process BD – Business Day, CD – Calendar Day

  17. Financial Security Postings BD – Business Day, CD – Calendar Day

  18. Interconnection Agreement (IA) Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting Small Generator Interconnection Agreement (SGIA) – 20MW or less Large Generator Interconnection Agreement (LGIA) – greater than 20 MW CAISO GIA is a three-party Agreement between CAISO, PG&E, and Interconnection Customer * Tariff timing regarding tendering an Interconnection Agreement post Facilities Study not identified ** Subject to CAISO BD – Business Day, CD – Calendar Day

  19. Project Implementation Technical Studies Interconnection Agreement Project Implementation Application Processing Technical Scoping Meeting • Post Interconnection Agreement, PG&E and Interconnection Customer should be engineering and designing, procuring, and constructing the electrical interconnection • PG&E will be engineering the Capital Improvements as agreed upon in the Interconnection Agreement • Interconnection Customer will be engineering the electrical system on the Interconnection Customer’s side of the meter and any upgrades that will be applicant built and deeded • Post EPC, PG&E, CAISO (if applicable), Interconnection Customer will coordinate a pre-parallel inspection and commissioning to achieve Commercial Operation.

  20. Deliverability • RA deliverability? What is it? • How do you get it? • Timing? • Participants are required to apply for CAISO deliverability studies to qualify for providing Resource Adequacy PG&E and Socal Edison and CAISO are currently developing the process to allow WDT projects to obtain Resource Adequacy. PG&E will provide guidance prior to the upcoming Cluster.

  21. Interconnection Resources PG&E Wholesale Generator Interconnections Website: http://www.pge.com/mybusiness/customerservice/nonpgeutility/generateownpower/wholesalegeneratorinterconnection/#thesmallgeneratorinterconnectionproceduresfortransmissionsysteminterconnectionstransmissionsgip Email for Interconnection Website: gen@pge.com Please check PG&E’s Wholesale Generator Interconnection Website March 1 for new application forms and filed tariff. CAISO: http://www.caiso.com/docs/2002/06/11/2002061110300427214.html Or via www.pge.com/rfo, select “Solar PV PPA Program RFO”.

  22. Appendix: Distribution Schedule Summary These diagrams are for estimating purposes. It assumes immediate response from Customer. Fast Track Process Independent Study Process Cluster Process

  23. Appendix: Transmission Schedule Summary These diagrams are for estimating purposes. It assumes immediate response from Customer. Fast Track Process Independent Study Process Cluster Process

More Related