1 / 32

Superconducting Spoke Resonator Cavities and Cryomodules

Superconducting Spoke Resonator Cavities and Cryomodules. Thomas H. Nicol Fermilab Accelerator Advisory Committee May 10 th – 12 th , 2006. Outline. Introduction Spoke Cavity Test Cryostat Spoke Cavity Design Slow Tuner Input Power Coupler Cryomodule Design Schedule Status.

betty_james
Télécharger la présentation

Superconducting Spoke Resonator Cavities and Cryomodules

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Superconducting Spoke Resonator Cavities and Cryomodules Thomas H. Nicol Fermilab Accelerator Advisory Committee May 10th – 12th , 2006

  2. Outline • Introduction • Spoke Cavity Test Cryostat • Spoke Cavity Design • Slow Tuner • Input Power Coupler • Cryomodule Design • Schedule • Status

  3. Introduction • Front End Layout • Meson Detector Building (MDB) Layout • Meson Detector Building (MDB) “Tunnel” Cross-Section • Front End Cryogenics Flow Schematic

  4. Front End Layout Meson Detector Building SSR Sections

  5. MDB Layout

  6. MDB “Tunnel” Cross-Section

  7. Front End Cryogenics Flow Schematic

  8. Single Spoke Test Cryostat • Goals • Design • Cost Estimate • Status

  9. Test Cryostat Goals • Individually test each spoke resonator with or without its associated solenoid or quadrupole • Accommodate all spoke resonator designs with minimal cryostat alterations • Apply input power using production couplers in multiple orientations (horizontal, vertical, 45° etc.) • Allow testing at 2 K if necessary for diagnostics • Identical (or nearly so) test cryostats at Fermilab and Argonne to allow identical test configurations

  10. Test Cryostat

  11. Test Cryostat

  12. Test Cryostat Cost Estimate

  13. Test Cryostat Status • Design review completed December 2005 • Solid modeling and drafting are in-process • Some commercial items are on order (valves, instrumentation, etc.) • In-house produced parts (valves, bayonets, etc.) are available • Expect major procurement of the vessel and internal piping in May or June 2006

  14. Spoke Resonator Cryomodules • Cavities • Helium Vessel • Slow Tuner • Input Power Coupler • Cryomodule Assembly

  15. b=0.22 and b=0.4 Cavity Cryomodules • Two b=0.22 cryomodules (SSR-1), each containing • 9 single spoke resonators, 325 MHz • 9 solenoids • Two b=0.4 cryomodules (SSR-2), each containing • 11 single spoke resonators, 325 MHz • 6 solenoids

  16. b=0.22 Cavity ~300 mm ~500 mm

  17. Cavity and Helium Vessel

  18. Slow Tuner Tuning range: ± 500 kHz

  19. Input Power Coupler Vacuum vessel flange Cold window Warm window Instrumentation and pump-out 4 K flange SSR input coupler power: 35 kW

  20. Input Power Coupler (exploded view)

  21. Complete Cavity Assembly

  22. b=0.22 Cold Mass Assembly

  23. b=0.22 Cryomodule Assembly

  24. b=0.22 Cryomodule Assembly

  25. SSR-1 Cryomodule Interconnect

  26. SSR-1 Cryomodule Interconnect

  27. Two SSR-1 Cryomodules 14.1 m

  28. SSR-2 Section 960 cm Drift space is introduced by missing the cavity 1 focusing period, length = 160 cm

  29. Cryomodule Heat Load Estimate

  30. Test Cryostat and SSR Cryomodule Schedule

  31. Conclusions • Test cryostat • Design is nearly complete • Some commercial parts on order • Procurement on the main vessels will begin soon • SSR-1 and SSR-2 cavities, tuner, and input coupler • SSR-1 cavity design complete and quotes for prototype assembly have been received • Tuner design in-process, prototype is planned • Input power coupler prototype in fabrication, delivery expected late May or early June with testing to follow • SSR-2 cavity design is in-process • SSR-1 cryomodules • Design in-process

  32. Acknowledgements • Test Cryostat • Mike White • Spoke Resonator Design • Giobatta Lanfranco • Ivan Gonin • Beam Dynamics • Peter Ostroumov • Gennady Romanov • Input Power Couplers • Timergali Khabibouline

More Related