bluma
Uploaded by
6 SLIDES
196 VUES
60LIKES

Expansion of Perryman 6 Power Plant: New 60 MW Generators and Emission Control Systems

DESCRIPTION

The Perryman 6 project proposes the addition of ten new 60 MW simple-cycle CT units at the existing facility located south of Perryman, MD. This expansion aims to increase the nominal generating capacity from 355 MW to 955 MW, with a 600 MW addition. Enhanced air emission control measures will be implemented, utilizing technologies such as water injection, selective catalytic reduction (SCR), and thermal oxidation reaction (TOR) systems. Construction is expected to commence in Q3 2009, with completion projected within five years.

1 / 6

Télécharger la présentation

Expansion of Perryman 6 Power Plant: New 60 MW Generators and Emission Control Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PSC Case No. 9136Perryman 6 Constellation Power Source Generation (CPSG)

  2. Perryman 6 • 704-acre site south of Perryman, MD • Site currently contains five simple-cycle CT units (Units 1-4 & 51) • Proposed addition of (10) new 60 MW simple-cycle CTs • Nominal Generating Capacity: 355 MW to 955 MW (600 MW addition)

  3. Perryman 6 • Air Emission Control Equipment • NOx : water injection and selective catalytic reaction (SCR) • CO & VOCs: thermal oxidation reaction (TOR) systems • SO2 & PM: clean-burning fuels (natural gas & ultra-low sulfur diesel (ULSD))

  4. Perryman 6 • Water • Proposed • Groundwater: (10) new on-site wells • Municipal Water: Harford County • Other Options • Sod Run? • Desalination?

  5. Construction anticipated to start in the 3rd quarter of 2009. All 10 units to be constructed within 5 years. 2 - 4 units (120 – 240 MW) by June 2010 All 10 units (600 MW) by 2014 Perryman 6