Alameda Unified School District. 2008 Construction Progress Report. Overview. Construction Goals Build a new K-5 school Work at existing schools Address Americans with Disabilities Act (ADA) compliance requirements Upgrade Fire Alarm Systems as needed Upgrade HVAC Systems

bonnie
Télécharger la présentation

Alameda Unified School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alameda Unified School District 2008 Construction Progress Report

  2. Overview Construction Goals • Build a new K-5 school Work at existing schools • Address Americans with Disabilities Act (ADA) compliance requirements • Upgrade Fire Alarm Systems as needed • Upgrade HVAC Systems • Repair aging building systems - i.e. roofs, windows & doors as needed • Repair worn or damaged finishes • Perform site specific projects including play structures, seal and re-line asphalt, irrigation …

  3. Source of the 91.4 Million Budget

  4. Current Budget all fund sources

  5. Board Approved Projects

  6. Ruby Bridges Elementary School • Scope • Construct New K-5 School • Accommodate students from Miller and Woodstock Elementary Schools • Increased capacity ( increment II ) to accommodate Longfellow students • Project Start Date 6/13/05 • Current Status Completed • Warrantee Work • Electrical • HVAC • Current Budget $22,050,880 • Funds Expended $20,918,639

  7. Amelia Earhart Elementary School • Scope • Fire Alarm • HVAC • Portable Relocation • ADA Compliance • Project Start Date 6/21/05 • Current Status Completed • Current Budget $5,504,457 • Funds Expended $4,966,040

  8. Lincoln Middle School • Scope • HVAC • Electrical upgrade • ADA compliance • Restrooms • 2 story addition • Project Start Date 6/21/05 • Current Status 90% Complete • Current Budget $8,550,000 • Funds Expended $8,266,070

  9. Haight Elementary School • Scope • Seismic Retrofit • HVAC • Alarm Systems • ADA Compliance • Exterior Paint • Project Start Date 6/24/06 • Current Status Complete • Current Budget $5,560,000 • Funds Expended $5,542,006

  10. Alameda High School • Scope • HVAC • Fire Alarm • ADA Compliance • Electrical upgrade • Interior finishes • Grounds upgrades • Exterior Paint • Project Start Date 6/22/06 • Current Status 99% Completed • HVAC • Irrigation • Current Budget $9,166,249 • Funds Expended $8,949,609

  11. Miller (Island High School) • Scope • HVAC • ADA Compliance • Interior Finishes • Alarms • Project Start Date 6/22/06 • Current Status Completed • Warrantee Phase • HVAC • Current Budget $2,340,000 • Funds Expended $2,330,363

  12. Edison Elementary School • Scope • Heat and Ventilation • ADA Compliance • Alarms • Project Start Date 6/18/07 • Current Status Complete • Current Budget $2,335,000 • Funds Expended $2,320,269

  13. Otis Elementary School • Scope • Heat and Ventilation • ADA Compliance • Alarms • Project Start Date 6/18/07 • Current Status Complete • Current Budget $1,910,000 • Funds Expended $1,881,809

  14. Lum Elementary School • Scope • HVAC • ADA Compliance • Alarms • Electrical Upgrade -Paging/Intercom • Project Start Date 6/18/07 • Current Status Complete • Warrantee Phase • HVAC • Electrical • Casework • Current Budget $1,812,000 • Funds Expended $1,791,739

  15. Washington Elementary School • Scope • Heat and Ventilation • ADA Compliance • Alarms • Electrical Upgrade -Paging/Intercom • Window Replacement • Project Start Date 6/18/07 • Current Status Complete • Current Budget $2,670,000 • Funds Expended $2,636,000

  16. Paden Elementary School • Scope • HVAC • ADA Compliance • Alarms • Project Start Date 6/18/07 • Current Status Complete • Current Budget $1,680,000 • Funds Expended $1,671,449

  17. Chipman Middle School Increment 1 • Scope • ADA Compliance Restrooms • Exterior Paint • Project Start Date 6/18/07 • Current Status Complete • Current Budget $1,370,000 • Funds Expended $1,362,926

  18. FF&E Interim Housing and Technology

  19. Remaining Projects PHASE IV Preliminary Construction Estimates • Chipman Middle School part II • HVAC retrofit • ADA Compliance parking lot, sidewalks, and other minor work • Encinal High School • HVAC coil replacement 200, 300, and 400 wing HV systems • HVAC Gym system upgrade • ADA Compliance major site accessibility work on the gym and building 400 • Fire Alarm System Upgrade system replacement • Woodstock Child Development Center • Minor ADA work at entry of building • HVAC repairs • Floor coverings and interior paint • Lighting retrofit • Adult School • Exterior Windows South and West restoration or replacement • Repair Plaster and wood trim • Exterior paint • Historical Alameda High School • Shore existing façade and construct new DSA compliant 12 classroom building inside.

  20. Remaining Projects PHASE V • Franklin Elementary School • Minor ADA work at entry of building • HVAC repairs to controls, boiler, circulation pumps and 3-way valves • Replace worn blinds • Wood Middle School • ADA compliance in affected areas • Fire Alarm System replacement • HVAC repairs to most systems • Exterior paint • Bayfarm Elementary School • ADA compliance path of travel and entrances to classrooms • HVAC in Media Center • Fire Alarm • Utility retrofit Natural Gas flex connector • Longfellow Education Center • ADA compliance in affected areas • Fire Alarm System replacement • HVAC repairs to most systems • Exterior paint • Woodstock Education Center • ADA compliance in affected areas • Fire Alarm System replacement • HVAC repairs to most systems • Exterior paint

  21. Moving Forward

  22. Calendar of events • June 24th 2008 Measure C Oversight Committee Report • June 24th Authorization to Advertise for Bids on phase 4 and 5 approved projects. • Construction Updates • October 2008 Construction Update • February 2009 Construction Update • June 2009 Construction Update

  23. Measure C The largest portion of the work identified in this report was funded through a bond measure passed in 2004. Alameda Unified School District would like to express our thanks to the citizens of Alameda for your support of Bond Measure C.