1 / 2

SG4a Project Timeline

SG4a Project Timeline. Interest Group ‘a’ Activities Nov 02: Interest Group ‘a’ formed Mar 03: Issued informal Call For Applications Jul 03: Study Group ‘a’ approved Aug 03 Issued official Call For Applications (CFA) Sep 03 Session #1 Develop SG work plan and project timeline

boone
Télécharger la présentation

SG4a Project Timeline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SG4a Project Timeline • Interest Group ‘a’ Activities • Nov 02: Interest Group ‘a’ formed • Mar 03: Issued informal Call For Applications • Jul 03: Study Group ‘a’ approved • Aug 03 • Issued official Call For Applications (CFA) • Sep 03 Session #1 • Develop SG work plan and project timeline • Hear responses to CFA • Begin discussion of PAR & 5C • Begin work of channel model subcommittee • Begin characterization of applications • Nov 03 Session #2 • Hear responses to CFA • Derive Application Requirements from CFA • Continue subcommittee activities, work on channel models • Continue discussion / drafting on PAR & 5C • Jan 04 Session #3 • Continue subcommittee activities, including channel model development • Start developing Technical Requirements • Draft and submit PAR & 5 Criteria • Motion to have PAR & 5C adopted to form Task Group (24 March 2004) • Mar 04 Session #4 • Complete Technical Requirements • Continue subcommittee activities, including channel model development • Start drafting Selection Criteria • May 04 Session #5 – First Task Group 15.4a Meeting • Complete Selection Criteria • Establish Down-Selection Procedure • Channel Model selection and approval • Issue Call for Proposals Project Authorization Request - PAR Larry Taylor / Jason Ellis

  2. SG4a Project Timeline 15.4IGa Formed PAR & 5C Complete 2004 2003 J F M A M N J J A S O N D J F M A M J J S O N A D D 2 StudyGroup Terms TG15.4a Approved 15.4SGa ApprovedInformal CFA Today * Assumes PAR & 5C warrants new standard Larry Taylor / Jason Ellis

More Related