An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AEEC MeetingBrussels 23.11.2009 Perspective of Nuclear Energy in Poland Tomasz Jackowski, Poland Department of Nuclear Energy Ministry of Economy

  2. Electrical energy consumption in European Union per capita Poland 2699 kWh/y per capita UE27 5707 kWh/y per capita Eurostat 2006 Tomasz Jackowski, Ministry of Economy

  3. Sources of electrical energy supply Poland EU World Electricity in 2005 – IEA 2008 Tomasz Jackowski, Ministry of Economy

  4. 58.7% 35.0% 1.7% 2.0% 2.2% 0.3% 0.1% Hard coal power stations and CHPs Lignite power stations Gas power stations Hydro power stations (included pumped-storage) Wind power stations Biogas and biomass power stations Other fuels Fuel Structure of Electricity Generation in Poland Tomasz Jackowski, Ministry of Economy 4

  5. 7% 6% 5% 5% 16% 44% 17% to 5 years 5-10 years 10-15 years 15-20 years 20-25 years 25-30 years over 30 years Age Structure of the Existing Power Plants in Poland Tomasz Jackowski, Ministry of Economy 5

  6. Energy Policy in Poland till 2030 adopted 10 November 2009Priorities • Raise of energy effectiveness • Safe energy supply • Implementation of nuclear power as the element of energy diversification • Development of renewable sources of energy including bio fuels • Creation of competitive market of energy • Limitation of environmental influence of power production Tomasz Jackowski, Ministry of Economy

  7. Sustainable development • Improvement of energy supply security taking into account energy supply for future generations • Climate preservation • Limitation of environmental influence of power production • Development of electrical, gas and oil transportation infrastructure Tomasz Jackowski, Ministry of Economy

  8. GOVERNMENT RESOLUTION ON THE MEASURES UNDERTAKEN IN THE AREA OF NUCLEAR POWER DEVELOPMENT • On January 13 2009, the following resolution has been adopted by the Government of the Republic of Poland : • To ensure the national energy security, and taking into account the economic development, a Polish nuclear power program shall be developed and implemented. Tomasz Jackowski, Ministry of Economy

  9. GOVERNMENT RESOLUTION ON THE MEASURES UNDERTAKEN IN THE AREA OF NUCLEAR POWER DEVELOPMENT –cont. • The draft of such program shall be developed and submitted to the Council of Ministers by the government commissioner; this program shall determine the nuclear power plants' number, size and possible sites. • Moreover, the government obligates the National Treasury Minister to ensure that PGE Polish Energy Group SA shall cooperate on the program's development and implementation. Tomasz Jackowski, Ministry of Economy

  10. Government Information Center added the following comment: • In connection with the government resolution of January 13, 2009 on starting the work on Polish Nuclear Power Program, at least two nuclear power plants will be built. The work will be conducted simultaneously, and the operation of at least one of these nuclear power plants should be started by 2020. • Nuclear power plant construction in Poland does not preclude Polish involvement in similar investments abroad. Tomasz Jackowski, Ministry of Economy

  11. Comment by the Government Information Center – cont. • Government's Plenipotentiary for Polish Nuclear Power Program shall be charged with the coordination and supervision of the measures for the preparation of the regulatory and institutional environment, necessary for the nuclear power plant commissioning in Poland. • Responsibility for the plant's construction rests with PGE Polish Energy Group SA. Tomasz Jackowski, Ministry of Economy

  12. Government Commissioner responsibilities • 12 May 2009 Governmental decree concerning responsibilities of the Plenipotentiary of Polish Government for the development of Nuclear Power • Role of the pleniptentiary –infastructure building and coordination of the programme of nuclear power implementation in Poland • Support from the Polish Energy Group Tomasz Jackowski, Ministry of Economy

  13. 19 May 2009 – Appointment of Mrs. Hanna Trojanowska to the post of Plenipotantiary of Polish Government for the Development of Polish Nuclear Power and Undersecretary of State in Ministry of Economy Tomasz Jackowski, Ministry of Economy

  14. Nuclear energy in energy policy - 1 • Activities leading to establishing Nuclear Energy Program Implementing Organisation supervised by Minister of Economy • Defining necessary changes in Polish law to implement nuclear power program • Human Resources Development for Nuclear Power Program Tomasz Jackowski, Ministry of Economy

  15. „Framework time schedule for nuclear power activities” acknowledged by the Council of Ministers on 11 August 2009 • I until 31.12.2010preparation and approval by theCouncil of Ministers of the Polish Nuclear Power Program • II 2011 – 2013 NPP site selection and conclusionof a contract forconstruction of the first NPP • III 2014 – 2015 preparation of technical design and obtaining allrequired decisions and permits • IV 2016 – 2020 construction of the first NPP in Poland Tomasz Jackowski, Ministry of Economy

  16. NEPIO • In February 2009 creation of Nuclear Energy Department having 9 employees • In 2009 plan to have 20 person • In 2010 plan to reach 44 person and take the promotion and coordination activities from National Atomic Energy Agency Tomasz Jackowski, Ministry of Economy

  17. Law adaptation • Analyses of existing systems of regulations in EU countries and some OECD countries • The development of draft regulations till the end of 2009 and government approval planned till June 2010 Tomasz Jackowski, Ministry of Economy

  18. Human resources development stage 1 • Educating and training HR for technical universities, NEPIO, Nuclear Regulatory and investors • 6 months in existing NPP and training center • 6 months in corresponding institution abroad – more than 100 persons Tomasz Jackowski, Ministry of Economy

  19. Human resources development - stage 2 • MSc II-ndstagestudies or post graduate studies partially abroad - 300 persons • Graduates from the above mentioned studies – 6 month training in NPP and training center Tomasz Jackowski, Ministry of Economy

  20. Human resources development – stage 3 • Reactor Engineering Departments at Technical Universities and other specializations needed for nuclear power implementation • 6 month training in foreign NPPs and training centers Tomasz Jackowski, Ministry of Economy

  21. Nuclear energy in energy policy - 2 • Information and education campaign concerning nuclear energy program • Site selection analyses for first NPPs • Site selection design and construction of the Low and Intermediate Level Radioctive Waste Repository • Reinforcement of human resources and competences of Nuclear Regulatory Institution Tomasz Jackowski, Ministry of Economy

  22. Nuclear energy in energy policy - 3 • Building nuclear R & D infrastructure on the basis of existing research institutions • Development of Fuel Cycle Solutions ensuring long-term and safe access to nuclear fuel, recycling of spent fuel and reposition of high level radioactive waste for Poland Tomasz Jackowski, Ministry of Economy

  23. Public information • Professional PR Department of NEPIO • Teachers education • Information about nuclear power in education programmes • Widely available web database concerning nuclear facilities Tomasz Jackowski, Ministry of Economy

  24. Site selection for NPPs • Lack of site selection criteria in Polish regulations • Site selection based on geology, tectonics, hydrology, demography, meteorology, grid infrastructure and power demand performed 20 years ago for 8 sites • Necessary verification of performedanalyses • Public consultations Tomasz Jackowski, Ministry of Economy

  25. Tomasz Jackowski, Ministry of Economy

  26. Tomasz Jackowski, Ministry of Economy

  27. Tomasz Jackowski, Ministry of Economy

  28. BuildingLow and Intermediate Radioactivity Waste Disposal • Site analyses • Project of the LIRW Disposal • Public consultation • Construction of the new disposal • Closure of the Różan disposal Tomasz Jackowski, Ministry of Economy

  29. Thank you for your attention!