PXL Detector Project Status
This outline presents the current status of the PXL Detector Project, covering project history, costs, schedules, risks, and testing plans. It delves into the history of the project's work breakdown structure (WBS), focusing on phases for electronics, sensors, ladder cables, and production electronics. The cost estimates based on CD-1 requirements are discussed, along with an overview of development activities, testing protocols, and anticipated risk management strategies. Detailed subsystem milestones and project timelines are also outlined to ensure readiness for the CD-2/3 review.
PXL Detector Project Status
E N D
Presentation Transcript
PXL Detector Project Status
Talk Outline • Project history – current CD status • Cost and schedule • Risk areas and mitigation • Testing plans • Summary
WBS Structure • 1.2.2 PXL Electronics • 1.2.2.1 Phase-1 Sensor • 1.2.2.1.1 Phase-1 Prototype • 1.2.2.1.2 Phase-1 Production • 1.2.2.2 PXL Sensor • 1.2.2.2.1 PXL Sensor Prototype • 1.2.2.2.2 PXL Sensor Production • 1.2.2.3 Ladder Cable • 1.2.2.3.1 Infrastructure Test Cable • 1.2.2.3.2 Prototype Ladder Cable (FR-4) • 1.2.2.3.3 Ladder Cable (Kapton + Cu conductor) • 1.2.3.3.4 Ladder Cable (Kapton + Al conductor) • 1.2.2.3.5 Ladder Cable PXL Sensor • 1.2.2.4 Phase-1 Ladder Assembly • 1.2.2.4.1 Ladder Mechanical / Electrical Prototypes • 1.2.2.5 Read-out Electronics • 1.2.2.5.1 RDO Board • 1.2.2.5.2 Mass Termination Board • 1.2.2.5.3 RDO PCs • 1.2.2.5.4 Control PC System • 1.2.2.6 PXL Sensor Ladder Production
Electronics Development Plan • Develop sensor chips, 3 generation program (WBS 1.2.2.2) • Develop readout electronics (WBS 1.2.2.5) • STAR compatible readout system - limited channel count • Upgrade to full detector capability • Develop flex PC readout cable (WBS 1.2.2.3) • copper version • aluminum version • Develop chip testing and characterization system (WBS 1.2.2.5, 1.2.2.6) • Individual sensor • probe test • Production testing of ladders (WBS 1.2.2.6)
Cost Estimate and Schedule Current Status • Current cost estimates are based on CD-1 needs (establish cost range). • BOE will be documented by CD-2/3. • For CD-2/3 we will probably need to re-baseline. This will mostly consist of a simple time shift. • The funding profile provided from DOE is the driving factor behind the schedule.
PXL Costs Contributed Labor is not costed in this estimate. (LG + 2 postdoc)
Cost Estimate and Schedule Details are on the handout or available as an Excel file
Detailed Subsystem Milestones Full details are on the handout or available as an Project file A complete resource loaded schedule will be produced for CD-2/3
Risk Preliminary Risk Table as per DOE template
Summary • The sensor and RDO project costs and schedule are understood at a level that allows for the creation of a resource loaded schedule that will be completed before CD-2/3 review. • The risks are understood and addressed. • We have a development and testing plan that addresses the needs of the project.