1 / 45

NPV IRR and Capital Budgeting

NPV IRR and Capital Budgeting. Capital Budgeting. Expenditures on projects that have a life greater than one year Long - Term Plans and lost flexibility. Independent Projects. Two projects are considered independent if undertaking one of them does not prevent us from considering the other

brook
Télécharger la présentation

NPV IRR and Capital Budgeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NPV IRR and Capital Budgeting

  2. Capital Budgeting • Expenditures on projects that have a life greater than one year • Long - Term Plans and lost flexibility

  3. Independent Projects • Two projects are considered independent if undertaking one of them does not prevent us from considering the other • The main question we will ask is whether or not a project is “acceptable.”

  4. Mutually Exclusive Projects • Two projects are considered to be mutually exclusive when undertaking one project will preclude the other from being accepted. • The criteria that causes this should be something other than cost. • Ranking Mutually Exclusive Projects need accept / reject then rank the projects • Timing of Cash Flows, Size of competing investments, Scarce Resources

  5. Project Valuation vs.. Security Valuation • Estimate the future cash flows • Determine the appropriate interest rate • Find the PV of the positive cash flows • Compare the PV to the cost

  6. What Cash Flow? • The incremental changes to cash flow that result from the project.

  7. Incremental Cash Flow • Cash flow changes that result from a particular project • Relevant Cash Outflows • Increase Cash outflow • Elimination of cash inflow • Investment in Assets • Relevant Cash Inflow • Increase in cash inflow • Elimination of cash outflow • Liquidation of assets

  8. Capital Budgeting Decision Tools • Net Present Value • Payback Period and Discounted Payback • Internal Rate of Return & Modified IRR • Profitability Index and Modified Profitability index

  9. Net Present Value • The sum of the PV of the positive cash flows minus the PV of negative cash flows and the initial cost or

  10. NPV Accept or Reject • If the NPV is positive the PV of the benefits is greater than the PV of the cost -- You should accept the project (The value of the firm will increase if the project is accepted) • If the NPV is negative, The PV of the benefits is less than the PV of the cost -- You should reject the project (The value of the firm would decrease if the project is accepted)

  11. NPV Example Assume a project cost of capital of 10% • Year Cash Flow Present Value • 0 -1,000 -1,000.00 • 1 1,000 909.90 • 2 -2,000 -1,652.89 • 3 3,000 2,253.94 • NPV = 510.14

  12. Calculator • HP 10B • -1,000 <CFj> • 1,000 <CFj> • -2,000 <CFj> • 3,000 <CFj> • 10 <I/Y> • <NPV>

  13. The Required Return • What interest rate should be used to discount the cash flows? • The project cost of capital WHY?

  14. NPV • Note, as in the case of our bond and stock valuation models there will be an inverse relationship between the required return and the NPV. • A lower Cost of Capital increases the NPV of the project (And the value of the firm)

  15. Special Case • What if the project is expected to return cash flows that grow at a constant rate forever and the only outlay is at the beginning of the project? • Use the constant growth formula (Stock Valuation)

  16. Internal Rate of Return • The IRR is the required return that makes the NPV of a project equal to zero. • If IRR is greater than the hurdle rate (the project cost of capital) Accept the project • IF IRR is less than the hurdle rate (the project cost of capital) Reject the project

  17. IRR and NPV • IRR and NPV will always provide the same accept / reject decision WHY???? • IRR is the rate that makes NPV zero • If: Project cost of capital < IRR accept the project, this also implies a positive NPV (inverse relationship) • If Project Cost of Capital > IRR reject the project , this also implies a negative NPV

  18. IRR Benefits • Intuitive • Measure of risk compared to WACC

  19. IRR Problems • Ignores size and amount of wealth created • Ignores project life • It is possible to have multiple IRR’s

  20. Multiple IRR’s • Time Cash Flow • 0 -100 • 1 275 IRR = 7.4% and 67.6% • 2 -180 • Time Cash Flow • 0 100 • 1 -275 IRR = 7.4% and 67.6% • 2 180

  21. Multiple IRR’s vs. NPV • Time Cash Flow • 0 -100 • 1 275 NPV @ 15% = $3 • 2 -180 • Time Cash Flow • 0 100 • 1 -275 NPV @ 15% = -$3 • 2 180

  22. Multiple IRR’s • An easy check for Multiple IRR’s • Mathematically the largest number of IRR’s that is possible equals the number of sign changes in the cash flow stream

  23. Modified IRR • The discount rate that makes the PV of the projects costs equal the PV of the terminal value of the project • Terminal Value = the FV of the positive Cash flows compounded at the cost of capital

  24. Example Cost of Capital = 10% Time Cash Flow PV FV 0 -1000 -1000 1 500 665.50 2 400 484.00 3 -150 -112.69 4 500 500.00 -1,112.691,649.50 1112.69 = 1649.50/(1+MIRR)4 MIRR = 10.34%

  25. Payback Period • Intuition: Measures length of time it takes for the firm to payback the original investment. • Simple example: • Cost = 100,000 Cash Flow = 20,000 a year • Payback = Cost / Cash Flows • = 100,000 / 20,000 = 5 years

  26. Payback Period • Most problems do not work out even…. • You need to look at the cumulative cash flow and compare to the initial cost.

  27. Calculating Payback Period • Calculate the cumulative cash flow (total cash flow received) • Calculate the Remaining Cost (Total Cost - Cumulative Cash Flow) • Repeat 1 and 2 until remaining cost is less than zero • In last positive year divide remaining cash flow by yearly cash flow in next year • Calculate total payback

  28. Example: Initial Cost = 100,000 Yearly Cumulative Remaining YR Cash Flow Cash Flow Cash Flow 1 40,000 40,000 60,000 2 30,000 70,000 30,000 3 25,000 95,000 5,000 4 20,000 115,000 -15,000 Payback = 3 + 5,000/20,000 = 3.25

  29. Payback Period: Benefits • Easy to Understand and Interpret • Reject / Accept based on a Minimum payback • Provides measure of risk

  30. Payback Period Weaknesses • Ignores Time Value of Money • Ignores all cash flows after the payback

  31. Discounted Payback Period • Attempts to account for time value of money by evaluating the yearly cash flows in their present value.

  32. Calculating Discounted Payback Period • Calculate the PV of each cash flow • Calculate the cumulative present value of the cash flow s(total cash flow received) • Calculate the Remaining Cost (Total Cost - Cumulative PV Cash Flow) • Repeat 1 and 2 until remaining cost is less than zero • In last positive year divide remaining cash flow by yearly cash flow in next year • Calculate total payback

  33. Initial Cost=100,000 r = 10% Yearly PV Cumul Remaining YR CF CF CF CF 1 40,000 36,364 36,364 63,636 2 30,000 24,793 61,157 38,843 3 25,000 18,783 79,940 20,060 4 20,000 13,660 93,600 6,400 5 15,000 9,314 102,914 -2,914 Payback = 4 + 6400/9314 = 4.687

  34. Discounted Payback • Weakness: Still ignores cash flows after payback • Strengths: Accounts for time value of money, easy to understand and calculate, risk measure • Accept / Reject -- Set Minimum payback and compare

  35. Profitability Index • Measures the value created per dollar invested

  36. PI • If the PI is greater than 1 accept the project (NPV is positive) • If the PI is less than 1 reject the project (NPV is negative) • If PI = 1.45 it would imply that the project will produce $1.45 for each $1 invested.

  37. Modified PI • The basic PI does not account for the possible future costs, modified PI attempts to do this:

  38. Modified PI • Same Accept Reject decision as regular PI

  39. Mutually Exclusive • NPV provides the best ranking when comparing between mutually exclusive investments, The rest can produce inconsistent rankings

  40. Example • ProjectInitial CostYR1 CFYR2 CF • A 1,000,000 1,000,000 0 • B 1,200,000 1,119,000 312,000 • C 900,000 195,000 970,000 • D 1,100,000 980,000 345,000 • Compare the different methods for both 7%and 12% (in Class)

  41. Comparison of results

  42. IRR vs. NPV revisited Investment Cost YR 1 IRR A 10,000 12,000 20% B 15,000 17,700 18% NPV@12% NPV@16% A 714 344.82 B 803.50 258.60 NPV@14% 526.31579 for both

  43. On the Graph 2,700 2,000 526.32 14% 18% 20%

  44. Quick Review Method Accept Reject Payback Payback < cutoff Payback>cutoff Disc. Payback Same as Payback NPV NPV > 0 NPV < 0 IRR IRR > WACC IRR < WACC MIRR MIRR >WACC MIRR < WACC PI PI > 1 PI < 1 MPI MPI > 1 MPI < 1

  45. Summary • Use NPV as the first rule • The other criteria can provide secondary information • Which Criteria is most often used by managers?

More Related