CPD Report Mack Surveillance Panel September, 2005

CPD Report Mack Surveillance Panel September, 2005. CPD Report Mack Surveillance Panel September, 2005. T10/T11 Small Turbo (631GC5145M3) 10 on order Mack is working with supplier on cost and timing Possible initial receipt in two weeks; remainder to follow. CPD Report

Télécharger la présentation

CPD Report Mack Surveillance Panel September, 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CPD Report Mack Surveillance Panel September, 2005

  2. CPD Report Mack Surveillance Panel September, 2005 • T10/T11 Small Turbo (631GC5145M3) • 10 on order • Mack is working with supplier on cost and timing • Possible initial receipt in two weeks; remainder to follow

  3. CPD Report Mack Surveillance Panel September, 2005 • T11 Top Rings • Replacement top rings (349GC3107) are being distributed to labs as they are being requested for any T11 kits in lab inventory • All kits are being sold with the 349GC3107 top ring

  4. CPD Report Mack Surveillance Panel September, 2005 • T-12 Hardware • A new set of rings from Batch M and Batch N have been supplied to Mack for analysis • One each of the Batch M and Batch N piston crowns have been supplied to Mack for analysis • Have reviewed dimensional data for each batch and found no major differences

  5. CPD Report Mack Surveillance Panel September, 2005 • T-10 Kits • TEI ordered 50 builds worth of T-10 kits and received less than half • TEI and Mack are working on obtaining more hardware, if needed • What is T-10 need?

  6. CPD Report Mack Surveillance Panel September, 2005 • Batch Coding • A batch is treated as all parts received at the same time. Each batch is given a letter code (A,B,C, etc..) • Date code corresponds with a package date not necessarily a manufacture date • There may be more than one date code within a batch indicating the parts were packaged on different dates

  7. CPD Report Mack Surveillance Panel September, 2005 • Rebuild Kit Serial Numbers • Example: MK12-12001-MJK • MK12 indicates a T12 kit • 12001 is a unique number assigned to each liner kit • M is the cylinder kit batch • J is the rod bearing batch • K is the main bearing batch

  8. CPD Report Mack Surveillance Panel September, 2005 • Rebuild Kit Serial Numbers (continued) • If a date code changes within a batch then a 1 is added. • Example: MK12-12001-MJ1K indicates that the date code for the rod bearing changed • Cylinder kits (liners and rings) are identified by individual numbers (12001, 12002, etc..) • The bearings are supplied with the set number and batch number