110 likes | 205 Vues
ES&H Status of Construction and Technical System Installations. Michael Scharfenstein Project ES&H Coordinator. Subcontracted Work Goals. GC managed Injury rate concern Project responsibility 90 days of field work remaining The goal is Zero future incidents
E N D
ES&H Status of Construction and Technical System Installations Michael Scharfenstein Project ES&H Coordinator
Subcontracted Work Goals • GC managed • Injury rate concern • Project responsibility • 90 days of field work remaining • The goal is Zero future incidents • CF & Technical Systems Installation • Maintaining exemplary safety record • Direct subcontractor management • Detailed work planning
Project-specific ISEMS Implementation • LCLS Directorate Integrated Safety Management Plan • LCLS Work Authorization Procedure • LCLS Project ES&H Plan • Job Safety Analysis • Daily Tailgate Safety Meetings • PM/UTR manages each subcontract • Leads to success • TCCO Project Health and Safety Plan • Job Safety Analysis • Daily Pre-Task Planning Meeting • Pre-Task Checklist • Superintendents assigned geographically
PROJECT SAFETY EXPERIENCEThrough April 2008 DART Rate • Total Project Hours • 1.8 M Hours worked • SubContractors • 484 K Hours worked • DART Rate 3.7 (9 Incidents) • TRC Rate 4.6 (2 Incidents) • LCLS Collaboration • 1,300 K Hours worked • DART Rate 0.3 (2 Incidents) Injury rates based on 200 K hours (100 man years) of effort. DOE/SC Goal is a Reportable Case (TRC) rate of < 0.25 and a Days Away, Restricted, or Transferred (DART) rate < 0.65 per 100 FTEs.
TCCo Stewardship • October ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations • Stand Down of Construction Activities : All Hands Meeting • Review of Work Planning Process for field work – JSA process inadequate • Check/correction of existing documentation • PMT changes • Deficiency Notices • May ’07 thru November ’07 Full Production : Injuries • Multi-day Stand Down of Construction Activities : Corrective Action Plan • Procedural violations transition to injures • Paperwork ineffectively utilized by CM/GC and trade contractors • PE changes • Deficiency Notices & Fines • Communication with Corporate TCCo • Safety Stewardship Committee Established • Full time on-site medic (+30hr OSHA) • UTRs added – focus on safety
TCCo Stewardship cont’d • December ’07 thru April ’08 : Injuries continue • Two incident associated with one sub • PM removed • Work stopped • 90 Days (to the end of field work) • Focus on effective work planning & execution sought • Plan for joint observation developed • Attendance at daily morning work planning meetings • JSA review with workers throughout the day • Identification / monitoring of specific trades or tasks for safe work practices • Must communicate with the worker • The goal is Zero!
CF & Technical Systems Stewardship • Excellent Safety Record • 100K+ hours w/o injury • S20, MMF, Injector, BC 1 & 2 • Issues addressed immediately • Positive Results • Project Managers / UTRs / Installation Managers • Direct management of subcontractors • Communicate ES&H Expectations • Guide them to success • Enforcement when needed • Thorough Work Planning and Control • Aggressive ISM management • Ownership of safety a condition of employment • The goal is to maintain Zero!
Conclusion • Past TCCo safety performance is not acceptable • LCLS providing more prescriptive direction • Past 2 months = acceptable performance • Maintain CF & Technical System direct managed work performance • The goal is Zero!