ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid. N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 09 Jul 2014. 3D-model of the new supply. Existing transfer line TL2. New transfer line TL4. New 10’000 L dewar.

Télécharger la présentation

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS LS1 infrastructure: Installation of a new 10’000 litreLHedewar for the Solenoid N. Delruelleon behalf of the TE/CRG groupLS1 Infrastructure Meeting – 09 Jul 2014

  2. 3D-model of the new supply Existingtransfer line TL2 New transfer line TL4 New 10’000 L dewar Existingtransfer line TL3 to solenoid New valve box Courtesy of Jos Metselaar

  3. New supplyinstalled New 10’000 L dewar New transfer line TL4 (during transport)

  4. New supply installed

  5. Installation & Tests planning • 10% X-rays on weldingsbetweendewar, TL4 and valve box: • Tue 15 July 2014 • Heliumleaktest on dewar, TL4 and valve box: • Thu 17 & Fri 18 July 2014 • Pressure test of the wholesupplybeforeconnection (cutting) to the existing system: • Mon 21 & Tue 22 July 2014 • Outgassing of TL4 & TL5 with hot GN2 (~100 °C) sent from USA15 towards UX15: • FromWed 23 till Tue 29 July 2014

  6. Installation & Tests planning Point of no-return… Thanks for your attention ! • Cutting of the existing TL3 (going to Solenoid control dewar): • From Thu 24 till Thu 31 July 2014 • 100% X-rays on weldingsdone on the existing TL3: • Thu 31 July 2014 • Final tests afterconnection to existing system: • From Mon 04 till Fri 08 Aug 2014