1 / 14

Sustainable Energy Management Options for Totara Bank

Sustainable Energy Management Options for Totara Bank. Project for Master of Technology: MUCER Mandy Armstrong. Project Intent. Provide a decision-support framework for investment in sustainable distributed generation energy systems for a multi-lot development

cecile
Télécharger la présentation

Sustainable Energy Management Options for Totara Bank

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sustainable Energy Management Options for Totara Bank Project for Master of Technology: MUCER Mandy Armstrong

  2. Project Intent • Provide a decision-support framework for investment in sustainable distributed generation energy systems for a multi-lot development • Establish the significant criteria influencing the economic, environmental & social viability of a net-billed system (look beyond ‘payback’) • Identify the best mix of energy-use options, including the impact of energy-efficient house design on system performance

  3. Totara Bank Energy Concept • All lots are designed to make maximum use of solar energy • Coppicing firewood is provided for heating energy. • Building Performance Indexes are specified by floor area to maximise energy efficient design • Each lot is limited to maximum current of 30A & 1 switchboard. • The site is designed with each lot connected to an internal grid, with 1 ICP connecting Totara Bank to the network. • Reconciliation of energy use will be done through Residents Association rules.

  4. Decision Support Framework - Structure

  5. Energy Balance Inputs • Demand data (10min) supplied from Beacon/BRANZ monitoring of an Auckland house (energy efficient) • Climate translation analysis using ALF 3.1 to assess likely heating requirements for the Wairarapa • Assumed morning & evening heating, to a minimum of 15oC; with kWh/day based on calculated AHE’s for May-September • NIWA Cliflo data (hrly) used for radiation & wind supply • Hourly Energy Balances done for February & July only, for one lot. • More fine tuning needed!

  6. Energy Balance - Summer 2.5kW Proven turbine

  7. Energy Balance - Winter Peak Demand: 2.8 kW, 9.30 am! 2.5kW Proven turbine

  8. Data Analysis Considerations • Although a detailed data set has been used, it is only for one house. • Other data sources include HEEP & another Wairarapa house • Considering electricity-based load only; (direct use of gas can reduce electricity demand yet still contribute to total energy demand) • Behaviour assumptions have to be made – as important as appliances & heating. • Peak is lower than expected, but daily use is higher. Why? • Energy Balances then rolled up for 8 lots

  9. Connection Scenarios 1.Radial connection/embedded network • Each lot as individual generators with own grid connection & I-E meters • Baseline scenario (current standard practise) Network Individual Network connections at boundary Flow in both directions I-E I-E I-E I-E Generation area

  10. Connection Scenarios 2.Internal Loop connection • Individual lot generator, single grid connection • Customer network Network connection at boundary I-E Flow in both directions I-E Lot surplus ‘sold’/distributed to other lots as first priority; then exported to network I-E Generation area I-E I-E

  11. Connection Scenarios 3.Internal Loop connection • Whole site as generator, single grid connection • Customer network Network connection at boundary I-E Flow in both directions I-E Lot surplus ‘sold’ to other lots as first priority; then exported to network I-El Generation area - supply connected to each lot I-E I-E

  12. Connection Scenarios 4.Internal Loop connection • Individual lot generator plus whole site generation, single grid connection • Customer network Network connection at boundary I-E Flow in both directions I-E Lot surplus ‘sold’ to other lots as first priority; then exported to network I_E Generation area Supply connected to each lot I-E I-E

  13. Connection Issues • There won’t be much economic benefit from net-billing in the short term if not enough excess energy (unless can somehow supply back at peak times) ref to Anita’s data! • Meter technology is changing rapidly, although NZ is still lagging in use of smart meters: • Lease rather than own • TOU is possible, but not common or encouraged • A customer network also requires data logger system • Interface with the retailer an issue for customer to access data • Data access from TOU meters is the best way to manage load, but will be interesting to achieve... • Current smart meter initiatives focussed on benefits to the retail supply chain

  14. Energy Model Next Steps • Confirm proportion of load to be met by available resources, as well as considering: • How much to invest in PV &/or future generation options? • Is storage desirable for the long-term? • What about genset? What about charging electric cars? • Explore further opportunities to manage demand profile & reduce overall demand • Work on an “ideal” demand profile for future dwellings • Start talking about costs, issues, opportunities etc for the connection scenarios with lines company, meter suppliers, test houses & retailers

More Related