1 / 9

WBS 1.3.2 Tokamak Exhaust Process

WBS 1.3.2 Tokamak Exhaust Process. Donald J. Green / Bernice C. Rogers WBS Manager / Program Manager. November 15, 2006. AGENDA. TEP Scope Flow Outline Key Requirements Schedule. Part of 1/10 th scale TEP. Scope. US ITER-Tokamak Exhaust Process Project.

chen
Télécharger la présentation

WBS 1.3.2 Tokamak Exhaust Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WBS 1.3.2 Tokamak Exhaust Process Donald J. Green / Bernice C. Rogers WBS Manager / Program Manager November 15, 2006

  2. AGENDA • TEP Scope • Flow • Outline • Key Requirements • Schedule Part of 1/10th scale TEP

  3. Scope

  4. US ITER-Tokamak Exhaust Process Project The ITER TEP project provides a technically mature, robust, and cost-effective solution for the separation of hydrogen isotopes from the Tokamak exhaust stream – a critical element in the ITER Project.

  5. Scope of Work • Deliver Tokamak Exhaust Processing System • Flowsheet Refinement (ITER-International Team/SRNL/LANL) • Catalyst Testing/Computer Modeling (LANL/SRNL) • Design (LANL/SRNL/IT) • Fabricate/Procure/Assemble (SRNL) • System Test (LANL/SRNL) • Ship System to Cadarache, France (SRNL) • Overall Project Objective: • Design, Procure, Assemble, Test, & Ship • The Tokamak Exhaust Process Gloveboxes • - Shell and Internals

  6. TEP Process Outline

  7. Key TEP Requirements • Current High Level Specs: • Tritium compatible • Process gas from 450 and 3000 second pulses at a flowrate of 75-150 SLPM • Send < 1 Ci/day to the Atmosphere (Vent) Detritiation System • Overall TEP decontamination factor (DF) of 108 • Delivery to ITER by 3/2014 • Exclude: • Installation, assembly, testing at ITER site • Interface systems, such as control system and gas analysis • Working toward a new baseline in 2007

  8. Planned Procurements • Gloveboxes • Vessels • Vacuum Pumps -Metal Bellows -Scroll -Turbomolecular • Specialty Vessels -Catalyst 1 -Catalyst 2 -Catalyst 3

  9. TEP Overview Schedule

More Related