An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SNS Fast Beam Loss Monitors Final Design Review David M. Gassner SNS Beam Loss Monitor

  2. BLM System Design Features Ion Chambers: • Wide Dynamic Range (IC 6 Decades) (2 dn, 4 up) • Gain adjustment (per channel) • Beam intensities • Detector shielding • Response Time • Ion Chamber • Micro-second response. Data can be available for multi-turn, per cycle, and per second intervals. • Order of 5-10 turns to generate Permit Link Fail(35 KHz BW = 10us) • FBLM, Liquid Cell/ PMT • Fast (ns), within turn loss data • Wide dynamic range • FBLM Test • LED mounted inside Scintillator/PMT assembly • Can be pulsed remotely SNS Beam Loss Monitor

  3. BLM Distribution Total 18 FBLM’s SNS Beam Loss Monitor

  4. HEBT Loss Monitors 169 meters BLM LocationQuantity Quads 37 Collimator 2 Cavities 2 Dump 2 BIG 1 Moveable 8 FBLM LocationQuantity Upstream 1 Bend 1 Dump 1 SNS Beam Loss Monitor

  5. Ring Loss Monitors 248 meter circumference BLM LocationQuantity Quad 44 Injection 7 Collimators 7 RF 5 Extraction 5 Moveable 7 FBLM LocationQuantity Injection 2 Straight Sec. End 4 Bends 4 Extraction 2 SNS Beam Loss Monitor

  6. RTBT Loss Monitors 150 meters BLM LocationQuantity Quads 27 Collimators 4 Dump 2 Target 3 Moveable 4 FBLM LocationQuantity Extraction 1 Collimators 1 Target area 1 SNS Beam Loss Monitor

  7. Liquid Cell/Photo-Multiplier Loss Monitor Detector • Available commercially from Bicron, Model MAB. • BC-505 Liquid (1,2,4 Trimethybenzene) • More Rad hard than plastics, (about 10X’s) • Highest light output of any liquid (80% anthracene) • Excellent light transmission (2.5m, min 1/e attenuation) • High Flash point (48oC, 118oF) • PMT - Hamamatsu 2060, 10 stage. • Sensitivity on order of 100uC/R, Relative to itself. SNS Beam Loss Monitor

  8. Loss Signals • Fast Loss Monitor Applications • Fast instabilities • Kicker errors • Momentum errors • Beam in Gap • Ring wire scanner data • Two Modes • Integrated signal over bunch duration, read out via digitizer clocked revolution frequency. • Losses within bunch. Signals buffered and sent through wideband mux to fast digitizer (1 GS/s). SNS Beam Loss Monitor

  9. FBLM - Liquid Cell & Photo Multiplier SNS Beam Loss Monitor

  10. Data Acquisition & Control Buffer Electronics: • Wideband amp, drives two outputs. Loss Data: • All channels digitized through standard 60 MS/s 14 bit ADC. • Selected channels at 1 GS/s via mux, (Example: LeCroy 374 Scope) • Data transferred to high level via Channel Access. Multiplexer for 1 GS/s: Keithley • 7001 High Density Switch system • 7016A 50 Ohm, Dual 1X4, 2 GHz Mux cards LED Test Pulse • Remote control • Timing HV Bias Control • EPIC’s Driver to ISEG VME based Bias Supply SNS Beam Loss Monitor

  11. HV Bias ISEG HV Bias Supply • VME High Voltage Power Supplies in 2 slot width • 1 channel and 2 channel versions in same dimensions • LCD display for voltage or current • variable rate of change of output voltage • switched polarity • integrated protection and control circuits • output overload and short circuit protected • SHV connector on front side • Full control via VMEbus • EPIC’s drivers • $1.2k/channel • Model VHQ 202M, 0-2kV, 3mA SNS Beam Loss Monitor