1 / 6

Update on the Boston Harbor Project

Update on the Boston Harbor Project. In 1999 , the $3.7 billion construction project is nearly complete, occupying most of Deer Island. Deer Island Wastewater Treatment Facility. BHP: Timeline. July 1985 MWRA created Dec. 1988 Scum discharges ended Dec. 1991 Sludge discharges ended.

chico
Télécharger la présentation

Update on the Boston Harbor Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on the Boston Harbor Project • In 1999, the $3.7 billion construction project is nearly complete, occupying most of Deer Island. Deer Island Wastewater Treatment Facility

  2. BHP: Timeline • July 1985 MWRA created • Dec. 1988 Scum discharges ended • Dec. 1991 Sludge dischargesended Fore River Sludge Pelletizing Facility

  3. BHP: Timeline • Jan 1995 New primary plant online • Dec 1995 Disinfection facilities completed Deer Island Disinfection Facilities under construction

  4. BHP: Timeline • 1997 Battery A: Secondary treatment • 1998 Battery B: Full (1200 MGD) pumping capacity North Main Pump Station

  5. BHP: Timeline • July 1998 Nut Island discharges ceased; South System flows transferred to Deer Island Sewage slick from Nut Island in Quincy Bay, 1985

  6. BHP: Timeline for future • Dec 1999 Secondary Battery C • Mar 2000 New outfall diffuser system start-up

More Related