An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Government of Andhra Pradesh Water Resources Department Welcome to the Hon’ble Chief Minister Sri Nara Chandrababu Naidu Garu

  2. CHINTALAPUDI LIFT IRRIGATION SCHEME Government of Andhra Pradesh Water Resources Department

  3. CHINTALAPUDI LIFT IRRIGATION SCHEME • Introduction • The Chintalapudi Lift irrigation scheme is envisaged for lifting of 53.50 TMC of flood waters from River Godavari in 90 Days and Irrigates 4.80 Lakh acres as below • 2.00Lakh acres in West Godavari District. • 2.10 Lakh acres in Krishna District under NSLMC. • 0.17 Lakh acres under KovvadaKalva Project in West Godavari District • 0.27 Lakh acres under Yerrakalva Project in West Godavari District • 0.24 Lakh acres under Tammileru Project in West Godavari and Krishna • Districts • Storage of 20.00 TMC in JelleruResevoir • Provides Drinking water facilities and Industrial use in enroute villages

  4. Index Map

  5. Basic Scheme of the Project:

  6. CHINTALAPUDI LIFT IRRIGATION SCHEME PROJECT COST SUMMARY :

  7. CHINTALAPUDI LIFT IRRIGATION SCHEME SALIENT FEATURES

  8. CHINTALAPUDI LIFT IRRIGATION SCHEME SALIENT FEATURES ….continued.

  9. CHINTALAPUDI LIFT IRRIGATION SCHEME DETAILS OF EARTH WORK & CONCRETE QUANTITIES

  10. CHINTALAPUDI LIFT IRRIGATION SCHEME PRESENT STATUS OF THE SCHEME (Phase-I): • Package No.1: • Agency : M/s MEIL-Gayatri-ZVS-ITT Consortium, Hyderabad • Agt. Value : Rs.1202.62Cr; Expenditure: Rs.397.908 • STAGE – I : (i) Pump House yet to started. • (ii) 0.66 Km of pressuremain completed out of 2.85Km • Leading Channel : (i)4.25Km completed out of 13.22Km. 4.20Km in progress. • (ii) 1 Structure completed out of 25 Nos. • STAGE – II : (i) Pump House Concrete up to Pump floor level completed and super structure work is in Progress. • (ii) 2.64 Km of Pressuremain completed out of 3.00 Km. • Main Canal : (i) 26.925Km completed out of 36.000.00Km. • (ii) 25 structures completed and 3 structures are in progress out of • 110 Nos. • STAGE – III : (For Jalleru Reservoir) • (i) Pump House foundation work is in Progress • (ii) 0.37 Km of Pressuremain completed out of 1.40 Km. • Package No.2: • Agency : M/s Gayatri Projects Ltd., Hyderabad • Agt. Value : Rs.497.95Cr; Expenditure: Rs.127.088Cr. • Main Canal : (i) 28.875Km completed out of 32.000.00Km. • (ii) 6 structures are in progress out of 84 Nos. • Total Expenditure: Rs.739.398 Cr. (Works: Rs.545.343Cr; Misc: Rs.0.025Cr; Lands: Rs.194.030Cr.)

  11. CHINTALAPUDI LIFT IRRIGATION SCHEME PHASE-II NEW WORKS : • PUMP HOUSE 1A (STAGE-I): • Total No. of Pumps - 10 Nos. • Each Capacity - 9380 H.P • PUMP HOUSE 2A (STAGE-II): • Total No. of Pumps - 10 Nos. • Each Capacity - 26140 H.P • PUMP HOUSE 3A (STAGE-III) for Jelleru Reservoir: • Total No. of Pumps - 4 Nos. • Each Capacity - 5630 H.P • LINK CANAL (from Km.82.150 to Km.95.000): • Total Length - 12.750 Kms. • No. of Structures - 30 Nos • Vempadu Major Head Reach (from Km.95.000 to Km.106.300): • Total Length - 11.300 Kms. • No. of Structures - 19 Nos

  12. Modification Works in CHLIS (Phase-I) • Modification of Leading channel (from Km.0.000 to Km.13.220). • Modification of Main Canal (from Km.0.000 to Km.68.000). • Modification of Tail End Branch Canal (from Km.0.000 to Km.14.150). • Modification of Jelleru Reservoir.

  13. CHINTALAPUDI LIFT IRRIGATION SCHEME LAND ACQUISITION FOR PHASE – I & II