This report outlines the current status of the NuMI upgrades and shutdown, as communicated by Cons Gattuso. Key activities include the completion of the installation for Horns 1 and 2, with pulse testing set for the following week. The power supply testing is also on schedule, along with interlock testing and preparations for thermal scanning. The raw water systems are operational, and major vacuum work on the beamline is completed. The installation of various components, including shielding and RF penetrations, is nearing completion, indicating significant progress ahead of the anticipated reopening of the facility.
E N D
Accelerator and NuMI UpgradesShutdown Update Cons Gattuso June 3, 2013 Cons Gattuso
NuMI Activities • Horn 1 and Horn 2 • Installation is complete • Pulse testing scheduled for next week • Target • Has been installed in the chase • Preparing for power supply testing (next week) • Interlock testing • Pretarget down to target hall • Prepare chase for Horn pulse testing & thermal scan of stripline • Next week, process will take ~3 days • General • Raw water systems • Complete and running: Target, Horn 1, Horn 2, All RAW skids system, exchange systems tested and operations • Completed beamline vacuum work & all ion pumps on. Final survey completed. • Started demobilizing shutdown equipment from Target Hall • Closed up By the 14 of June…. • Installed LBNE Muon Monitor prototype infrastructure in Absorber Passageway
MI/RR Shutdown 2012 • Injection Line Remaining Work: • Magnet installation • Complete • Vacuum system • MI • 100% Complete and under vacuum • Recycler • Q848-100 installed • Leak checked fine • Q100-Q104 • Beam Box installation on new stand complete • Cable termination 100-105 • Powered elements • Cable terminations -95% complete • Instrumentation • Cable terminations -95% complete • Alignment • MI and RR from 848-102 complete • RR from 102 to 105 still left to be done • Installation of components and vacuum system
MI/RR Shutdown 2012 RR-30 straight: • MI primary collimator marble shielding re-installation is complete • Bake is completed downstream of 309. • Bake is completed upstream of 229. • Installing Recycler Ring beam pipe between girders: Approximately 90% complete. • 229 Recycler Kicker spool installed, kickers pumping down. • Replacing corroded MI beam pipe (301-304) • Starting on MI re-assembly at 306 – 308 • Need MI drawings • Reworking multiwire installations to • clear obstructions
MI/RR Shutdown 2012 Still addressing MI corrosion issues in 30 straight section
MI/RR Shutdown 2012 MI 52 Lambertson: Leak checks complete Bake terminated today Blankets off tomorrow followed by the leak check.
MI/RR Shutdown 2012 RR 53 MHz Cavity Installation
MI/RR Shutdown 2012 • RR Bakes: • Bake status ~97% complete • 105-109 Completed 601-607Completed • 125-203 Completed 608-610Completed • 210-219 Completed 620-627Completed • 319-328 Completed 227-229Completed • 335-400 Completed309-311 Completed • 618-620 Completed MI306 Lambertson ( extraction line) • Bake what were added during the shut down • 219-227 Completed, was added due to a component failure • 527 -601 Completed, was added due to MI buss repair • MI521-522 Completed, MI 52 lambertson Flange leak
Shutdown Dose Accumulation Cons Gattuso
MI Radiation Shielding Status • Sight Risers • One of three fabricated • Service Building • LCW – 100 % complete • Power Supply Cabinets 100 % complete • MI-60 • RF Penetrations • Empty RF Penetrations 100 % complete • Rooms 117 &118 Cons Gattuso
Radiation Shielding • Service building power supply/LCW headers 100% complete * • MI-60 • Empty RF penetration 100% complete * • RF Penetrations – installation underway • Sight Risers * • Welding and installing by the end of first week of June • 1 of 3 is welded up and ready for installation • Problem areas • MI60 LCW Penetrations • Waiting on material • Steel to arrive mid June • Poly to arrive late June ( installation ~ 1-2 days) • Power supply Rooms 117 and 118 ( completion aprox. first week of July) • Waiting on designs (poly block) • Est First week of June • Waiting on ploy block • Est first week of July * (required to run low intensity beam) Cons Gattuso
Shielding Types Sight Riser Buss penetrations Room 118 LCW penetrations RF penetrations Room 117 Cons Gattuso
Recycler Shims • Fabrication has started on the RGD shims • Completed sometime middle/late of June • Fabrication of the RGF Shims • Start late June/early July • Completed by the middle July • Tunnel installation could start mid June • Conservative est. Would have them complete installed sometime Mid-End July (WAG) Cons Gattuso
MI/RR Shutdown 2012 Startup activities for last week: • Removed all locks from the MI/RR MCR LOTO box by Friday. • Re-core tunnel to standard tunnel access keys for the weekend. • Safety system tests were successfully completed • Successfully high potted all the MI busses to 1 KV • To many faults were removed to list… • Re-core back to shutdown keys on Monday morning to continue with tunnel installation Startup activities for this week: • Removed all locks from the MI/RR MCR LOTO box by Friday. • Re-core tunnel to standard tunnel access keys for the weekend. • Main Buss Power supply testing through out the weekend • Re-core back to shutdown keys on Monday morning to continue with tunnel installation