1 / 10

LCW Upgrades Update

LCW Upgrades Update. Booster Cavity LCW Isolation Valve Replacement. 8 valves and unions previously replaced An additional 10 valves and unions were replaced during long shut-down. The remaining 20 will be replaced whenever possible - coordinate with cavity rework schedule.

nili
Télécharger la présentation

LCW Upgrades Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCW Upgrades Update • Booster Cavity LCW Isolation Valve Replacement. • 8 valves and unions previously replaced • An additional 10 valves and unions were replaced during long shut-down. The remaining 20 will be replaced whenever possible - coordinate with cavity rework schedule. • All valves and unions are on hand • Remaining Stations: 9, 10, 11, 12, 13, 14, 15, 16, 17, 18 • Booster Bus LCW Strainer and Isolation Valve Replacement. • Remove existing Y-strainers and replace with basket strainers at wall opposite beamline • Strainers at 6 locations have been installed: 1, 3, 6, 7, 13, & 19 • Basket strainer and parts for the remaining 7 locations have been purchased and will be installed when possible. D. Hixson

  2. LCW Upgrades Update Booster Cavity LCW Isolation Valve Replacement Old Valves at 03 & 04 New Valves at 03 & 04 D. Hixson

  3. LCW Upgrades Update Booster Cavity LCW Strainer & Isolation Valve Replacement Old Strainer & Valves at 07 New Strainer and Valves at 07 D. Hixson

  4. LCW Upgrades Update • Finish connection of LCW Return piping in East and West Booster Galleries to LCW Return piping at CUB. • $128,800 Fixed Price Contract plus $9,839 change order for additional work with Voris Mechanical • All work was completed at the end of August • LCW Return Pump at CUB • Remove northern most old, existing return pump, and install previously purchased pump, and relocate valves to allow return pump isolation. • FESS T&M Contract with SEA, ~ $45,000 • Work is in progress and should be complete by Friday? D. Hixson

  5. LCW Upgrades Update LCW Return Pump at CUB Old North LCW Return Pump New Pump – Install in Progress D. Hixson

  6. LCW Upgrades Update • Install LCW Isolation Valves in CUB Utility Tunnel • FESS T&M Contract with SEA ~ $18,000 • Work is complete • EDWA Magnets • Repipe EDWA magnet coils in parallel instead of in series • Work is in progress • Remove LCW Piping for Long 13 New Absorber • Remove sections of 95LCW piping and cap • Remove sections of 55LCW Supply and Return • Work is complete • Some minor adjustment of the vertical alignment of the 95 LCW piping may still be required D. Hixson

  7. LCW Upgrades Update LCW Enclosure Isolation Valves in CUB Utility Tunnel New Valve in LCW Return from Enclosure New Valve in LCW Supply to Enclosure D. Hixson

  8. LCW Upgrades Update Remove LCW Piping for Long 13 New Absorber Removed 55 LCW and Capped 95 LCW Removed 55 LCW and 95 LCW D. Hixson

  9. LCW Upgrades Update • Miscellaneous LCW Work • Magnet bus hose fittings for drainage • Repair Choke leaks and Choke Tubing • Remove Candy Cane Stop-Cocks and plug • Replace Long 3 LCW Hoses • Replace 400 MeV LCW hoses up chute • Install LCW bypasses at return valves in the Galleries • Work above is complete D. Hixson

  10. LCW Upgrades Update • Booster Refill, Leak Testing, Commissioning and Balancing • Booster LCW is in the process of being refilled • Need to do leak checking • Need to do flow and pressure balancing D. Hixson

More Related