Magellan technical updates, Pasadena April 2006 – September 2006
120 likes | 254 Vues
Magellan technical updates, Pasadena April 2006 – September 2006. Instrument Development. Meetings with instrument teams catch interface problems Telescope Guiders Computing Logistics Observatory learns about design, construction, and maintenance requirements. Instrument Development.
Magellan technical updates, Pasadena April 2006 – September 2006
E N D
Presentation Transcript
Magellan technical updates, PasadenaApril 2006 – September 2006
Instrument Development • Meetings with instrument teams catch interface problems • Telescope • Guiders • Computing • Logistics • Observatory learns about design, construction, and maintenance requirements
Instrument Development • PISCO (Parallel Imager for Southern Cosmology Obsv’ns) • Chris Stubbs, Tony Stark, Will High • In design • PFS (Planet Finding Spectrograph) • Paul Butler, Steve Shectman, Jeff Crane • Halfway thorough construction
Instrument Development • MagE (Magellan Echellette) • Scott Burles, Ian Thompson, Steve Shectman • Early construction • FIRE (Folded port Infrared Echellette) • Rob Simcoe, Adam Burgasser • PDR soon
Instrument Development • FourStar (4K IR imager) • Eric Persson, David Murphy, JHU/IDG • CDR soon • Mosaic2 (second CCD dewar for IMACS) • Alan Dressler, Ian Thompson, Pat McCarthy, Alan Uomoto • CCDs ordered; construction starting soon
Instrument Development • WFC (Wide Field Corrector for f/5) • Andy Szentgyorgyi • Construction almost finished
Instrument deployments • MMTF (Maryland-Magellan Tunable Filter) • Sylvain Veilleux, Ben Weiner, Alan Dressler, OCIW engineering • Successful installation and testing • Further engineering this semester • http://www.astro.umd.edu/~bjw/mmtf/
Instrument deployments • POETS (Portable Occultation Eclipse and Transit System) • Jim Elliot, Alycia Weinberger, Mercedes López-Morales, David Osip • Successful speckle tests LLL mode (Weinberger) • Successful photometric transit observations (López-Morales )
F/5 secondary mirror • Mirror is being integrated onto the polishing cell at SOML • Approximate finish date is mid-2007 • Expect 2007B engineering on Clay (baffles, testing)
Guider upgrades • Charlie Hull, Jose Soto • New lead screws for finer position control • Modifications to improve reliability • New motion actuator designs • Better cable routing and strain relief • Testing this year
Bibliography • 186 refereed publications total