This plan outlines the implementation strategy of the HACT framework in Cambodia. Activities include orientation sessions, inventory assessments, and contracting auditors. Timeframe for completion is the end of December 2005 to the 3rd quarter of 2006. Learning resources available on the UNDG website for further guidance and support.
E N D
Roll-out Plan Who By Ex com Reps BL HN TM RC (Ann Lund) Consult UNCT RC funded consultant Activities 1.Extra clause in CPAP 2.UNCT briefing 3.Orientation for RGC and IPs on HACT 4.OMT/Program Orientation Timeframe End Dec05 2nd week 06 By May 06 By May 06 Learning Resources Annex 5 from HACT framework Adaptation of HACT Materials (package 1) Consolidated HACT Package (Package 2) Package 1 + 2
Roll-out Plan (ct.) Who By Consultant Consultant Activities 5. Macro a)Inventory IFI & desk reports b)Bid process to conduct Desk Review+ reporting 6.Micro: Inventory of Ifs. Bid process to contract auditors 7.M & E plan + assurance place Timeframe 3rd Quarter06 3rd Quarter06 Learning Resources UNDG website