90 likes | 167 Vues
CO2 transfer lines on YB0. Review held on the 17 th of April was successful and this project has been endorsed as baseline. Thanks to all of you for this effort ! Committee report outlined a few issues. In particular:
E N D
CO2 transfer lines on YB0 • Review held on the 17th of April was successful and this project has been endorsed as baseline. Thanks to all of you for this effort ! • Committee report outlined a few issues. In particular: • Examining the possibilities of connecting the independent vacuum of the two jacketed lines at the connection box. • It is much preferable if the vacuum jacketed transfer line can be continued into the inside of the vacuum tank. • The currently scheduled windows for verifying design and for installation are too late/short. The Master schedule and coherent placement of order/delivery are to be adapted accordingly in cooperation with TC. …the revision should include reasonable contingency. N.Bacchetta
Connecting vacuum at the intermediate junction box • Seems do-able within the envelope of the present junction box • It will be an option in the new offer from DeMaCo PP1 -6 intermediate junction box N.Bacchetta
Pipes ending inside the vac-tank • Top sectors have no issues. PP1 +5 N.Bacchetta
Vactank surface Vactank surface Vactank surface Vactank surface PP1+5C PP1+6A +5B EB/HB 5/6 Pixel Inlet Cold Dry Gas Inlet Thermal Screen Inlet Thermal screen Outlet PP1 +5 N.Bacchetta
CO2 transfer lines on YB0 PP1 +14C is the most challenging N.Bacchetta
Create a later window for installation of CO2 pipes on YB0- Z+ installation (Dec 6) here Dates from: CMS_LS1_20130410.mpp Before installation of YE-4 seems the best option (a few days staggering with +Z installation window): Skip task “Install 2 sets of CO2 pipes (including supports) on -Z” (no gain) Skip task “YB0- restore vac-tank environment” or partially skip it (gain of up to 2 weeks) Scaffolding from YE-1 removed (currently Dec 6, 2013) Move YBs –Z away from vac-tank (new), (loss of 2 days) Install new CO2 pipes –Z (new), (loss of 5 days) Restore vac-tank environment, (loss of up to 2 weeks) Move YBs –Z on vac-tank and lock (new), (loss of 2 days) At this point back to same sequence as current schedule starting with “Move YE-1-2-3 towards IP”, 3 days 2 weeks total loss
Where we stand • Need to finish the technical specifications (now ready to be circulated) • Need to finalize the end points and specially find a decent solution for PP1 +14 • Agree on a later installation for the –Z end • Once the final offer is received, decide on the vacuum connection at the junction box. • Define/specify the sample piece for welding inspection in order to qualify DeMaCo work. N.Bacchetta
spare N.Bacchetta
What’s in the CMS LS1 schedule today • A window for verifying the 3D model on the vac-tank. June 17 and June 19, 1.5 days per end. • A window for installing the full –Z set of pipes, Aug 12, 5 days including test and certification. • A window for installing the full +Z set of pipes, Dec 10, 5 days including test and certification. NB: above dates are obtained by adding 13 working days to the original dates from Dec. 2012 schedule. Subject to changes. N.Bacchetta