Unit 3. Introduction to Procurement for Public Housing Authorities. Independent Cost Estimates and Cost/Price Analyses. Learning Objectives. Define: Independent Cost Estimate Price Analysis Cost Analysis

davinag
Télécharger la présentation

Introduction to Procurement for Public Housing Authorities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Unit 3 Introduction to Procurement for Public Housing Authorities Independent Cost Estimates and Cost/Price Analyses

  2. Learning Objectives • Define: • Independent Cost Estimate • Price Analysis • Cost Analysis • Understand how to develop an independent cost estimate, price analysis and cost analysis • Understand when/how to use an independent cost estimate, price analysis and cost analysis

  3. 10 Basic Procurement Steps

  4. Independent Cost Estimate (ICE) An ICE is required for each procurement action!* • Estimate of goods/services to be acquired under a contract or a modification • Purposes: • As a yardstick measure in determining price/cost reasonableness • For budgetary purposes • To help determine procurement method • Prepared before solicitation (or modification) • *Generally not necessary for micro purchases (< $2,000) • If significant period of time elapses or market conditions change between time ICE prepared and offers received, may need to update ICE!

  5. Independent Cost Estimate (ICE) An ICE is required for each procurement action! • In developing the ICE, PHAs may use: • Price last paid for similar procurement • Catalog price, or other advertised offers • Comparison of previous bid prices • Personal experience • Other historical information • Detailed analyses • May be developed in-house or using outside parties (or both) • When using outside parties avoid conflicts of interestand ensure the outside party does not obtain a competitive advantage from advance knowledge of the cost estimate

  6. Price Reasonableness • Prior to making an award, a PHA must support the award by documenting that the price/cost for the goods or services is reasonable! • Either a Price or Cost Analysis is always required! • Amount and type of purchase or acquisition determines the degree of analysis • Performed on the apparent low bidder • Usually the force of competition is adequate to allow price reasonableness determination based on simple comparison of offered prices • The ICE developed priorto issuing the solicitation should always be used as a reference • Can help determine need to verify bids or negotiate competitive proposals

  7. Price Analysis Cost Analysis • Simple comparison of prices when competition is adequate • More detailed analysis of component parts when competition is inadequate

  8. Price Analysis • A simple comparison of the pricesquoted by suppliers, contractors, etc., to each other and to the ICE or to other information. • Typically used for Micro or Small Purchases, Sealed Bids and simple Competitive Proposals when only the price paid is the determining factor and “fair” competition is present. • Usually 3 or more offers or quotes is adequate competition • Once the Contracting Officer determines that the prices quoted or offered in response to the solicitation are reasonable, the PHA can award the solicitation to the lowest bidder/offeror.

  9. Price Analysis: Making the comparison • Small Purchase Procedures • Bids to each other • Bids to ICE • Bids to other sources of pricing, including: • Previous purchases, current price lists or catalogs, or ads • For micro purchases, need only compare quotes received

  10. Price Analysis: Making the comparison • Sealed Bids • Bids to ICE (if adequate competition, e.g ., >3 offerors) • If insufficient competition, (e.g., < 3 offerors) use: • Prior historical prices (consider inflation), published catalog prices or current market price, or third-party estimate • Simple Competitive Proposals • Bids to bids • Bids to ICE • If insufficient competition, (e.g, 2 offerors) use: • Prior historical prices (consider inflation), published catalog prices or current market price, or third-party estimate

  11. Cost Analysis • A detailed evaluation of the separate elements that make up the total proposed cost or price • The review and evaluation of each element of cost is to determine its reasonableness, allocability and allowability! • Reasonable per market prices or other data, Allocated proportionally to each category, and Allowed for the contract being sought. • Used mostly for complex Competitive Proposals and for Noncompetitive Proposals

  12. Cost Analysis • Required when… • Price is not the determining factor for the award, • There is no competition in the marketplace, • There is inadequate competition and alternative means cannot be used, • e.g., comparison to prior prices for the same or similar items/services or to competitive price lists/indices or to professional estimate • There is a contract modification that changes the scope and impacts price, or • Prices vary widely (from the ICE) • Once the Contracting Officer determines that the prices quoted or offered in response to the solicitation are reasonable, the PHA can award the solicitation to the lowest bidder/offeror.

  13. 13 Cost Analysis… …For Example Work item: New Roofing • Break down the price into its components of cost • Examine each item of cost • Materials, such as plywood, nails, felt, asphalt shingles; • Equipment, such as cranes, dump truck; and • Labor costs for the size of the job at hand, such as hauling asbestos debris out.

  14. 14 Remember… • An ICE is required for every procurement action prior to solicitation • All awards must be supported by documenting price/cost reasonableness prior to award • Price Analysis • Simple comparison of prices when competition is adequate • Cost Analysis • More detailed analysis of component parts when competition inadequate

  15. References • 24 CFR 85.36(f) • PHA Procurement Handbook7460.8 REV 2 - • Chapter 3.2 • Chapter 10.3