1 / 18

USING MS PROJECT

USING MS PROJECT. M. J. Liberatore DIT 1141. Project management software programs such as Microsoft Project can be used for developing the project schedule We demonstrate the use of MS Project for a sample project Complete model found in construction.mpp. Example Project.

daxia
Télécharger la présentation

USING MS PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. USING MS PROJECT M. J. Liberatore DIT 1141 • Project management software programs such as Microsoft Project can be used for developing the project schedule • We demonstrate the use of MS Project for a sample project • Complete model found in construction.mpp

  2. Example Project • Table 1: Task, Duration, and Immediate Predecessor Information for Construction Project • IMMEDIATE DURATION • TASKDESCRIPTIONPREDECESSORS(WEEKS) • 1 START -- 0 • 2 Excavate and Pour Footers 1 3 • 3 Pour Concrete Foundation 2 1 • 4 Erect Rough Wall & Roof 3 4 • 5 Install Siding 4 6 • 6 Install Plumbing 4 3 • 7 Install Electrical 4 4 • 8 Install Wallboard 6,7 5 • 9 Lay Flooring 8 6 • 10 Do Interior Painting 8 3 • 11 Install Interior Fixtures 9,10 3 • 12 Install Gutters & Downspouts 5 2 • 13 Do Grading & Landscaping 12 3 • 14 FINISH 11,13 0

  3. MS Project Setup • Launch MS Project, click on New, OK • Click on Project, Project Information, select 10/1/01 as the start date, OK • Click on Save icon, type in project name, OK

  4. MS Project Setup

  5. MS Project Setup • Use Tools, Change Working Time, to make necessary adjustments • Tools, Options, click on “Schedule” tab • select “weeks” in Duration is entered in • make sure New tasks are effort driven is not checked • default task type is “fixed duration” • Click Set as Default, OK

  6. MS Project Setup Tools, Options, Schedule

  7. Entering Task Information • Gantt Chart is the default view, Entry table on left, chart on right • Type in task name in the field, tab over to enter duration ( w for weeks) • Enter predecessor task numbers in the “Predecessors” field • Can use link and unlink icons • MS Project automatically gives start and finish dates based on critical path analysis (to be discussed) • The Task Information icon can be used to access information about a particular task

  8. Entering Task Information

  9. Drawing AON Network • 1 0 • 2 3 • 3 1 • 4 • 4 • 6 5 3 6 7 4 • 2 12 5 8 • 10 3 • 6 9 • 3 13 11 3 • 14 0 Construction example

  10. Networks in MS Project • The Gantt Chart view shows task linkages • Change view to Network Diagram by clicking on the icon on the panel on the extreme left • Use “zoom” to focus in as desired

  11. Gantt Charts in MS Project

  12. Summary Tasks In Ms Project 2000 • Summary tasks can be used to better organize a project • Returning to construction.mpp we add three tasks with 0 duration: Structure, Interior, and Exterior • Structure includes current tasks 2 – 4, Interior includes 6 – 11, Exterior includes 5, 12, 13 • The tasks that are included in each of the summary tasks are moved under them and are indented (thick arrow point to the right)

  13. Summary Tasks In Ms Project 2000 • The summary tasks are outdented (thick arrow point to the left) and appear in bold • See constructionS.mpp for the revised project

  14. Summary Tasks In Ms Project 2000 Figure 17.10: Gantt Chart View Using Summary Tasks

  15. Critical Path Analysis • MS Project automatically computes the critical path and the earliest and latest start and finish times and slack • Project, Project Information, Statistics shows the critical path is 26 weeks in our project

  16. Critical Path Analysis

  17. Critical Path Analysis • Critical path tasks can be identified as those have zero total slack(TS) or float • TS = LF – EF = LS – ES • The TS of only 1 task can be used if we want to be certain about not delaying the project • Free slack (FS) of a task is the difference between the smallest of the ES’s of the task’s immediate successors and the task’s EF. • Using FS does not affect the start times of a task’s successors • FS <= TS • FS of of multiple tasks can be used without delaying the project

  18. Critical Path Analysis in MS Project • To display the results just shown in MS Project, in the Gantt Chart view, click Views, select Table: Entry, and click on Schedule

More Related