1 / 13

FAR Subpart 49.4 to 49.607

FAR Subpart 49.4 to 49.607. Termination of Contracts – Part 2. FAR Subpart 49.4 to 49.607. 49.4 Termination for Default 49.5 Contract Termination Clauses 49.6 Contract Termination Forms and Formats. FAR Subpart 49.4 Termination for Default. 49.401 General

Télécharger la présentation

FAR Subpart 49.4 to 49.607

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAR Subpart 49.4 to 49.607 Termination of Contracts – Part 2

  2. FAR Subpart 49.4 to 49.607 • 49.4 Termination for Default • 49.5 Contract Termination Clauses • 49.6 Contract Termination Forms and Formats

  3. FAR Subpart 49.4 Termination for Default • 49.401 General • Termination for default is the Governments contractual right to terminate a contract. • Contracts can be terminated due to contractor’s actual or anticipated failure to perform contractual obligations. • If the contractor can establish that they were not in default of that the failure to perform is excusable, the termination for default will be considered termination for convenience. • Government may exercise termination or cancellation rights in addition to contract clauses in the contract (52.249-8(h)). • The CO may reinstate the terminated contract by amending the notice of termination.

  4. FAR Subpart 49.4 Termination for Default • 49.402 – Termination of FP Contracts for Default • 49.402-1 - The Government’s Right • To terminate the contract completely or partially for default if the contractor fails to make delivery of supplies or services within the time specified, perform an of the provision of the contract, or make progress and that failure endangers the performance of the contract. • 49.402-2 – Effect of Termination for Default • Government is not liable for contractor’s costs on undelivered work • The CO shall not acquire any completed supplies or manufactured materials unless the government has title under some provision in the contract • The Government shall pay the contractor the contract price for completed supplies and manufactured materials. • Government must be protected from potential liability for outstanding lien rights against completed supplies or materials. • The contractor is liable to the Government for any excess costs incurred in acquiring supplies and services, and for any other damages.

  5. FAR Subpart 49.4 Termination for Default • 49.402-3 Procedure for Default • Factors to be considered in determining whether to terminate for default • Terms of contract and applicable laws and regulations. • Specific failure of the contractor and the excuses for the failure. • The availability of supplies or services from other sources. • Urgency of the need for the supplies or services as compared to obtaining from other sources • Degree of essentiality of the contractor in the Government acquisition program. • The effect of the TOD on the ability of the contractor to liquidate guaranteed loans, progress payments, or advance payments. • Any other pertinent facts and circumstances. • Determine which termination action to take – default, convenience, or no-cost cancellation. • If contractor has failed to make delivery of supplies or services within the specified time, no notice of failure or the possibility of termination for default is required before the actual notice of termination. • If contractor fails to perform other provisions of the contract such as furnishing a performance bond, the CO shall give written notice specifying the failure and provide 10 days or a specified period as necessary to cure the failure.

  6. FAR Subpart 49.4 Termination for Default • 49.402-4 – Procedure in Lieu of Termination for Default • Permit the contractor, surety, or guarantor to continue performance under a revised delivery schedule. • Permit the contractor to continue performance by the means of a subcontract or business arrangement with an acceptable third party. • Execute a no-cost termination settlement agreement if the requirement for the supplies and services no longer exist. • 49.402-5 – Memorandum by the Contracting Office • 49.402-6 – Repurchase Against Contractor’s Account • 49.402-7 – Other Damages • 49.402-8 – Reporting Information

  7. FAR Subpart 49.4 Termination for Default • 49.403 – Termination of Cost Reimbursement Contracts for Default • Clause 52.249-6 provides the right to terminate a cost-reimbursement contract. • 10 day notice to the contractor is required • Settlement is subject to Subparts 49.1 and 49.3 except that • Costs in preparing the contractor’s settlement proposal are unallowable; and • The contractor is reimbursed the allowable costs with an appropriate reduction made to the total fee. • Procedures in 49.402 shall be used in considering the TOD of a cost-reimbursement contract.

  8. FAR Subpart 49.4 Termination for Default • 49.404 – Surety-Takeover Agreements • Procedures in this section apply primarily to FP construction contracts. • The CO must consider carefully the surety’s proposals for completing the contract. • The CO should permit the surety to complete the contract unless it is believed they are not competent or qualified or is not in the Government’s best interest. • 49.405 – Completion by Another Contractor • 49.406- Liquidation of Liability

  9. Subpart 49.5 – Contract Termination Clauses • 49.501 – General • Provides the principal contract termination clauses. • Does not apply to contracts using clause 52.213-4 Terms and Conditions – Simplified Acquisitions (Other Than Commercial Items). • 49.502- Termination for Convenience of the Government • 59.249-1 unless 52.249-4 is appropriate for general use in FP contracts not exceeding the simplified acquisition threshold. • 52.249-2 FP contracts exceeding the simplified acquisition threshold. • 52-249-3 FP contracts for Dismantling and Demolition. • 52-249-4 FP contracts for Services Contracts (short form). • 52-29405 FP contracts for Research and Development .

  10. Subpart 49.5 – Contract Termination Clauses • 49.503 – Termination for Convenience of the Government and Default • Clause 52.249-6 Cost Reimbursement Contracts. • Clause 52.249-7 Fixed Price Architect-Engineer. • 49.504 – Termination of FP Contracts for Default • Clause 52.249-8 Supplies and Services • Clause 52.249-9 Research and Development • Clause 52.249-10 Construction • 49.505 – Other Termination Clauses • Clause 52.249-12 Personal Service Contracts • Clause 52.249-14 Excusable Delays

  11. Subpart 49.6 – Contract Termination Forms and Formats • 49.601 – Notice of Termination for Convenience • 49.601-1 – Telegraphic Notice • 49.601-3 – Letter Notice - Notice of Termination to Prime Contractors • 49.602 – Forms for Settlement of Terminated Contracts • 49.602-1 – Termination Settlement Proposal Forms. • 49.602-2 – Inventory Forms. • 49.602-3 – Schedule of Accounting Information. • 49.602-4 – Partial Payments. • 49.602-5 – Settlement Agreement.

  12. Subpart 49.6 – Contract Termination Forms and Formats • 49.603 – Formats for Termination for Convenience Settlement Agreements • 49.603-1 - FP Contracts – Complete Termination. • 49.603-2 – FP Contracts – Partial Termination • 49.603-3 – Cost-Reimbursement Contracts – Complete Termination, if Settlement Includes Costs. • 49.603-4 – Cost-Reimbursement Contracts – Complete Termination, With Settlement Limited to Fee. • 49.603-5 – Cost-Reimbursement Contracts – Partial Termination • 49.603-6 – No-Cost Settlement Agreement – Complete Termination • 49.603-7 – No-Cost Settlement Agreement – Partial Termination • 49.603-8 – FP Contracts – Settlements With Subcontractors Only. • 49.603-9 – Settlement of Reservations

  13. Subpart 49.6 – Contract Termination Forms and Formats • 49.604 – Release of Excess Funds Under Terminated Contracts. • 49.605 – Request to Settle Subcontractor Settlement Proposals. • 49.606 – Granting Subcontract Settlement Authorization. • 49.607 – Delinquency Notices.

More Related