New page for summary of test status. https://espace.cern.ch/mddb/Systems%20Dry%20Run%20Tests/Home.aspx. Dry Run week 19. Pulse injection kickers in point 2 BIS arming and frequency control (linking, starting) through sequencer Trigger BPMs with pre-pulses Prepulse coming 900 ms too late

deacon
Télécharger la présentation

New page for summary of test status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New page for summary of test status • https://espace.cern.ch/mddb/Systems%20Dry%20Run%20Tests/Home.aspx

  2. Dry Run week 19 • Pulse injection kickers in point 2 • BIS arming and frequency control (linking, starting) through sequencer • Trigger BPMs with pre-pulses • Prepulse coming 900 ms too late • New LHC mastership scheme • New mastership scheme: can become master on spare (remove user request) • Logging of transfer lines • Independent of user and extraction time (for PCs) • Solution for power converter logging will be tested next dry run

  3. FGCs – operational settings Slides by Alick

  4. “Dry run” week 21 - cancelled • Extract to TT40 and TT60 • Check mastership: extract under LHC master, re-phasing, check pre-pulse • Verify that cannot have any dynamic destination when under injection test mode • Pulse MKIs (new softstart for MKI 8?) postponed to next week • Run collimators through sequencer this week

  5. Dry run week 22 • BLM online-check • Transfer line logging: new PC logging • BPM triggered by pre-pulses • BCTs – SMP? • Test RF power: • Sequencer tasks, status fixed display, application • Trim + incoorporate • 26th of May: RBAC dry run: • Mode: operational/ non-operational • PIQUET role

  6. Dry run VI June > week 23 • RF low level: • All tasks: • Load actual settings: gains, voltages, frequencies • Load gains, voltages, frequencies • Reset F-rev [before first injection] • Re-phase [before collisions] • All applications ready and settings for operational hyper-cycle available: • RF low level application: status of loops, plus possibility to switch loops • Injection signals fixed displays available • Follow-up issues

  7. Dry run week 26 • MKQA AC-Dipole • All applications: tune, multiturn • Timing events • Interlocking tests (keys,...) • Transverse feedback • Application • Cleaning • Sequencer task • Follow-up issues