Summary status update. SPIRE Consortium meeting La Palma, 1-3 October 2008. Göran L. Pilbratt Herschel Project Scientist, Herschel Science Centre ESA Research and Scientific Support Department (& A.P.Marston). In last few months…. Mechanical testing – acoustics & vibration – completed.

lynley
Télécharger la présentation

Summary status update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary status update SPIRE Consortium meetingLa Palma, 1-3 October 2008 Göran L. PilbrattHerschel Project Scientist, Herschel Science CentreESA Research and Scientific Support Department(& A.P.Marston)

  2. In last few months…. • Mechanical testing – acoustics & vibration – completed

  3. In last few months…. • Mechanical testing – acoustics & vibration – completed • PACS blue bolometer irregularity

  4. PACS bolometer irregularity • PACS blue phot subarrays 5 & 6 • Found after acoustics • Going to shaker delayed for investigations • Open circuit in single address line can explain • Problem in the warm harness! (neither in FPU nor WE) • Connector problems – fixed!

  5. In last few months…. • Mechanical testing – acoustics & vibration – completed • PACS blue bolometer irregularity • Superfluid production and top-up • Took longer than planned • ‘Learning’ how to top-up He-II • Empty HOT • Contaminated helium (dewar) • IST 2 in He-II • Instrument tests in He-II • SFTs, SPTs, EMC • Incl PACS H-field testing => warm harness rerouting on CVV • RMS • Ventline blockage before RMS • SOVT-1 • Directly after RMS, low(ish) helium filling level for SOVT • Short hold times for cooler recycling for both PACS & SPIRE.

  6. Full 5 days of simulated routine-phase operations (6-10 Sept). Simulation dates of 3-7 December. NO safe modes encountered – one failure of FDIR. Full flow of data: AOTs  PSF  MPS POS MOC MTL  S/C (in DTCP)  MOC  HSC (propagation)  ICCs  NHSC DP Pipeline  HSA  Astronomer Retrieval Report now available – second iteration (nearly 300 pages). Includes report sections supplied by all ICCs. SOVT-1

  7. SPIRE PSW large scan map. Level 2 product visualisation.

  8. In last few months…. • He-II top-up after SOVT – went fairly well • Coping with oscillations • Launch autonomy – successfully completed. • Remarks regarding remaining hardware issues • HIFI LOAA heated baffle • Old, new old, new new => new new design being built • Integrated in the last weeks. • Telescope alignment => several measurement campaigns • Final report and TRB couple of weeks ago – aligned! • Also s/c alignment (thrusters, reaction wheels, etc) • PACS H-field • Rerouting of harness on CVV

  9. Schedule – AIV v8.9.3 * Activities to come • Launch autonomy test just finished • Partial warm-upend Sep – end Oct • Helium depletion • Warming to 100 K – OK for air decontamination • Various parallel work to minimize schedule impact, incl. PACS harness re-routing and HIFI LO radiator. • TB/TV test (in LSS) end Oct – mid Dec • IFARs end Oct • SOVT-2 early Jan • FAR early Dec – mid Jan • Transport to Kourou (by air) late Jan • Launch campaign late Jan – early Apr • Launch early Apr

  10. Herschel launch window

  11. Launch • Launch in 2009 from Kourou • Using an Ariane 5 ECA • Shared with Planck • Now in April

  12. Target visibility