Presentation. Hospital Commissioning Case Study. WellStar Paulding Hospital Hiram, Georgia. Rusty Ross, PE, CxA – SSRCx Rick Ziegler, PE – SSRCx Michael Paul - WellStar. The Project. $125 Million Replacement Hospital 295,000 SQFT, Eight Floors

dinh
Télécharger la présentation

Hospital Commissioning Case Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation Hospital Commissioning Case Study WellStar Paulding Hospital Hiram, Georgia Rusty Ross, PE, CxA – SSRCx Rick Ziegler, PE – SSRCx Michael Paul - WellStar

  2. The Project • $125 Million Replacement Hospital • 295,000 SQFT, Eight Floors • 56 beds, expandable to 112 beds (6th & 7th floors shelled) • 40 ER exam rooms • 4 surgical suites • First Patient – March 28, 2014

  3. Commissioning Scope • Review the energy model • Design reviews at 100% DDs and 100% CDs • Cx Specifications

  4. Commissioning Scope • Cx Plan • Shop Drawing Review • Prepare Installation Checklists monitor subs execution of these checklists • Prepare Functional Test Procedures, direct execution, document findings

  5. Commissioning Scope • Review: • T&B report • O&Ms • O&M staff training • Final Report • Opposed Season Testing • Warranty Meeting

  6. Commissioning Scope • Mechanical Systems • Domestic Hot Water • Fire Protection • Fire Alarm • Electrical Distribution • Essential Electrical System (Emergency Power) • Elevators • Lighting Controls • Building Envelope

  7. Mechanical systems • Multistack chiller (1,050 T) uses ground water loop when needed • Full Load testing to be conducted summer 2014 • Primary mode is simultaneous heating and cooling

  8. Mechanical systems • Desiccant AHUs serve Surgery • DOAS units serve multiple AHU systems • Air valves on supply and return in OR systems • 412 Tons of air-cooled Chillers serve DOAS units

  9. Energy Model Review • Energy Star Target Score: 94 • Model not updated for 100% CD design • Walls sections in model don’t match design • Insulation in roof in model different from design • Roof deck design (thickness) ≠ model

  10. Energy Model Review • Thermal resistance of windows over estimated in the model • Sun shade sizing differ between mode and design • DOAS, AHU and exhaust fan power understated in model vs 100% CDs • AHU SAT reset schedule in the EM ≠ the design

  11. Energy Model Review • Energy model over estimates unoccupied operating timeframe, thus under estimating energy usage

  12. 95% CD Plan Review - Mechanical • No detail provided for piping propane (secondary fuel) to steam boilers

  13. 95% CD Plan Review - Mechanical • No conditioned air in main electrical room • Plans did not indicate all isolation valves and flushing connections in Ground Loop system or at the Heat Pump Chiller • No SOO defined for atrium smoke evacuation function • No SOO for VAV boxes in kitchen tracking variable flow in range hood exhaust and dishwasher exhaust

  14. 95% CD Plan Review - Mechanical • Incomplete or missing SOO for stairwell pressurization and elevator shaft smoke vent • Purging and pressure testing procedures for ground loop piping not defined in the specifications

  15. 95% CD Plan Review - Electrical • No lighting controls SOO provided • No lighting controls specification included • Obstruction lighting control not defined, no photocell shown • Initiation of stairwell pressurization not defined • Electrical riser diagram, 4 dry type transformer shown fed from incorrect panels • 13 Panel schedules omitted from drawings • No IR scanning windows in some SWGR

  16. 95% CD Plan Review - Electrical • BOD states emergency generators shall be bi-fuel. Specifications do not require this capability. • “Pole” requirements for shunt trip breakers serving loads under kitchen hoods not identified in panel schedule

  17. Findings – HVAC Hydronics • CHW flow required for AHUs greater that CHW system output. (Strainers were loaded, had to be cleaned 3 times over course of FPTs) • Surgery Unit and AHU-Imaging not able to maintain DAT 55º with CHS @ 42º. (Strainers)

  18. Findings - BAS • OR AHU SAT controlled by 3 factors. Design sequence changed to insure SAT did not rise above desired conditions. • SAT • Dew point control • Temperature reset in unoccupied mode • OR pressure control incorrect (setpoints incorrect) • OR pressure alarms did not alarm when rooms negative (programming) • Critical zone reset for SP setpoint not programmed for Surgery system

  19. Findings - BAS • Surgery AHU Return Air SP safety tripped 5x when in un-occupied mode (added sensors) • DOAS and AHU SP control initially caused tripping of both systems on SP alarms (programming - rate of operation of control dampers) • HWPs and CHWPs did not operate in parallel (ramped individually in series) • Lag HWP and CHWP did not cycle off as load reduced

  20. Findings - BAS • SAT reset based on dew point not programmed • Humidifier not able to control to setpoint (programming) • DOAS filter alarms not programmed • Isolation Room alarms failed to alarm (programming)

  21. Findings - BAS • Isolation exhaust stand-by fan does not start when “lead” fan fails (N+1 programming)

  22. Findings - BAS • Graphics incomplete and/or inaccurate

  23. Findings - BAS • No time of use schedule programmed for boilers (3 total, 1 stand-by) • No communication between FO system and BAS • Sensors defective (MAT) • Domestic Booster pump alarms not programmed • Domestic Hot water alarms not programmed

  24. Findings – Fire Alarm System/ Life Safety • Dry Pipe system annunciation did not identify area protected • Inoperable tamper switches on A/S control valves • Elevator recall programming incorrect

  25. Findings – Lighting Controls • Occupancy sensors not programmed • Occupancy sensors would not time out • Lighting controls not programmed • Sensors blocked by OFE

  26. Findings – Emergency Power • Load Demand control setpoint initially set too low (operated 2 gensets when load required 1) • Day Tank FO return pump did not operate when high level alarm activated (G1) • FO return pump not operable (G2) • Priority Loads and Load Demand functions operated correctly

  27. MEP Lessons Learned • Ready to test • Despite scheduling, not ready to test • Programming incomplete, incorrect setpoints • Conflict between incomplete state and need to finish prior to occupancy • Controls associated with OR AHUs and OR space controls • Restart of AHUs on Emergency Power

  28. Project Timeline

  29. Enclosure Commissioning • Environmental Separation Control insects, rodents, and vermin Control fire Provide strength and rigidity Be durable • Control heat flow • Control airflow • Control vapor flow • Control rain • Control groundwater • Control light and solar radiation • Control noise and vibration

  30. Owner’s Project Requirements • Design life of at least 50 years • No systemic water leaks, all leaks resolved prior to occupancy • Whole building air leakage rate of 0.1 cfm/sf @ 75 Pa • Slight positive pressure • Intent is to have continuous air, water, and thermal protection

  31. Design Phase • Owner’s Project Requirements • Two Design Reviews • Specification Development • Review of Energy Model

  32. Design Phase

  33. Pre-Construction Phase • Submittal and shop drawing reviews • Mock-up construction and testing • Update to functional performance test plan

  34. Mock-up

  35. Mock-up

  36. Mock-up

  37. Mock-up Summary • Water leakage at window collar flashings • Masonry tie air leakage at one location • Whole mock-up air leakage testing pass • Significant air leakage at roof to wall interface • Curtain wall water leaks • Retesting and next steps

  38. Construction Phase

  39. Construction Phase

  40. Construction Phase

  41. Construction Phase

  42. Questions