This document outlines key milestones and evaluations for the MIFS and AHAB projects from April to October 2023. It begins with the initial evaluation of the MIFS breadboard in July, followed by the production delivery, mooring delivery, and deployment tests for AHAB. Additionally, it details the MOBY crossover and subsequent decommissioning of the MOBY system, leading to the operational start of the AHAB on October 3rd. This timeline serves as a concise reference for stakeholders tracking project progress and achievements.
AHAB Milestones
E N D
Presentation Transcript
MIFS breadboard evaluation by 4/07 MIFS prototype final by 12/07 MIFS production delivery 5/08 AHAB mooring delivery 6/08 AHAB test deployments start 8/08 AHAB/MOBY crossover 3/09 to 2/10 MOBY decommissioned 3/10 AHAB operational starting 3/10 AHAB Milestones