An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EUSO SYSTEM STATUS • Introduction • EUSO mass, power and telemetry budgets • Summary of panels recommendations and priority list to tackle the issues till February • Conclusions, plans and deadlines O. Catalano- EUSO IM General meeting-Munich 17-20 November

  2. Introduction • Report on the System status based exclusively on the scientific-technological aspects of the present System configuration, i.e. “baseline CEPF accommodation”. • taking into account the Phase A final review panels (Science- Instrument and MSM-Payload) conclusions and recommendations of the 30-31 October (details by Livio and Andrea) • Attempt to identify the major issues and System criticality to be fulfilled by the end of February 2004 • Reports on subsystem status in the afternoon General meeting-Munich 17-20 November

  3. Mass, Power & Telemetry budget MPT Resources budget (COLUMBUS) (IRD) MPT Required budget (SYSTEM) (IIDD) 4 Instrument-Payload I/F meetings ++… MPT Allocated budget (IRD-IIDD) = I/F meeting between EUSO P/L and Instrument appointed on 9-10 December in Palermo General meeting-Munich 17-20 November

  4. Mass, Power & Telemetry budget • Phase AMPT allocation: “baseline CEPF accommodation” • Mass • Mass on Orbit:1500 kg (including 1170 kg Instrument) • Mass at launch: 2500 kg • Power • operations: 750 W (including 670W Instrument) • non - operations:150 W (including 80W Instrument) • Telemetry • 100 kbits/s (1553 bus and LAN) General meeting-Munich 17-20 November

  5. Instrument MPT breakdown IMPORTANT!!!!! With current MPT allocation: FOV =  25°  Mass Observational duty cycle = 18%  Power Telemetry limitation ? General meeting-Munich 17-20 November

  6. Summary and priority actions list General meeting-Munich 17-20 November

  7. Conclusions, plan and deadline • It is compulsory close by the end of February the open actions • Adopt the priority actions list to define plan and deadline to be finalized during this meeting with the contribution and collaboration of everyone General meeting-Munich 17-20 November

  8. General meeting-Munich 17-20 November

  9. General meeting-Munich 17-20 November