660 likes | 804 Vues
Garnet Mine Area Reclamation Project Final Engineering Evaluation/Cost Analysis Public Meeting – March 3, 2010. Montana Department of Environmental Quality Mine Waste Cleanup Bureau. Project Location.
E N D
Garnet Mine Area Reclamation ProjectFinal Engineering Evaluation/Cost AnalysisPublic Meeting – March 3, 2010 Montana Department of Environmental Quality Mine Waste Cleanup Bureau
Project Location • Located approximately 2.5 miles southwest of Pony, Montana in the Mineral Hill (Pony) Mining District of Madison County. Pony Garnet Mine
Mining History • Mining • Garnet Mine began underground operations mining gold, silver, copper and lead in the late 1800s. • Most production occurred between 1897 and 1909 and continued intermittently through the 1930s. • Milling • Initial milling was conducted using a 20-stamp amalgamation mill. • Later used conventional floatation mill and tailings facility to produce concentrate for shipping. • Production Estimate – • 175,000 tons of ore
Garnet Area Mine Features • Adits, some caved • Waste Rock Piles • Shafts and Collapsed Stopes • Valley Fill Tailings • Other Hazardous and Non-Hazardous Materials from Past Mining and Milling
Oriole Adit Portal (F-7) with Seepage Flow 2.2 – 7.1 gpm
Purpose and Objectives Purpose – Prepare a functional guide for conducting reclamation activities that to the extent possible mitigate human health and environmental risks. Objectives – To screen, develop and evaluate potential response alternatives that would be used to clean up site mine waste.
Waste Rock Characteristics Mine Waste Rock Investigation • Acid-Base Accounting (ABA) – determine potential to generate acidic leachate • Metal Mobility – evaluate potential to release metals in concentrations exceeding DEQ surface water standards • Volume Survey – determine total volume of each waste pile
Waste Rock Characteristics - Acid-Base Accounting ABA Results Summary • Uncertain acid generation potential indicated by NNP (values between +20 and -20 CaCo3/kiloton of rock) • 3 Samples have somewhat greater potential to generate acid based on NP:AP (values below 1)
Waste Rock Characteristics – Metal Mobility Summary Metal Mobility Summary • All six waste rock samples exceeded DEQ-7 acute aquatic life, chronic aquatic life, and/or human health standards for surface water for at least one metal. • Pb was most common metal detected constituent • Cu exceeded acute aquatic life standards in five of six samples • Standards for As, Cd, Hg, or Zn were exceeded in three or fewer samples
Tailings Characteristics Floodplain Tailings Investigation • Test pits were excavated throughout the tailings deposit • Excavated test pits were sampled at 1ft. Intervals below ground surface • Samples were analyzed using and X-ray Fluorescence (XRF) instrument and compared to background soil samples
Eroded Tailings Dam – Cascade Creek Assumed Original Top of Dam Estimated Height 8’-10’
Oriole Adit Portal (F-7) with Seepage Flow 2.2 – 7.1 gpm
Oriole Adit Workings (1,095 feet) Malachite (Cu) precipitate from Jackleg Drill Holes
Oriole Adit Plan Map Oriole Adit Seepage Flow 2.2 – 7.1 gpm
Human Health Recreational Use Risk Assessment No Human Health affects from tailings, waste rock or surface water (excluding the Oriole Adit seepage) for any of the following recreational uses • Soil Ingestion • Dust inhalation • Water Ingestion • Fish Ingestion
Development and Screening or Reclamation Alternatives Purpose – Identify and screen technology types and process options • Eliminate technologies that are obviously unfeasible or ineffective • Retain potentially effective options General Response Actions • No Action – no further response or monitoring • Institutional Controls – restrict or control access • Engineering Controls –reduce or eliminate the contaminant • Excavation and Treatment – removal and subsequent treatment of contaminant • In-Situ Treatment – treat in place, reducing mobility and toxicity of contaminant
No Action • No Action is generally used as a baseline against which other response options are compared
Institutional Controls • Land use restrictions would limit the possible future uses of the land at the site • Mine portal closures • Fencing and gates • Area closures • Institutional Controls do not meet clean-up goal • Does not address long term public safety
Engineering Controls Engineering Controls typically include containment, capping, run-on/run-off controls, revegetation and/or disposal • Underground Flow Control – eliminate, minimize, or divert contaminated water flows for entering or leaving underground mine workings • Containment – eliminate direct contact and fugitive releases of contaminated materials • Surface Controls – minimize contaminate release and migration • On-Site Disposal – placement of contaminate in an engineered on-site repository • Off-Site Disposal – transporting contaminate to an engineered off-site repository permitted to accept such materials
Excavation and Treatment Excavation and Treatment involves the removal of the contaminated materials and subsequent treatment to reduce toxicity and/or volume • Reprocessing– transporting contaminate to existing mill or smelter for processing and recovery of valuable metals • Fixation/Stabilization – chemically alter the contaminant to reduce its mobility or toxicity or encapsulating contaminant in inert material • Physical/Chemical Treatment – use of physical chemical processes to concentrate constituents into a smaller volume for disposal or further treatment
In-Situ Treatment In-Situ Treatment involves treating contaminate in place with the objective of reducing mobility and toxicity of problem constituents. • Physical/Chemical Treatment – used to create a chemical or physical change in the mobility and/or toxicity of the contaminants • Thermal Treatment – used to melt contaminated solid media in place to immobilize metals into a glass-like, inert, non-leachable solid matrix
Detailed Analysis of Alternatives Response Action Alternative Evaluation 1. Effectiveness 2. Implementability 3. Cost
Detailed Analysis of Alternatives Effectiveness – • Overall protection of human health and the environment • Compliance with the ARARs • Long-tem effectiveness and performance • Reduction of toxicity, mobility, or volume through treatment • Short-term effectiveness
Detailed Analysis of Alternatives Implementability – • Address the technical and administrative feasibility of implementing an alternative and the availability of various services and materials required to accomplish its implementation.
Detailed Analysis of Alternatives Cost – • Developing conservative cost estimates based on the materials needed and the construction elements associated with implementing the alternative. • Cost do not necessarily represent the cost the may actually be incurred because many design details are preliminary at this stage.