1 / 11

Safety and Database Subsection ADO - PO - SA Safety achievement and future activities

Safety and Database Subsection ADO - PO - SA Safety achievement and future activities Database (see K. Pommes talk) 08.09.2009 , O. Beltramello. Recent achievement We are ready for 2009 LHC HW and Operation commissioning tests and for the 2009 LHC Run period

elata
Télécharger la présentation

Safety and Database Subsection ADO - PO - SA Safety achievement and future activities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Safety and Database Subsection ADO - PO - SA • Safety achievement and future activities • Database (see K. Pommes talk) • 08.09.2009 , O. Beltramello

  2. Recent achievement We are ready for 2009 LHC HW and Operation commissioning tests and for the 2009 LHC Run period • All safety systems have been maintained / upgraded and are receptionned • LACS/LASS and SSA (Systeme de surete ATLAS) have been upgraded and are ready for operation • FPIAA project (Sofia, Nuno, Xavier) • Phase 2 installation has been completed: sensors coverage extended now to the forward trenches, the Big Wheels gangways and the Open Configuration scaffolding zones

  3. Recent achievement • ATLAS cavern protection campaign against accidental He release in the LHC machineis finished(Nuno, Dimi, Raphael) • Q1, Q2 survey holes have been protected and sealed: • 110 mbars pressure resistant, special cut outs for survey equipment, ALARA principle respected

  4. Recent achievement • Survey galleries end of zone doors and walls have been redesigned: fire resistant, 110 mbars pressure resistant, sealed, with special cut out for the survey equipment , ALARA principle respected • A protection of the TAS area has been • designed and installed : • 110 mbars pressure resistant, ALARA • principle respected, sealed

  5. Recent achievement • US15 / UX15 end of zone doors have been changed to be fire resistant and 110 mbars pressure resistant and sealed. • All ventilation doors are monitored and • connected to LACS and LASS • The US15/UX15 and USA15/UX15 • holes have been sealed

  6. Recent achievement • ATLAS Pressure sensors installation (Fernando, Jan) • In collaboration with EN-CV, additional pressure pipes and sensors have been installed to monitor the overpressure between the caverns UX15, US15, USA15 and the tunnel sectors. • The overpressures will be monitored and and controlled at SLIMOS desk to identify a possible RP • Water leak detection system in racks is installed (Fernando, Charles)

  7. Recent achievement • Gate monitors at UX15 entrance and at SDX1 Buffer zone entranceinstalled and operational at SLIMOS desk (Serguei, Tatiana)

  8. Future development and activities • AL3 alarms safety system need under investigation • This system will be required to implement the ATLAS safety matrixes in a compatible way with RP requirements • (especially different ventilation matrix in case of UX15 Closed or Open mode) • Overpressure test campaign in collaboration with EN-CV group • Planned end of September to control that the overpressure requirements between the tunnel , US15 service cavern, UX15 cavern and USA15 service area are met. • Final ID CO2 test campaign with the shafts closed and ventilation in LHC run mode (air recycling).

  9. Future development and activities • FPIAA project upgrade : • Replacement of the sensors supports and sensors connectivity to minimize the replacement and disconnecting time (ALARA) • Creation of the Surface Radioactive Buffer Zone • To be ready for the 2010 Shutdown period • SLIMOS desk improvement • Patrols : Patrollers training and shifts start up • General ATLAS training to be revised • Configuration control / seismic analyses

  10. Future development and activities • ALARA activities : • Analysis of the ATLAS closure activities is on going • Analysis of the specific activities for the coming shutdown period • Development of a strategy and procedures to control all ALARA aspects for the persons and per activity, development of the associated personnel database. • Augmented reality project : • A pilot project is run to evaluate a tool to minimize the time of intervention for specific maintenance in highest radioactive regions of the detector

  11. Future development and activities • ALARA activities : • Contact with specific companies specialized in maintenance in radioactive environment for specific interventions • Participation to the upgrade activities (IBL, Lar,..) • Participation and follow up of the Radioactive WS creation at CERN • An ALARA Work Shop will be run in October

More Related